2022-01-03 15:52:55BUILDING PLAN REVIEW
  
 CHRISTOPHER S. THROOP, C.B.O., CFM
 PLANS EXAMINER II PX3169/SFP306
 INSPECTOR BN4338
 BUILDING OFFICIAL BU1635
 ASFPM CERTIFIED FLOODPLAIN MANAGER US-21-11935
 DEVELOPMENT SERVICES DEPARTMENT
 CITY OF WEST PALM BEACH
 (561) 805-6726
 [email protected]
  
 CODES IN EFFECT:
 2020 FLORIDA BUILDING CODE, 7TH EDITION W/2017 WEST
 PALM BEACH AMENDMENTS TO THE FLORIDA BUILDING CODE,
 CHAPTER 1 ADMINISTRATION
 2017 NEC
 CITY OF WEST PALM BEACH, FLORIDA ORDINANCE NO. 4729-17
  
  
 1ST REVIEW
  
 RESULTS: DENIED
  
  
 1.THIS PROJECT IS LOCATED IN A SPECIAL FLOOD HAZARD
 AREA (SFHA). THE STRUCTURE IS LOCATED WITHIN TWO AE
 FLOOD ZONES WITH BASE FLOOD ELEVATIONS (BFE) OF
 6'0"NAVD AND 7'0" NAVD. THE CITY OF WEST PALM BEACH
 (THROUGH ORDINANCE NO. 4729-17) REQUIRES AN ADDITIONAL
 24 INCHES OF FREEBOARD. THE DESIGN FLOOD ELEVATION
 (DFE) SHALL BE AT OR ABOVE 9'0"NAVD.
  
 CITY OF WEST PALM BEACH, FLORIDA ORDINANCE NO. 4729-17
 SECTION 4: THE CODE OF ORDINANCES IS HEREBY AMENDED AT
 CHAPTER 18, BUILDINGS AND BUILDING REGULATIONS, ARTICLE
 II, BUILDING CODE, TO ADD SECTION 18-33, TECHNICAL
 AMENDMENTS TO FLORIDA BUILDING CODE, RESIDENTIAL, WHICH
 SHALL READ AS FOLLOWS:
  
 SEC. 18-33 - TECHNICAL AMENDMENTS TO FLORIDA BUILDING
 CODE, RESIDENTIAL.
 R322.2.1 ELEVATION REQUIREMENTS.
 1. BUILDINGS AND STRUCTURES IN FLOOD HAZARD AREAS NOT
 DESIGNATED AS COASTAL A ZONES SHALL HAVE THE LOWEST
 FLOORS ELEVATED TO OR ABOVE THE BASE FLOOD ELEVATION
 PLUS TWO FEET OR THE DESIGN FLOOD ELEVATION, WHICHEVER
 IS HIGHER.
  
 2.PLACE THE FINISHED FLOOR ELEVATION (FFE) OF THE MAIN
 DWELLING UNIT AND THE ATTACHED GARAGE ON THE SITE PLAN,
 THE FLOOR PLAN AND THE FOUNDATION PLAN.
  
 3. NOTICE: THE GARAGE FLOOR IS BELOW THE DFE OF 9'0"
 NAVD.
 FLOOD OPENINGS ARE REQUIRED.
 R322.2.2ENCLOSED AREA BELOW DESIGN FLOOD ELEVATION.
 ENCLOSED AREAS, INCLUDING CRAWL SPACES, THAT ARE BELOW
 THE DESIGN FLOOD ELEVATION SHALL:
 1. 1.BE USED SOLELY FOR PARKING OF VEHICLES, BUILDING
 ACCESS OR STORAGE.
 2. 2.BE PROVIDED WITH FLOOD OPENINGS THAT MEET THE
 FOLLOWING CRITERIA AND ARE INSTALLED IN ACCORDANCE WITH
 SECTION R322.2.2.1:
 1. 2.1.THE TOTAL NET AREA OF NON-ENGINEERED OPENINGS
 SHALL BE NOT LESS THAN 1 SQUARE INCH (645 MM2) FOR EACH
 SQUARE FOOT (0.093 M2) OF ENCLOSED AREA WHERE THE
 ENCLOSED AREA IS MEASURED ON THE EXTERIOR OF THE
 ENCLOSURE WALLS, OR THE OPENINGS SHALL BE DESIGNED AS
 ENGINEERED OPENINGS AND THE CONSTRUCTION DOCUMENTS
 SHALL INCLUDE A STATEMENT BY A REGISTERED DESIGN
 PROFESSIONAL THAT THE DESIGN OF THE OPENINGS WILL
 PROVIDE FOR EQUALIZATION OF HYDROSTATIC FLOOD FORCES ON
 EXTERIOR WALLS BY ALLOWING FOR THE AUTOMATIC ENTRY AND
 EXIT OF FLOODWATERS AS SPECIFIED IN SECTION 2.7.2.2 OF
 ASCE 24.
 2. 2.2.OPENINGS SHALL BE NOT LESS THAN 3 INCHES (76 MM)
 IN ANY DIRECTION IN THE PLANE OF THE WALL.
 3. 2.3.THE PRESENCE OF LOUVERS, BLADES, SCREENS AND
 FACEPLATES OR OTHER COVERS AND DEVICES SHALL ALLOW THE
 AUTOMATIC FLOW OF FLOODWATER INTO AND OUT OF THE
 ENCLOSED AREAS AND SHALL BE ACCOUNTED FOR IN THE
 DETERMINATION OF THE NET OPEN AREA.
  
  
 OPTION:
 ENGINEERED FLOOD VENTS
  
 1) PROVIDE ENGINEERED FLOOD VENTS. (SMART VENTS)
 2) ATTACH A COPY OF THE INDIVIDUAL ENGINEERED FLOOD
 VENT CERTIFICATION OR EVALUATION SERVICE REPORT ISSUED
 BY THE INTERNATIONAL CODE COUNCIL EVALUATION SERVICE
 (ICC ES).
 3) PROVIDE FLORIDA PRODUCT APPROVALS FOR PROPOSED SMART
 VENTS.
 FBC 107.3.4 PROVIDE PRODUCT APPROVALS FOR THOSE
 PRODUCTS WHICH ARE REGULATED BY FAC RULE
 9N-3 REVIEWED AND APPROVED IN WRITING BY THE DESIGNER
 OF RECORD.
 5) FLOOD OPENINGS SHALL BE INSTALLED PER
 R322.2.2.1INSTALLATION OF OPENINGS:
 6) SHOW NUMBER AND LOCATION OF FLOOD OPENINGS ON
 FOUNDATION PLAN. INCLUDE THE FLORIDA PRODUCT APPROVAL
 NUMBER AND IDENTIFY THE VENT MODEL TO BE INSTALLED.
 R322.2.2.1INSTALLATION OF OPENINGS.
 THE WALLS OF ENCLOSED AREAS SHALL HAVE OPENINGS
 INSTALLED SUCH THAT:
 1. 1.THERE SHALL BE NOT LESS THAN TWO OPENINGS ON
 DIFFERENT SIDES OF EACH ENCLOSED AREA; IF A BUILDING
 HAS MORE THAN ONE ENCLOSED AREA BELOW THE DESIGN FLOOD
 ELEVATION, EACH AREA SHALL HAVE OPENINGS.
 2. 2.THE BOTTOM OF EACH OPENING SHALL BE NOT MORE THAN
 1 FOOT (305 MM) ABOVE THE HIGHER OF THE FINAL INTERIOR
 GRADE OR FLOOR AND THE FINISHED EXTERIOR GRADE
 IMMEDIATELY UNDER EACH OPENING.
 3. 3.OPENINGS SHALL BE PERMITTED TO BE INSTALLED IN
 DOORS AND WINDOWS; DOORS AND WINDOWS WITHOUT INSTALLED
 OPENINGS DO NOT MEET THE REQUIREMENTS OF THIS SECTION.
  
 FEMA TECHNICAL BULLETIN #1
 LOCATION OF FLOOD OPENINGS
 THE IRC AND IBC (BY REFERENCE TO ASCE 24) REQUIRE FLOOD
 OPENINGS ?ON DIFFERENT SIDES OF EACH ENCLOSED AREA?
 (IRC R322.2.2.1) AND ?IN AT LEAST TWO WALLS OF EACH
 ENCLOSED AREA? (ASCE 24, SECTION 2.7.3).
  
  
 4. NOTE: PLAN PAGE C-1 INDICATES FOUR FLOOD VENTS ARE
 INSTALLED WITH UNDER SLAB CHANNELS.
 PROVIDE A DETAIL OF THE CHANNELS AND A REFERENCE TO THE
 FEMA REGULATION THAT ALLOWS THIS TYPE OF INSTALLATION.
  
  
 NOTICE: SUBMIT THE FOLLOWING ELEVATION CERTIFICATES, AS
 REQUIRED. (SEE NFIP REVIEW COMMENTS)
  
 THREE ELEVATION CERTIFICATES (EC) ARE REQUIRED
  
 A CONSTRUCTION DRAWING ELEVATION CERTIFICATE IS
 REQUIRED AT TIME OF PERMIT APPLICATION.
  
 A BUILDING UNDER CONSTRUCTION ELEVATION CERTIFICATE IS
 REQUIRED AT PLACEMENT OF 1ST FLOOR.
  
 A FINISHED CONSTRUCTION ELEVATION CERTIFICATE IS
 REQUIRED AND SHALL BE SUBMITTED FOR REVIEW AND APPROVAL
 PRIOR TO THE ISSUANCE OF THE CERTIFICATE OF OCCUPANCY.
  
 NOTE: YOU MAY SUBMIT THIS EC FOR REVIEW AFTER FINAL
 GRADE AND PLACEMENT OF EQUIPMENT SERVICING THE
 BUILDING.
  
 5. REF. SITE PLAN PAGE C-1 FOR THE FOLLOWING COMMENT:
 EQUIPMENT SERVICING THE BUILDING SHALL BE AT OR ABOVE
 9'0" NAVD. PLEASE CORRECT.
  
 6. REF. PLAN PAGES S-101 AND C-1 FOR THE FOLLOWING
 COMMENT: PG. S-101 INDICATES TOS TO BE 9'0". PG. C-1
 INDICATES TOS TO BE 8.83' WITH FINISHED FLOOR TO BE
 9'0" NAVD. PLEASE CLARIFY.
  
 7. PROVIDE COVER SHEETS FOR ALL PRODUCT APPROVALS
 SUBMITTED FOR REVIEW.
 PROVIDE THE FLORIDA STATE PRODUCT APPROVAL COVER
 SHEETS; THEY SHOW THE APPROVAL NUMBER, CODE VERSION,
 AND STATUS, FBC R 301. (MIAMI DADE NOAS ARE OK, DO NOT
 NEED FL COVER PAGE).
 FBC 107.3.4 PROVIDE PRODUCT APPROVALS FOR THOSE
 PRODUCTS WHICH ARE REGULATED BY FAC RULE 9N-3 REVIEWED
 AND APPROVED IN WRITING BY THE DESIGNER OF RECORD.
  
 8. PROVIDE PRODUCT APPROVALS FOR THE WINDOW MULLIONS.
 FBC 107.3.4 PROVIDE PRODUCT APPROVALS FOR THOSE
 PRODUCTS WHICH ARE REGULATED BY FAC RULE 9N-3 REVIEWED
 AND APPROVED IN WRITING BY THE DESIGNER OF RECORD.
  
 9. PROVIDE THE ICC-ES REPORT FOR THE SPRAY APPLIED
 INSULATION.
 FBC 107.3.4 PROVIDE PRODUCT APPROVALS FOR THOSE
 PRODUCTS WHICH ARE REGULATED BY FAC RULE 9N-3 REVIEWED
 AND APPROVED IN WRITING BY THE DESIGNER OF RECORD.
  
 10. REF. PLAN PAGE S003 FOR THE FOLLOWING COMMENT:
 PROVIDE A ROOF SHEATHING FASTENER SCHEDULE BASED ON THE
 CALCULATED DESIGN PRESSURES.
 PROVIDE ROOF SHEATHING FASTENER SCHEDULE PER DESIGN
 PRESSURES.
 TABLE R301.2.1.2 WINDBORNE DEBRIS PROTECTION FASTENING
 SCHEDULE FOR WOOD STRUCTURAL PANELS.
  
 NOTICE: PROVISO'S
 PLAN PAGE C-1; SITE WALLS REQUIRE A SEPERATE PERMIT.
 PLAN PAGE L1.1; POOL REQUIRES A SEPERATE PERMIT.
  
 PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED
 MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS.
  
 WHEN RESUBMITING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM.
  
  
  