Date |
Text |
2022-06-30 14:31:38 | RESIDENTIAL (R3) ADDITION SECOND BUILDING REVIEW |
| COMMENTS |
| CODE: FBC 7TH EDITION (2020) AND CITY AMENDMENTS. |
| PERMIT #22010026 |
| |
| |
| |
| NOTE: |
| ***REVISED DRAWING A-2 WAS NOT DIGITALLLY SIGNED AND |
| SEALED BY THE ARCHTECT. DRAWING NEEDS TO BE SIGNED AND |
| SEALED. |
| |
| |
| |
| |
| NOTE: |
| BUILDING REVIEW MAY BE APPROVED WITH PROVISO. PROVISO |
| MEANS CONTRACTOR WILL SUBMIT REQUIRED INFORMATION AFTER |
| THE PERMIT IS ISSUED BUT BEFORE INSPECTIONS TO AVOID |
| CONFLICTS/DELAYS. REVISION FEES MAY APPLY. CONTRACTOR |
| TO ADVICE IF PROVISO OPTION IS PREFERRED AT THIS TIME |
| OR IF RE-SUBMITTING REQUIRED INFORMATION BEFORE PERMIT |
| ISSUANCE. |
| |
| |
| |
| |
| ORIGINAL COMMENT: |
| 1-THIS BUILDING IS GOING TO BE BUILT IN A AE FLOOD ZONE |
| WITH THE BASE FLOOD BFE: 6 & 7 FEET BASED ON NAVD 1988. |
| CITY OF WEST PALM BEACH ORDINANCE REQUIRES A TWO (2) |
| FOOT FREE BOARD ABOVE THE BASE FLOOD ELEVATION (SEC. |
| 18-284 CITY ORDINANCE NO. 4729-17). NEED TO SPECIFY THE |
| PROPOSED FINISHED FLOOR ELEVATION IN ALL FLOOR PLANS |
| BASED ON NAVD 1988. SEC.107.3.5.3 CITY AMENDMENTS. |
| |
| NOTE: DURING THE PERMITTING OF THIS STRUCTURE THREE |
| DIFFERENT FLOOD ELEVATION CERTIFICATES WILL BE REQUIRED |
| (SEC. 107.3.5.1.1 CITY AMENDMENTS): |
| A) CONSTRUCTION DRAWINGS. |
| B) BUILDING UNDER CONSTRUCTION. |
| C) FINISHED CONSTRUCTION. |
| |
| NOTE: |
| NEED TO PROVIDE THE CONSTRUCTION DRAWINGS ELEVATION |
| CERTIFICATE NOW FOR REVIEW. |
| |
| RESPONSE: |
| ELEVATION CERTIFICATE SUBMITTED IS FOR THE MAIN |
| RESIDENCE. NEED TO PROVIDE THE CONSTRUCTION DRAWINGS |
| ELEVATION CERTIFICATE FOR THE PROPOSED BUILDING. |
| NOTE: FLOOD VENTS ARE REQUIRED FOR GARAGE AND EXISTING |
| STORAGE/SHED. REVISE PLANS AS REQUIRED. |
| ALSO, CLARIFY IF USING ENGINEERED FLOOD VENTS OR |
| NON-ENGINEERED FLOOD VENTS. IF USING ENGINEERED FLOOD |
| VENTS, THEN PROVIDE PRODUCT APPROVAL (IT MAY BE |
| DEFERRED) AND WRITE STATEMENT REQUIRED BY SEC. R322.2.2 |
| FBC-RESIDENTIAL. |
| IF USING NON-ENGINEERED VENTS, THEN NEED TO PROVIDE |
| COMPLETE DETAILS/SPECIFICATIONS. SEC. 107.2.1 CITY |
| AMENDMENTS. |
| |
| ORIGINAL COMMENT: |
| 2- PROVIDE CURRENT SURVEY SHOWING PROPOSED ADDITION AND |
| FINISHED FLOOR ELEVATION INCLUDING THE FINISHED FLOOR |
| ELEVATION OF THE EXISTING BATH HOUSE. SEC.107.3.5.3 |
| CITY AMENDMENTS. |
| |
| RESPONSE: |
| DESCRIPTION AND USE OF EXISTING STRUCTURE SHOWN ON THE |
| SOUTH EAST CORNER OF THE PROPOSED GARAGE IS NOT CLEAR. |
| SURVEY, ARCHITECT'S SITE PLAN(DWG SP-1) AND STRUCTURAL |
| PLANS CALLS IT "BATH HOUSE", WHILE ALL OTHER |
| ARCHITECTURAL PLANS CALLS IT "STORAGE/SHED". REVISE AS |
| REQUIRED TO MATCH IN ORDER TO AVOID CONFLICTS/DELAYS. |
| SEC. 107.2.2 AND SEC. 107.2.1 CITY AMENDMENTS. |
| |
| 3- OK. |
| 4- OK. |
| |
| ORIGINAL COMMENT: |
| 5- DESIGN PRESSURES SPECIFIED ON SHEET S-0 AND SHEET |
| SP-1 ARE LOW FOR WORST CASE CONDITION. SEE SPECIFIED |
| EXPOSURE AND HEIGHT AND REVISE AS REQUIRED. TABLE |
| R301.2(2) FBC-RESIDENTIAL. |
| |
| RESPONSE: |
| DESIGN PRESSURES WERE NOT REVISED. BASED ON EXPOSURE D, |
| HEIGHT (28.5 FT), EDGE DISTANCE (5'-0")SPECIFIED ON |
| PLANS AND THE HEIGHT AND EXPOSURE ADJUSTMENT FROM TABLE |
| R301.2(3) THE DESIGN PRESSURES NEED TO BE HIGHER. |
| REVISE AS REQUIRED OR PROVIDE ACTUAL CALCULATIONS FOR |
| EACH OPENING. |
| NOTE: SIZE OF GARAGE DOOR SPECIFIED ON PLAN IS NOT |
| LISTED ON TABLE R301.2(4) FBC-RESIDENTIAL. YOU MAY USE |
| THE DESIGN PRESSURES FOR 9X7 DOOR OR PROVIDE |
| CALCULATIONS BASED ON THE ACTUAL SIZE OF SPECIFIED |
| DOOR. |
| |
| 6- OK. |
| 7- OK. |
| 8- OK. |
| 9- OK. |
| 10-OK. |
| 11-OK. |
| 12-OK. |
| |
| 13-ENERGY CALCULATIONS SUBMITTED: |
| A)OK. |
| B)OK. |
| C)OK. |
| |
| ORIGINAL COMMENT: |
| D)REVISE THE WINDOWS INFORMATION SHOWN ON PAGE 3 TO |
| MATCH PLANS. REVISE OVERHANG SEPARATION TO MATCH |
| EXTERIOR ELEVATIONS. SEC. R101.5.1.1.2 FBC-ENERGY |
| CONSERVATION. |
| |
| RESPONSE: |
| WINDOW OVERHANG SEPARATION FOR WINDOWS LOCATED ON THE |
| GABLE END SIDES IS INCORRECT. ALSO, CALCULATIONS ARE |
| NOW MISSING THE FRENCH GLASS DOOR ON THE EAST |
| ELEVATION. THIS DOOR WAS CONSIDERED IN THE PREVIOUS |
| ENERGY CALCULATIONS AND NOW IT WAS DELETED. REVISE AS |
| REQUIRED TO MATCH PLANS. |
| |
| 14- OK. |
| |
| 15-DEFERRED PRODUCT APPROVALS: |
| (NOTE: PROVIDE COMPLETE INFORMATION FOR REVIEW PRIOR TO |
| INSTALLATION TO AVOID CONFLICTS/DELAYS. ALL PRODUCT |
| APPROVALS NEED TO BE APPROVED IN WRITING BY DESIGNER OF |
| RECORD PRIOR TO SUBMITTAL): |
| A)EXTERIOR DOORS. |
| B)WINDOWS. |
| C)HURRICANE SHUTTERS IF DOORS AND WINDOWS DON'T HAVE |
| IMPACT GLAZING. AND, PROVIDE COMPLETE INSTALLATION |
| SCHEDULE. SEE CITY SAMPLE. |
| D)DECORATIVE SHUTTERS AND SPECIFY FASTENING. |
| E)ROOF TILE AND CLEARLY SPECIFY ROOF TILE FASTENING |
| METHOD. |
| F) ROOF TILE ADHESIVE (IF USED) AND CLEARLY SPECIFY |
| PADDY SIZE. |
| G)ROOF TILE HIP & RIDGE METAL SUPPORT TO BE USED. |
| CLEARLY MARK WHICH ONE WILL BE USED. |
| H) FLOOD VENTS. COORDINATE WITH ITEM #1 ABOVE. |
| |
| 16- DEFERRED SUBMITTAL: |
| GUARDRAILS AND HANDRAILS. |
| (NOTE: PROVIDE COMPLETE INFORMATION FOR REVIEW PRIOR TO |
| INSTALLATION TO AVOID CONFLICTS/DELAYS. INFORMATION TO |
| BE APPROVED IN WRITING BY DESIGNER OF RECORD PRIOR TO |
| SUBMITTAL). |
| |
| WHEN RESUBMITTING, A TRANSMITTAL LETTER LISTING THE |
| ORIGINAL REVIEW COMMENT WITH A DESCRIPTION OF THE |
| REVISION MADE WILL HELP TO EXPEDITE THE REVIEW PROCESS. |
| THANK YOU FOR YOUR ANTICIPATED COOPERATION. |
| |
| PLEASE FEEL FREE TO CONTACT ME IF YOU HAVE ANY |
| QUESTIONS REGARDING THESE COMMENTS, |
| JULIO GOMEZ |
| COMMERCIAL COMBINATION PLANS EXAMINER |
| DEVELOPMENT SERVICES DEPARTMENT |
| BUILDING DIVISION |
| (561)805-6712 |
| [email protected] |
| |