Date |
Text |
2022-12-08 17:47:54 | RESIDENTIAL(R3) ADDITION/ALTERATION THIRD BUILDING |
| REVIEW COMMENTS |
| CODE: FBC 7TH EDITION (2020) AND CITY AMENDMENTS. |
| PERMIT #22050916 |
| 372 FOREST HILL BLVD |
| |
| ARCHITECTS-ENGINEERS |
| FLORIDA STATUTE 553.80(2)(B): |
| ARCHITECTS WITH RESPECT TO EVALUATION OF DESIGN |
| PROFESSIONALS DOCUMENTS, IF A LOCAL GOVERNMENT FINDS IT |
| NECESSARY, IN ORDER TO ENFORCE COMPLIANCE WITH THE |
| FLORIDA BUILDING CODE AND ISSUE A PERMIT, TO REJECT |
| DESIGN DOCUMENTS REQUIRED BY THE CODE THREE OR MORE |
| TIMES FOR FAILURE TO CORRECT A CODE VIOLATION |
| SPECIFICALLY AND CONTINUOUSLY NOTED IN EACH REJECTION, |
| INCLUDING, BUT NOT LIMITED TO, EGRESS, FIRE PROTECTION, |
| STRUCTURAL STABILITY, ENERGY, ACCESSIBILITY, LIGHTING, |
| VENTILATION, ELECTRICAL, MECHANICAL, PLUMBING, AND GAS |
| SYSTEMS, OR OTHER REQUIREMENTS IDENTIFIED BY RULE OF |
| THE FLORIDA BUILDING COMMISSION ADOPTED PURSUANT TO |
| CHAPTER 120, THE LOCAL GOVERNMENT SHALL IMPOSE, EACH |
| TIME AFTER THE THIRD SUCH REVIEW THE PLANS ARE REJECTED |
| FOR THAT CODE VIOLATION, A FEE OF FOUR TIMES THE AMOUNT |
| OF THE PROPORTION OF THE PERMIT FEE ATTRIBUTED TO PLANS |
| REVIEW |
| |
| |
| PREVIOUS RESPONSE COMMENT: |
| 1- BASED ON DRAWINGS SUBMITTED, 12" DEEP FOOTINGS DON'T |
| PROVIDE 12" MINIMUM FOOTING DEPTH. SEE SECTION 1 ON |
| SHEET S-200. ALSO, ENGINEER AND ARCHITECT OF RECORD |
| NEED TO COORDINATE PLANS TO SHOW COMPLIANCE WITH THE |
| MINIMUM FOOTING DEPTH AND CLEARANCE FOR TERMITE |
| INSPECTION AS REQUIRED BY SEC. R403.1.4 FBC-RESIDENTIAL |
| AND SEC. R318.7 FBC-RESIDENTIAL. |
| ALSO, ARCHITECT AND ENGINEER NEED TO COORDINATE TYPE OF |
| FOOTING. ARCHITECT SHOWS A DIFFERENT FOOTING TYPE ON |
| SHEET A1-4.2. |
| |
| NEW RESPONSE TO ENGINEERS LETTER DATED OCTOBER 22, |
| 2022: |
| ENGINEER'S RESPONSE LETTER STATES: "SECTION R403.1.4 |
| APPLIES TO ISOLATED AND STRIP FOOTINGS. THIS IS A |
| MONOLITHIC FOOTING." |
| THIS IS INCORRECT. SECTION R403.1.4 APPLIES TO "ALL |
| EXTERIOR FOOTINGS". THERE ARE NO EXCEPTIONS. SEE |
| SECTION R403.1.4 AND REVISE ALL DETAILS AND |
| SPECIFICATIONS AS REQUIRED. |
| ALSO, PROVIDE DETAIL/SPECIFICATIONS SHOWING COMPLIANCE |
| WITH THE MINIMUM FOOTING DEPTH AND CLEARANCE FOR |
| TERMITE INSPECTION AS REQUIRED BY SEC. R403.1.4 |
| FBC-RESIDENTIAL AND SEC. R318.7 FBC-RESIDENTIAL. |
| |
| |
| ORIGINAL COMMENT: |
| 9- BUILDING THERMAL ENVELOPE. DESIGNER OF RECORD NEEDS |
| TO DEPICT THE BUILDING THERMAL ENVELOPE. NEED TO |
| SPECIFY INSULATION MATERIALS AND THEIR R-VALUES.(ROOF, |
| WALLS, RAISED FLOOR ABOVE GARAGE, ETC.) AS REQUIRED BY |
| SEC. R103.2 FBC-ENERGY CONSERVATION. |
| NOTE: KEEP IN MIND THERE ARE FLAT ROOFS AND PITCHED |
| ROOFS. AND, COORDINATE WITH ENERGY CALCULATIONS TO |
| AVOID CONFLICTS/DELAYS. |
| |
| RESPONSE: |
| PROPOSED SECTION 01/A1-4.3 ON SHEET A1-4.3 SHOWS |
| ICYNENE INSULATION IN THE PITCHED AND FLAT ROOF AREAS. |
| IT LOOKS LIKE ARCHITECT IS DESIGNING AN UNVENTED ATTIC. |
| IF SPECIFYING UNVENTED ATTIC THEN ARCHITECT TO CLARIFY |
| WHY SPECIFYING ROOF ATTIC VENTILATION ON DETAIL |
| 03/A1-4.3 AND DETAIL 04/A1-4.3 ON THE SAME SHEET? |
| PROVIDE ICYNENE INSULATION ICC EVALUATION REPORT. |
| ARCHITECT TO REVIEW AND APPROVE EVALUATION REPORT PRIOR |
| TO SUBMITTAL. (NOTE: THIS REPORT MAY BE SUBMITTED LATER |
| AFTER THE PERMIT IS ISSUED BUT BEFORE INSTALLATION) |
| |
| NOTE: THERE IS A CONFLICT WITH SUBMITTED REVISED |
| DRAWINGS. IT LOOKS LIKE THE NUMBER OF THE DRAWINGS WERE |
| REVISED BY THE ARCHITECT. FOR EXAMPLE ORIGINAL PROPOSED |
| ELEVATIONS WAS DRAWING A1-4.1. REVISED PROPOSED |
| ELEVATIONS DRAWING NUMBER WAS CHANGED TO DRAWING |
| A1-4.2. THIS CREATES A CONFLICT BECAUSE THE PREVIOUS |
| PROPOSED ELEVATIONS DRAWING WAS VERSIONED WITH THE |
| REVISED PROPOSED ELEVATIONS. NOW THE FILE NAME DOESN'T |
| MATCH THE REVISED DRAWING NUMBER. |
| NEED TO COORDINATE WITH THE PERMIT LIBRARIAN TO GET THE |
| CORRECT FILE NAME AND DRAWING NUMBER. |
| THIS APPLIES TO FILE #008 ALSO. THE FILE NAME AND THE |
| DRAWING NUMBER DON'T MATCH). COORDINATE FILE #007, #008 |
| AND #009 TO MATCH FILE NAME AND DRAWING NUMBER. |
| |
| ORIGINAL COMMENT: |
| 10- ROOF WITH LESS THAN 6" EAVES REQUIRES GUTTERS WITH |
| DOWNSPOUTS AS REQUIRED BY SEC. R318.5 FBC-RESIDENTIAL. |
| SPECIFY GUTTERS ON PLANS. PROVIDE DETAILS AND |
| SPECIFICATIONS, INCLUDING TERMINATION OF DOWNSPOUTS. |
| |
| RESPONSE: |
| REVISE PROPOSED ROOF PLAN (SHEET A1-4.1). THERE IS A |
| FLAT ROOF (REAR AND FRONT AREAS). NEED TO SPECIFY |
| SCUPPERS AT THE PERIMETER OF THE ROOF WHERE THE EAVE IS |
| LESS THAN 6". THE ONLY EXCEPTION WHERE GUTTER IS NOT |
| REQUIRED IS FOR GABLE ROOFS. |
| |
| ORIGINAL COMMENT: |
| 12- DESIGNER OF RECORD OF RECORD TO SPECIFY ROOF |
| VENTILATION AS REQUIRED BY SEC. R806 FBC-RESIDENTIAL. |
| SPECIFY VENT SIZE AND LOCATION. |
| NOTE: THERE ARE FLAT AND PITCHED ROOFS. IF DESIGNING |
| UNVENTED ATTICS, THEN SPECIFY HOW COMPLYING WITH SEC. |
| R806.5 FBC-RESIDENTIAL. |
| |
| RESPONSE: |
| RESPONSE LETTER STATES: "PLEASE SEE REVISED SHEET |
| A1-4.1 INDICATING ROOF PITCH". |
| THIS IS INCORRECT. THE REQUEST WAS TO SPECIFY ROOF |
| VENTILATION NOT ROOF PITCH. READ SEC. R806 |
| FBC-RESIDENTIAL AND PROVIDE THE REQUIRED INFORMATION |
| FOR CROSS VENTILATION FOR ALL ROOF AREAS. (SEE NOTE ON |
| ITEM #12 ABOVE. ALSO, COORDINATE WITH ITEM #9 ABOVE). |
| |
| 13- DEFERRED SUBMITTAL: PRODUCT APPROVALS (NOTE: |
| PROVIDE COMPLETE INFORMATION FOR REVIEW AFTER PERMIT |
| ISSUANCE BUT PRIOR TO INSTALLATION TO AVOID |
| CONFLICTS/DELAYS. ALL PRODUCT APPROVALS NEED TO BE |
| APPROVED IN WRITING BY DESIGNER OF RECORD PRIOR TO |
| SUBMITTAL: |
| A)FLAT ROOF. AND, CLEARLY MARK WHICH APPROVED ASSEMBLY |
| IS GOING TO BE INSTALLED TO VERIFY COMPLIANCE WITH THE |
| DESIGN PRESSURES OF SEC. R301.1 FBC-RESIDENTIAL. |
| NOTE: IF THE SELECTED ASSEMBLY DOESN'T MEET THE DESIGN |
| PRESSURES FOR ALL ROOF ZONES, THEN SIGNED AND SEALED |
| RAS 117 CALCULATIONS ARE REQUIRED. |
| |
| D)INSWING ENTRY DOOR AS SHOWN ON PLANS. (NOTE: FLOOR |
| PLAN ON SHEET A1-4. WAS CHANGED SHOWING AN OUTSWING |
| DOOR BUT PROPOSED WINDOWS & DOORS FLOOR PLAN ON SHEET |
| A1-4.3 WAS NOT REVISED. NEED TO REVISE BOTH PLANS TO |
| MATCH AVOID CONFLICTS/DELAYS). |
| |
| E)HORIZONTAL SLIDING WINDOWS. |
| F)FIXED WINDOWS. |
| G) REAR SWING DOOR. |
| H)SLIDING GLASS DOOR. |
| |
| 14- DESIGNER OF RECORD TO REVIEW AND APPROVE IN WRITING |
| (NOT SIGNING AND SEALING) ABOVE PRODUCT APPROVALS AS |
| REQUIRED BY SEC. 107.3.4.1 CITY AMENDMENTS. |
| |
| ORIGINAL COMMENT: |
| 15- BEDROOM #3 WINDOW W-11: PROVIDE MANUFACTURER'S |
| SPEC'S SHOWING COMPLIANCE WITH THE EGRESS REQUIREMENTS |
| OF SEC. R310.2.1 FBC-RESIDENTIAL. NEED TO VERIFY CLEAR |
| WIDTH OPENING ON SPECIFIED SIZE WITH 4 PANELS. |
| |
| RESPONSE: |
| RESPONSE LETTER STATES "WINDOW TO BE REPLACED WITH |
| 3-EQUAL SIZE PANELS". |
| WINDOW SCHEDULE WAS NOT REVISED TO REFLECT THIS CHANCE. |
| ALSO, ARCHITECT'S RESPONSE LETTER IS REFERENCING SEC. |
| R310.2.5 REPLACEMENT WINDOWS. BEDROOM #3 NEEDS TO |
| COMPLY WITH THE EMERGENCY EGRESS REQUIREMENTS, |
| ACCORDING TO CITY RECORDS, THIS ROOM IS A CHANGE OF |
| OCCUPANCY. THIS ROOM WAS EITHER A GARAGE OR CARPORT AND |
| THERE ARE NO CITY RECORDS FOR THE CONVERSION OF THIS |
| ROOM TO LIVABLE AREA. |
| |
| 17- REVISE ENERGY CALCULATIONS SUBMITTED: |
| |
| A) |
| |
| ORIGINAL COMMENT: |
| B)CEILING INFORMATION NEED TO BE COORDINATED WITH ITEM |
| #9 ABOVE. PLANS NEED TO SHOW THE THERMAL ENVELOPE AND |
| SPECIFY IF DESIGNING VENTED OR UNVENTED ATTICS. NOTE: |
| THERE ARE SOME FLAT ROOFS IN THIS PROJECT THAT NEED TO |
| BE CONSIDERED ALSO. SEC. R101.5.1.1.2 FBC- ENERGY |
| CONSERVATION. |
| |
| RESPONSE: |
| THIS NEEDS TO BE COORDINATED WITH THE DESIGNER OF |
| RECORD TO AVOID MORE CONFLICTS/DELAYS. ARCHITECT OF |
| RECORD IS SPECIFYING ICYNENE ATTIC INSULATION. IT LOOKS |
| LIKE ARCHITECT IS DESIGNING UNVENTED ATTICS. ITEM |
| #11(B) SPECIFIES A VENTED ATTIC. REVISE AS REQUIRED TO |
| MATCH PLANS. COORDINATE WITH ITEM #9 ABOVE. |
| |
| C) |
| |
| ORIGINAL COMMENT: |
| D) REVISE ATTIC INFORMATION ON PAGE 3. COORDINATE WITH |
| ITEM (B) ABOVE. |
| SEC. R101.5.1.1.2 FBC- ENERGY CONSERVATION. |
| NOTE: TYPICALLY THE VENT RATIO (WHEN PROVIDED) IS AT |
| LEAST 1/150. |
| IF ENGINEER PREPARING THE ENERGY CALCULATIONS WANTS TO |
| USE 1/300 VENT RATIO, THEN NEED TO PROVIDE COMPLETE |
| DETAILS AND SPECIFICATIONS SHOWING COMPLIANCE WITH THIS |
| RATIO. SEC. 107.2.1.2 CITY AMENDMENTS. |
| |
| RESPONSE: |
| REPEAT COMMENT. NOT REVISED. |
| NOTE: COORDINATE WITH ITEM #17(B) ABOVE. |
| |
| WHEN RESUBMITTING, A TRANSMITTAL LETTER LISTING THE |
| ORIGINAL REVIEW COMMENT WITH A DESCRIPTION OF WHERE AND |
| HOW THE COMMENT WAS ADDRESSED WILL HELP TO EXPEDITE THE |
| REVIEW PROCESS. THANK YOU FOR YOUR ANTICIPATED |
| COOPERATION. |
| |
| PLEASE FEEL FREE TO CONTACT ME IF YOU HAVE ANY |
| QUESTIONS REGARDING THESE COMMENTS, |
| JULIO GOMEZ |
| COMMERCIAL COMBINATION PLANS EXAMINER |
| DEVELOPMENT SERVICES DEPARTMENT |
| BUILDING DIVISION |
| (561)805-6712 |
| [email protected] |