Date |
Text |
2022-03-28 12:36:32 | NEW COMMERCIAL BUILDING R2 |
| REVIEWED BY ROGER MCPHERSON |
| 561-805-6716 |
| [email protected] |
| CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1 |
| AMENDMENT |
| |
| CORRECTIONS NEEDED - |
| |
| 1) REVISED DRAWINGS LS1.108 AND LS1.107 - THE DOORS |
| FROM THE UNITS TO THE CORRIDOR LOBBY AND ELEVATOR LOBBY |
| DO NOT SHOW THE FIRE RATINGS. |
| |
| 2) DRAWING A1.105 DIMENSIONS OF THE MASTER BATH TOILET |
| ROOM IS SHOWN SMALLER THAN THE FHA DRAWING DIMENSIONS |
| ON DRAWING A1.314 |
| |
| 3) PLEASE SHOW THE POOL BARRIER FOR PENTHOUSE POOL FBC |
| 454.2.17.1 (PRIVATE POOLS ALSO REQUIRE A POOL BARRIER) |
| |
| 4) DRAWING LS1.102 AND LS1.103 ELEVATOR R2 SHOULD HAVE |
| FIRE PROTECTION FROM THE CROSS CORRIDOR - UNLESS THE |
| ELEVATORS ARE PRESSURIZED PER FBC 3006.3 (PLEASE |
| PROVIDE A NOTE ON THE DRAWINGS IF THE ELEVATOR |
| HOISTWAYS ARE PRESSURIZED) |
| |
| 5) PLEASE MARK THE FULLY ACCESSIBLE FHA UNIT RESTROOMS |
| ON DRAWING A1.314 AS "TYPE B" - PLEASE SHOW ON THE |
| FLOOR PLANS THAT EACH UNIT BATHROOM COMPLIES WITH SPEC. |
| A OR B - FBC FHA REQUIREMENT 7. (2) |
| |
| 6) PLEASE SHOW THE UNIT FLOOR FINISHES - FOR OTHER THAN |
| CARPET AND PROVIDE THE FOLLOWING ACOUSTICAL TEST |
| REPORTS - (CAN BE ADDED TO THE DEFERRED SUBMITTAL LIST) |
| |
| MANUFACTURER SPEC SHEETS ARE NOT ACCEPTABLE DUE TO |
| DISCREPANCIES BETWEEN SPEC SHEETS/BROCHURES AND TEST |
| REPORTS FOR SOME MANUFACTURERS (NOT NECESSARILY THE |
| MANUFACTURER SELECTED; THIS IS A GENERAL COMMENT) |
| |
| A. FBC 1207.2, FLOOR/CEILING ASSEMBLIES SEPARATING |
| DWELLING UNITS FROM EACH OTHER OR FROM PUBLIC OR |
| SERVICE AREAS SHALL HAVE A SOUND TRANSMISSION CLASS |
| (STC) OF NOT LESS THAN 50 (45 IF FIELD TESTED) FOR AIR |
| BORNE NOISE WHEN TESTED IN ACCORDANCE WITH ASTM E 90.. |
| PROVIDE A COPY OF THE TEST REPORT. (A DROP CEILING |
| SHOULD NOT BE INCLUDED IN THE FLOOR/CEILING ASSEMBLY |
| DESCRIPTION UNLESS THE UNIT MATCHES THE TESTED DROP |
| CEILING DESCRIPTION) |
| |
| B. FBC 1207.3, FLOOR/CEILING ASSEMBLIES BETWEEN |
| DWELLING UNITS OR BETWEEN A DWELLING UNIT AND A PUBLIC |
| OR SERVICE AREA WITHIN THE STRUCTURE SHALL HAVE AN |
| IMPACT INSULATION CLASS (IIC) RATING OF NOT LESS THAN |
| 50 (45 IF FIELD TESTED) WHEN TESTED IN ACCORDANCE WITH |
| ASTM E 492. PROVIDE A COPY OF THE TEST REPORT. (A DROP |
| CEILING SHOULD NOT BE INCLUDED IN THE FLOOR/CEILING |
| ASSEMBLY DESCRIPTION UNLESS THE UNIT MATCHES THE TESTED |
| DROP CEILING DESCRIPTION) |
| |
| C. FBC 603.1, ALLOWABLE MATERIALS IN NON COMBUSTIBLE |
| BUILDINGS, SEE ITEM 2, EXCEPTION 2, ACOUSTICAL |
| INSULATION INSTALLED BETWEEN A FINISHED FLOOR AND SOLID |
| DECKING WITHOUT INTERVENING AIRSPACE SHALL BE ALLOWED |
| TO HAVE A FLAME SPREAD INDEX OF NOT MORE THAN 200. SEE |
| 803.1.1, PROVIDE TEST DATA IN ACCORDANCE WITH ASTM E 84 |
| OR UL 723. (DO NOT NEED THIS REPORT IF THE PADDING IS |
| ATTACHED TO THE FLOORING) |
| |
| 7) (CAN BE ADDED TO THE DEFERRED SUBMITTALS LIST) |
| PLEASE PROVIDE COMPLETE (FRONT PAGES AND THE |
| INSTALLATION INSTRUCTIONS) MIAMI DADE OR FLORIDA STATE |
| PRODUCT APPROVALS FOR THE EXTERIOR WINDOWS, EXTERIOR |
| DOORS, ROOFING SYSTEMS, EXTERIOR LOUVERS, EXTERIOR |
| CLADDING - ETC. - ALL PRODUCT APPROVALS NEED TO BE |
| REVIEWED AND MARKED APPROVED BY THE BUILDING DESIGNER |
| OF RECORD FBC WPB 107.3.4 |
| |
| 8) PLEASE PROVIDE A DEFERRED SUBMITTALS LIST ON THE |
| DRAWINGS - - ITEMS SUCH AS WINDOW, DOOR AND ROOFING |
| PRODUCT APPROVALS, FLOORING/UNDERLAYMENT ACOUSTICAL |
| TEST REPORTS - ETC. MAY BE DEFERRED SUBMITTALS BY |
| LISTING ITEMS TO BE DEFERRED ON THE CONSTRUCTION |
| DOCUMENTS - 107.3.4.1 DEFERRED SUBMITTALS. FOR THE |
| PURPOSES OF THIS SECTION, DEFERRED SUBMITTALS ARE |
| DEFINED AS THOSE PORTIONS OF THE DESIGN THAT ARE NOT |
| SUBMITTED AT THE TIME OF THE APPLICATION AND THAT ARE |
| TO BE SUBMITTED TO THE BUILDING OFFICIAL WITHIN A |
| SPECIFIED PERIOD. DEFERRAL OF ANY SUBMITTAL ITEMS SHALL |
| HAVE THE PRIOR APPROVAL OF THE BUILDING OFFICIAL. THE |
| REGISTERED DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE |
| SHALL LIST THE DEFERRED SUBMITTALS ON THE CONSTRUCTION |
| DOCUMENTS FOR REVIEW BY THE BUILDING OFFICIAL. |
| DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE |
| SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN |
| RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD |
| THEM TO THE BUILDING OFFICIAL WITH A NOTATION |
| INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE |
| BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO |
| THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL |
| ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED |
| SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE BUILDING |
| OFFICIAL. |
| |
| |
| |
| |