2022-05-16 10:56:42 | NEW WAREHOUSE |
| REVIEWED BY ROGER MCPHERSON |
| 561-805-6716 |
| [email protected] |
| CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1 |
| AMENDMENT |
| |
| CORRECTIONS NEEDED - |
| |
| 1) PLEASE PROVIDE COMPLETE (FRONT PAGES AND THE |
| INSTALLATION INSTRUCTIONS) MIAMI DADE OR FLORIDA STATE |
| PRODUCT APPROVALS FOR THE OVERHEAD DOORS. |
| |
| 2) PLEASE PROVIDE DETAILS FOR THE ALUMINUM CANOPIES TO |
| COMPLY WITH THE WIND LOADS - FBC 1609.1 - OR LIST THE |
| CANOPIES TO BE A DEFERRED SUBMITTAL ON THE DRAWINGS FBC |
| WPB 107.3.4.1 |
| |
| 3) PLEASE PROVIDE THE COMPLETE (FRONT PAGES AND THE |
| INSTALLATION INSTRUCTIONS) MIAMI DADE OR FLORIDA STATE |
| PRODUCT APPROVAL FOR THE ROOFING SYSTEM OR LIST THE |
| ROOFING TO BE A DEFERRED SUBMITTAL ON THE DRAWINGS FBC |
| WPB 107.3.4.1 |
| |
| 4) ROOFING SYSTEM PRODUCT APPROVALS, AWNING SHOP |
| DRAWINGS AND WINDOW AND DOOR PRODUCT APPROVALS MAY BE |
| DEFERRED SUBMITTALS BY LISTING ITEMS TO BE DEFERRED ON |
| THE CONSTRUCTION DOCUMENTS - 107.3.4.1 DEFERRED |
| SUBMITTALS. FOR THE PURPOSES OF THIS SECTION, DEFERRED |
| SUBMITTALS ARE DEFINED AS THOSE PORTIONS OF THE DESIGN |
| THAT ARE NOT SUBMITTED AT THE TIME OF THE APPLICATION |
| AND THAT ARE TO BE SUBMITTED TO THE BUILDING OFFICIAL |
| WITHIN A SPECIFIED PERIOD. DEFERRAL OF ANY SUBMITTAL |
| ITEMS SHALL HAVE THE PRIOR APPROVAL OF THE BUILDING |
| OFFICIAL. THE REGISTERED DESIGN PROFESSIONAL IN |
| RESPONSIBLE CHARGE SHALL LIST THE DEFERRED SUBMITTALS |
| ON THE CONSTRUCTION DOCUMENTS FOR REVIEW BY THE |
| BUILDING OFFICIAL. DOCUMENTS FOR DEFERRED SUBMITTAL |
| ITEMS SHALL BE SUBMITTED TO THE REGISTERED DESIGN |
| PROFESSIONAL IN RESPONSIBLE CHARGE WHO SHALL REVIEW |
| THEM AND FORWARD THEM TO THE BUILDING OFFICIAL WITH A |
| NOTATION INDICATING THAT THE DEFERRED SUBMITTAL |
| DOCUMENTS HAVE BEEN REVIEWED AND FOUND TO BE IN GENERAL |
| CONFORMANCE TO THE DESIGN OF THE BUILDING. THE DEFERRED |
| SUBMITTAL ITEMS SHALL NOT BE INSTALLED UNTIL THE |
| DEFERRED SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE |
| BUILDING OFFICIAL. |
| |
| |
| |