Plan Review Notes
Plan Review Notes For Permit 21041277
Permit Number 21041277
Review Stop G
Sequence Number 1
Notes
Date Text
2021-06-03 16:40:39FBC = FLORIDA BUILDING CODE 2020 7TH EDITION
 WPB FBC = WEST PALM BEACH AMENDMENTS TO THE FBC 2017
 6TH ED, CHAPTER 1
 WPB CCCM=WEST PALM BEACH CROSS-CONNECTION CONTROL
 MANUAL REVISED 2017
 FBC EC = FLORIDA BUILDING CODE ENERGY CONSERVATION 2020
 7TH EDITION
 FBC ACC = FLORIDA ACCESSIBILITY CODE 2020 7TH EDITION
 FBC EX = FLORIDA EXISTING BUILDING CODE 2020 7TH
 EDITION
 FBC PL = FLORIDA PLUMBING CODE 2020 7TH EDITION
 FBC FG = FLORIDA FUEL GAS CODE 2020 7TH EDITION
 NFPA 54 = NATIONAL FUEL GAS CODE
 NFPA 96 = STANDARD FOR VENTILATION CONTROL AND FIRE
 PROTECTION OF COMMERCIAL COOKING OPERATIONS 2017FAC=
 FLORIDA ADMINISTRATIVE CODE
 FS = FLORIDA STATUTES
  
  
 1ST REVIEW
  
 GAS COMMENTS: DENIED
  
 PROVISO: WATER HEATER SCHEDULE INDICATES THAT AN
 ALTERNATE MANUFACTURER MAY BE SUBMITTED TO A/E FOR
 APPROVAL AND USE. PLEASE NOTE THAT A MANUFACTURER?S
 SPECIFICATION INSTALLATION MANUAL SHALL BE SUBMITTED TO
 THE BUILDING DEPARTMENT FOR REVIEW AND APPROVAL AND IF
 DIFFERENT FROM THE CURRENT SCHEDULE A PLAN REVISION
 SHALL BE SUBMITTED TO THE BUILDING DEPARTMENT FOR
 REVIEW AND APPROVAL. BOTH SHALL BE ON SITE FOR FINAL
 INSPECTION.
  
 PROVISO: REGULATOR SCHEDULE INDICATES THAT AN ALTERNATE
 MANUFACTURER MAY BE SUBMITTED TO A/E FOR APPROVAL AND
 USE. PLEASE NOTE THAT A MANUFACTURER?S SPECIFICATION
 INSTALLATION MANUAL SHALL BE SUBMITTED TO THE BUILDING
 DEPARTMENT FOR REVIEW AND APPROVAL AND IF DIFFERENT
 FROM THE CURRENT SCHEDULE A PLAN REVISION SHALL BE
 SUBMITTED TO THE BUILDING DEPARTMENT FOR REVIEW AND
 APPROVAL. BOTH SHALL BE ON SITE FOR FINAL INSPECTION.
  
  
 1.WATER HEATER DETAIL; PER WPB FBC 107.2.1, CLARIFY THE
 FOLLOWING.
 A.SHOWS GAS SUPPLIED FROM FPU TANKS
 B.SHOWS GAS- REGULATOR TO REDUCE PRESSURE TO 2 PSI.
  
 2.SUBMIT CALCULATIONS FOR COMBUSTION AIR (NOT TO BE
 CONFUSED WITH MAKE-UP AIR.) PER FBC FG 304.1
  
 3.GAS RISER: CLEARLY SHOW THE LOCATION OF ALL MP
 (STEP-DOWN) REGULATORS, VALVES AND UNIONS . A LISTED
 SHUTOFF VALVE SHALL BE INSTALLED IMMEDIATELY AHEAD OF
 EACH MP REGULATOR. FBC FG 409.4
  
 4.NOTES ON P0.0 ARE UNCLEAR AS TO INTENT. WHERE DOES
 THE 2PSI SYSTEM END AND THE LESS THAN 2PSI BEGIN. PER
 WPB FBC 107.2.1, CLARIFY. IS A REGULATOR TO BE PROVIDED
 IMMEDIATELY DOWNSTREAM OF THE FPU METER/ REGULATOR TO
 REDUCE PRESSURE AND THEN AN APPLIANCE REGULATOR TO BE
 SUPPLIED AT THE APPLIANCE; PER WPB FBC 107.2.1,
 CLARIFY. PROVIDE TABLES FOR SIZING FOR 2 PSI AS WELL AS
 LESS THAN 2 PSI. CLEARLY INDICATE ON THE PIPING PLAN,
 THE 2 PSI PIPING AND WHICH GAS NOTE (2 OR 7) APPLIES TO
 WHICH SECTIONS OF PIPE.
  
 5.SUBMIT MANUFACTURER?S SPECIFICATION SHEETS /
 INSTALLATION MANUAL FOR ALL GAS EQUIPMENT TO VERIFY
 COMPLIANCE FBC FG 402.2, AND 301.3. GAS APPLIANCES
 SHALL BE LISTED AND LABELED. THE INSTALLATION MANUALS
 FOR ALL GAS APPLIANCES / EQUIPMENT SHALL BE ONSITE AT
 THE TIME OF INSPECTION. FBC FG 305.1
  
 6.GAS RISER: CLEARLY SHOW THE LOCATION OF THE EMERGENCY
 HOOD SHUT DOWN SHUT OFF VALVE SHALL BE BELOW THE
 CEILING. THE MANUAL SHUTOFF VALVE SHALL BE UPSTREAM.
 UNION TO BE DOWN STREAM OF MANUAL VALVE. SECS. 10.4,
 10.5 OF NFPA 96-08. PROVIDE DETAIL.
  
 7.PER WPB FBC 107.2.1, SPECIFY THE UNDERGROUND PIPING
 MATERIAL AND PROVIDE SIZING TABLE.
  
 8.PER WPB FBC 107.2.1, EXPLAIN THE DESIGNATION LNG ON
 THE RISER DIAGRAM. IS THIS LIQUIFIED NATURAL GAS?
 CLARIFY.
  
 9.WHEN ADDING UP THE MBTU IN THE GAS FIXTURE LOAD
 SUMMARY, I COME UP WITH 967 MBH. THE SUMMARY INDICATES
 588 MBH. PER WPB FBC 107.2.1, CLARIFY.
  
 10.PER WPB FBC 107.2.1, SHOW LOCATION OF THE FPU
 METER/REGULATOR ON THE PLAN VIEW.
  
 11.EQUIPMENT SCHEDULE ON P2.0 IS PARTIALLY OBSCURED BY
 A STAMP. PER WPB FBC 107.2.1, REMOVE OR RELOCATE THE
 STAMP SO THAT THE ENTIRE SCHEDULE IS LEGIBLE.
  
  
 END OF COMMENTS.
 PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED
 MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS.
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM. PLEASE, ADDITIONALLY, INSERT
 CORRECTED PAGES INTO TO SUBMITTAL AND REMOVE OR VOID
 THE PREVIOUSLY REVIEWED SHEETS.ALL PLANS TO BE SIGNED
 AND SEALED BY THE DESIGNER AS REQUIRED BY FAC AND FS.
  
  
  
 JERALD SMITH
 PLUMBING PLANS EXAMINER
 CITY OF WEST PALM BEACH
 EMAIL [email protected]
 MOBILE 561-246-0882
 PLEASE NOTE THAT I TYPICALLY WORK ON TUESDAYS AND
 THURSDAYS
  
 21041277 7402 S DIXIE HWY