2021-12-29 10:10:05 | JONATHAN BROOKS JR. |
| BUILDING PLANS EXAMINER |
| WORK HOURS: MONDAY - FRIDAY 7:00 AM TO 3:00 PM |
| PHONE (561) 805-6656 |
| EMAIL: [email protected] |
| |
| 1ST REVIEW: FBC 2020 7TH EDITION |
| FBC = FLORIDA BUILDING CODE, 7TH EDITION (2020) |
| FBC B = FBC BUILDING |
| FBC R = FBC RESIDENTIAL |
| FBC EB = FBC EXISTING BUILDING |
| FBC A = FBC ACCESSIBILITY |
| FBC EC = FBC ENERGY CONSERVATION |
| WPB A = CITY OF WEST PALM BEACH AMENMENTS TO THE FBC |
| RESULTS: DENIED |
| ADDRESS THE ATTACHED COMMENTS AND RE-SUBMIT |
| TO RESUBMIT, YOU CAN EITHER DROP OFF YOUR SUBMITTAL AT |
| CITY HALL, OR EMAIL [email protected] AND REQUEST |
| THAT IT BE CONVERTED TO PROJECTDOX. |
| |
| 1. SUBMITTED PRODUCT APPROVAL FL 12328-R9 COVERS |
| MULTIPLE PRODUCTS. SELECT PRODUCT DESCRIPTION AND |
| LIMITS OF USE. SELECT PRODUCT TO BE USED. ALL |
| APPLICABLE DETAILS AND ATTACHMENTS MUST BE CLEARLY |
| IDENTIFIED ON THE PRODUCT APPROVAL DRAWINGS. SECOND |
| REQUEST. |
| 2. SUBMITTED PRODUCT APPROVAL FL10124-R29 HAS BEEN |
| REVISED TO FL10124-R31. PLEASE PROVIDE A COMPLETE SET. |
| ALL APPLICABLE DETAILS AND ATTACHMENTS MUST BE CLEARLY |
| IDENTIFIED ON THE PRODUCT APPROVAL DRAWINGS. DETAILS |
| AND ATTACHMENTS NOT SPECIFICALLY COVERED IN PRODUCT |
| APPROVALS WILL NEED SITE-SPECIFIC ENGINEERING. AS PER |
| RULE 61G20-3. SECOND REQUEST. |
| 3. FBC B 107.2.1. SUBMITTED FLORIDA DBPR PRODUCT |
| APPROVAL FL17084-R10 OR FL16717-R11 IS NOT APPROVED FOR |
| USE AS A SEAM TAPE. PROVIDE A COMPLETE SET OF 2020 CODE |
| VERSION PRODUCT APPROVALS/NOA'S FOR THE PROPOSED ROOF |
| UNDERLAYMENT (JOINT TAPE/STRIPS) TO BE USED. INCLUDE |
| COVER PAGE, EVALUATION REPORTS AND INSTALLATION |
| INSTRUCTIONS FOR SYSTEM USED. ALL APPLICABLE DETAILS |
| AND ATTACHMENTS MUST BE CLEARLY IDENTIFIED ON THE |
| PRODUCT APPROVAL DRAWINGS. DETAILS AND ATTACHMENTS NOT |
| SPECIFICALLY COVERED IN PRODUCT APPROVALS WILL NEED |
| SITE-SPECIFIC ENGINEERING. (OPTIONS FL12328-R9, |
| FL2569-R23, FL5259-R33 ETC.) SECOND REQUEST. |
| |
| PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED |
| MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMEMTS. |
| |