Plan Review Notes
Plan Review Notes For Permit 21080536
Permit Number 21080536
Review Stop P
Sequence Number 2
Notes
Date Text
2022-04-14 11:51:292ND REVIEW REV 1
 SEE COMMENT #4; ***A) AND ***C)
 PLUMBING COMMENTS: DENIED
  
  
 1. NEW COMMENT: DUE TO A CHANGE IN PROCESS, THE
 BACKFLOW PERMIT AND GREASE INTERCEPTOR PERMITS ARE
 REQUIRED TO BE SUBMITTED PRIOR TO ISSUANCE OF THE
 PRIMARY PERMIT (AS APPLICABLE). YOU CAN SUBMIT AN
 APPLICATION "TBD" (TO BE DETERMINED) IF YOU DO NOT HAVE
 A CONTRACTOR SELECTED BY EMAILING A COMPLETED PERMIT
 APPLICATION TO [email protected] . YOU WILL
 RECEIVE INSTRUCTIONS TO PAY FEES AND UPLOAD PLANS. YOU
 MAY UPLOAD PLANS AND PAY FEES AT A FUTURE DATE, BUT THE
 APPLICATION IS REQUIRED AT THIS TIME. WE RECOMMEND THAT
 YOU PAY FEES AND UPLOAD PLANS AT THE SAME TIME. AFTER
 YOU HAVE THE PERMIT(S) GENERATED, NOTIFY ME VIA EMAIL
 AND I WILL CHANGE THE REVIEW STATUS TO PASS.
  
 2.NEW COMMENT: GREASE INTERCEPTOR; PLEASE NOTE THAT PER
 FBC PL 301.7 AND 303.2, THE INSTALLATION OF THE SCHIER
 GB-75 GREASE INTERCEPTOR SHALL CONFORM TO A MINIMUM OF
 THE MANUFACTURER'S RECOMMENDATIONS. IN ACCORDANCE WITH
 THE GB-75 INSTALLATION GUIDE PAGE 8, 9 AND 10 OF 10, A
 TWO-WAY CLEANOUT IS REQUIRED ON BOTH THE INLET AND
 OUTLET SIDE OF THE GREASE INTERCEPTOR.
  
 3.SECOND REQUEST: PER WPB FBC 107.2.1, PROVIDE DETAIL
 FOR TIEDOWN OF TANK. PROVIDE DETAIL OF BURIED TANK.
 PROVIDE INFORMATION SHOWING THAT BOTTOM EDGE OF
 EXCAVATION WILL NOT ADVERSELY AFFECT OR UNDERMINE THE
 FOOTERS. SEE FBC PL 307.5 AND FBC 1803.5.7. SEE THE
 FOLLOWING:
 ***A) PLEASE NOTE THAT PER FBC PL 301.7 AND 303.2, THE
 INSTALLATION OF THE SCHIER GB-75 GREASE INTERCEPTOR
 SHALL CONFORM TO A MINIMUM OF THE MANUFACTURER'S
 RECOMMENDATIONS.
 ***B) TO BE CLEAR, PROVIDE A DETAIL FOR THE UNDERGROUND
 INSTALLATION OF THE SCHIER GB-75 GREASE INTERCEPTOR.
 PLEASE REFER TO THE SCHIER GB-75 INSTALLATION GUIDE
 PAGE 3, 8, 9 AND 10 OF 10 FOR DETAILS. PLEASE NOTE THE
 REFERENCE TO TIE DOWNS AND MAKE A FINAL DETERMINATION
 AS TO THE APPLICABILITY TO THIS PROJECT.
 ***C) PROVIDE INFORMATION SHOWING THAT BOTTOM EDGE OF
 EXCAVATION WILL NOT ADVERSELY AFFECT OR UNDERMINE THE
 FOOTERS. SEE FBC PL 307.5 AND FBC 1803.5.7.
  
 4.NEW COMMENT: REGARDING THE SAMPLING POINT INSTALLED
 UPSTREAM OF THE GB-75;
 ***A) REV 1- IN ACCORDANCE WITH THE SCHIER SV-10
 INSTALLATION GUIDE (SEE FBC PL 301.7 AND 303.2), THE
 SAMPLING POINT SHALL BE DOWNSTREAM OF THE INTERCEPTOR.
 ***B) PER WPB FBC 107.2.1, PLEASE SPECIFY THE SAMPLING
 POINT DEVICE TO BE INSTALLED (SCHIER PRODUCT IS SV-10)
 ***C) REV 1- PLEASE NOTE THAT THE JURISDICTION ACCEPTS
 A TWO-WAY CLEANOUT FOR USE AS A SAMPLING POINT
  
  
 END OF COMMENTS.
  
  
 PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED
 MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS.
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM. PLEASE, ADDITIONALLY, INSERT
 CORRECTED PAGES INTO TO SUBMITTAL AND REMOVE OR VOID
 THE PREVIOUSLY REVIEWED SHEETS. ALL PLANS TO BE SIGNED
 AND SEALED BY THE DESIGNER AS REQUIRED BY FAC AND FS.
  
 JERALD SMITH
 PLUMBING PLANS EXAMINER
 CITY OF WEST PALM BEACH
 EMAIL [email protected]
 MOBILE 561-246-0882
 PLEASE NOTE THAT I TYPICALLY WORK ON TUESDAYS AND
 THURSDAYS
  
 21080534 620 7TH ST
 MASTER PERMIT 19120500 LOT 5B REVISION
2022-03-17 16:42:54CODES IN EFFECT:
 FBC = FLORIDA BUILDING CODE 2017 6TH EDITION
 WPB FBC = WEST PALM BEACH AMENDMENTS TO THE FBC 2017
 6TH ED, CHAPTER 1
 WPB CCCM=WEST PALM BEACH CROSS-CONNECTION CONTROL
 MANUAL REVISED 2017
 FBC EC = FLORIDA BUILDING CODE ENERGY CONSERVATION 2017
 6TH EDITION
 FBC ACC = FLORIDA ACCESSIBILITY CODE 2017 6TH EDITION
 FBC EX = FLORIDA EXISTING BUILDING CODE 2017 6TH
 EDITION
 FBC PL = FLORIDA PLUMBING CODE 2017 6TH EDITION
 FBC FG = FLORIDA FUEL GAS CODE 2017 6TH EDITION
 FAC= FLORIDA ADMINISTRATIVE CODE
 FS = FLORIDA STATUTES
  
 21080534 620 7TH ST
 MASTER PERMIT 19120500 LOT 5B REVISION
  
 2ND REVIEW
 PLUMBING COMMENTS: DENIED
  
 1. NEW COMMENT: DUE TO A CHANGE IN PROCESS, THE
 BACKFLOW PERMIT AND GREASE INTERCEPTOR PERMITS ARE
 REQUIRED TO BE SUBMITTED PRIOR TO ISSUANCE OF THE
 PRIMARY PERMIT (AS APPLICABLE). YOU CAN SUBMIT AN
 APPLICATION "TBD" (TO BE DETERMINED) IF YOU DO NOT HAVE
 A CONTRACTOR SELECTED BY EMAILING A COMPLETED PERMIT
 APPLICATION TO [email protected] . YOU WILL
 RECEIVE INSTRUCTIONS TO PAY FEES AND UPLOAD PLANS. YOU
 MAY UPLOAD PLANS AND PAY FEES AT A FUTURE DATE, BUT THE
 APPLICATION IS REQUIRED AT THIS TIME. WE RECOMMEND THAT
 YOU PAY FEES AND UPLOAD PLANS AT THE SAME TIME. AFTER
 YOU HAVE THE PERMIT(S) GENERATED, NOTIFY ME VIA EMAIL
 AND I WILL CHANGE THE REVIEW STATUS TO PASS.
  
 2.NEW COMMENT: GREASE INTERCEPTOR; PLEASE NOTE THAT PER
 FBC PL 301.7 AND 303.2, THE INSTALLATION OF THE SCHIER
 GB-75 GREASE INTERCEPTOR SHALL CONFORM TO A MINIMUM OF
 THE MANUFACTURER'S RECOMMENDATIONS. IN ACCORDANCE WITH
 THE GB-75 INSTALLATION GUIDE PAGE 8, 9 AND 10 OF 10, A
 TWO-WAY CLEANOUT IS REQUIRED ON BOTH THE INLET AND
 OUTLET SIDE OF THE GREASE INTERCEPTOR.
  
 3.SECOND REQUEST: PER WPB FBC 107.2.1, PROVIDE DETAIL
 FOR TIEDOWN OF TANK. PROVIDE DETAIL OF BURIED TANK.
 PROVIDE INFORMATION SHOWING THAT BOTTOM EDGE OF
 EXCAVATION WILL NOT ADVERSELY AFFECT OR UNDERMINE THE
 FOOTERS. SEE FBC PL 307.5 AND FBC 1803.5.7. SEE THE
 FOLLOWING:
 ***A) PLEASE NOTE THAT PER FBC PL 301.7 AND 303.2, THE
 INSTALLATION OF THE SCHIER GB-75 GREASE INTERCEPTOR
 SHALL CONFORM TO A MINIMUM OF THE MANUFACTURER'S
 RECOMMENDATIONS.
 ***B) TO BE CLEAR, PROVIDE A DETAIL FOR THE UNDERGROUND
 INSTALLATION OF THE SCHIER GB-75 GREASE INTERCEPTOR.
 PLEASE REFER TO THE SCHIER GB-75 INSTALLATION GUIDE
 PAGE 3, 8, 9 AND 10 OF 10 FOR DETAILS. PLEASE NOTE THE
 REFERENCE TO TIE DOWNS AND MAKE A FINAL DETERMINATION
 AS TO THE APPLICABILITY TO THIS PROJECT.
 ***C) PROVIDE INFORMATION SHOWING THAT BOTTOM EDGE OF
 EXCAVATION WILL NOT ADVERSELY AFFECT OR UNDERMINE THE
 FOOTERS. SEE FBC PL 307.5 AND FBC 1803.5.7.
  
 4.NEW COMMENT: REGARDING THE SAMPLING POINT INSTALLED
 UPSTREAM OF THE GB-75;
 ***A) IT IS MY UNDERSTANDING THAT THE SAMPLING POINT
 SHOULD REFLECT THE QUALITY OF THE DISCHARGE TO THE
 SEWAGE SYSTEM AND SHOULD BE DOWNSTREAM OF THE
 INTERCEPTOR.
 ***B) PER WPB FBC 107.2.1, PLEASE SPECIFY THE SAMPLING
 POINT DEVICE TO BE INSTALLED (SCHIER PRODUCT IS SV-10)
  
 END OF COMMENTS.
  
  
 PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED
 MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS.
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM. PLEASE, ADDITIONALLY, INSERT
 CORRECTED PAGES INTO TO SUBMITTAL AND REMOVE OR VOID
 THE PREVIOUSLY REVIEWED SHEETS. ALL PLANS TO BE SIGNED
 AND SEALED BY THE DESIGNER AS REQUIRED BY FAC AND FS.
  
 JERALD SMITH
 PLUMBING PLANS EXAMINER
 CITY OF WEST PALM BEACH
 EMAIL [email protected]
 MOBILE 561-246-0882
 PLEASE NOTE THAT I TYPICALLY WORK ON TUESDAYS AND
 THURSDAYS
  
 21080534 620 7TH ST
 MASTER PERMIT 19120500 LOT 5B REVISION


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved