Date |
Text |
2021-03-18 16:10:13 | PLAN REVIEW BUILDING |
| |
| CHRISTOPHER S. THROOP, C.B.O. |
| PLANS EXAMINER PX3169 1&2 FAMILY SFP306 |
| INSPECTOR BN4338 |
| BUILDING OFFICIAL BU1635 |
| CONSTRUCTION SERVICES DIVISION |
| TEL: 561-805-6726 |
| FAX: 561-805-6676 |
| E-MAIL: [email protected] |
| |
| CODES IN EFFECT: |
| 2020 FLORIDA BUILDING CODE, 7TH EDITION W/2017 WEST |
| PALM BEACH AMENDMENTS TO THE FLORIDA BUILDING CODE, |
| CHAPTER 1 ADMINISTRATION |
| 2017 NEC |
| |
| 1ST REVIEW |
| |
| RESULTS: DENIED |
| ADDRESS THE ATTACHED COMMENTS AND RE-SUBMIT |
| |
| 1. PROVIDE A SURVEY, A SITE PLAN AND SITE DRAINAGE |
| PLAN. |
| |
| FBC R 401.3 (DRAINAGE) |
| FBC 107.2.5 (SITE PLAN) CITY AMENDMENTS |
| |
| PROVIDE A SITE PLAN. DRAINAGE/SURVEY |
| 107.2.5 SITE PLAN. THE CONSTRUCTION DOCUMENTS SUBMITTED |
| WITH THE APPLICATION FOR PERMIT SHALL BE ACCOMPANIED BY |
| A SITE PLAN SHOWING TO SCALE THE SIZE AND LOCATION OF |
| NEW CONSTRUCTION AND EXISTING STRUCTURES ON THE SITE, |
| DISTANCES FROM LOT LINES, THE ESTABLISHED STREET GRADES |
| AND THE PROPOSED FINISHED GRADES, DEPICTING THE |
| PROPOSED LOT DRAINAGE AND, AS APPLICABLE, FLOOD HAZARD |
| AREAS, FLOODWAYS, AND DESIGN FLOOD ELEVATIONS; AND IT |
| SHALL BE DRAWN IN ACCORDANCE WITH AN ACCURATE AND |
| INCLUDED BOUNDARY LINE SURVEY. |
| |
| FBC R401.3 SITE DRAINAGE |
| |
| PROVIDE A SITE DRAINAGE PLAN SHOWING COMPLIANCE WITH |
| FBC R401.3 DRAINAGE. |
| SURFACE DRAINAGE SHALL BE DIVERTED TO A STORM SEWER |
| CONVEYANCE OR OTHER APPROVED POINT OF COLLECTION THAT |
| DOES NOT CREATE A HAZARD. |
| LOTS SHALL BE GRADED TO DRAIN SURFACE WATER AWAY FROM |
| FOUNDATION WALLS. THE GRADE SHALL FALL A MINIMUM OF 6 |
| INCHES WITHIN THE FIRST 10 FEET. |
| |
| 2. PROVIDE A SOILS REPORT OR A COPY OF THE BUILDING PAD |
| CERTIFICATION FROM THE PROJECT GEO-TECHNICAL ENGINEER. |
| |
| FBC 1803.1 GENERAL. GEOTECHNICAL INVESTIGATIONS SHALL |
| BE CONDUCTED IN ACCORDANCE WITH SECTION 1803.2 AND |
| REPORTED IN ACCORDANCE WITH SECTION 1803.6. |
| |
| 1803.2 INVESTIGATIONS REQUIRED. |
| GEOTECHNICAL INVESTIGATIONS SHALL BE CONDUCTED IN |
| ACCORDANCE WITH SECTIONS 1803.3 THROUGH 1803.5. |
| EXCEPTION: THE BUILDING OFFICIAL SHALL BE PERMITTED TO |
| WAIVE THE REQUIREMENT FOR A GEOTECHNICAL INVESTIGATION |
| WHERE SATISFACTORY DATA FROM ADJACENT AREAS IS |
| AVAILABLE THAT DEMONSTRATES AN INVESTIGATION IS NOT |
| NECESSARY FOR ANY OF THE CONDITIONS IN SECTIONS |
| 1803.5.1 THROUGH 1803.5.6 AND SECTIONS 1803.5.10 AND |
| 1803.5.11. |
| |
| 3. PROVIDE FINISHED FLOOR ELEVATION. |
| R403.1.7.3 FOUNDATION ELEVATION. |
| ON GRADED SITES, THE TOP OF ANY EXTERIOR FOUNDATION |
| SHALL EXTEND ABOVE THE ELEVATION OF THE STREET GUTTER |
| AT POINT OF DISCHARGE OR THE INLET OF AN APPROVED |
| DRAINAGE DEVICE A MINIMUM OF 12 INCHES (305 MM) PLUS 2 |
| PERCENT. ALTERNATE ELEVATIONS ARE PERMITTED SUBJECT TO |
| THE APPROVAL OF THE BUILDING OFFICIAL, PROVIDED IT CAN |
| BE DEMONSTRATED THAT REQUIRED DRAINAGE TO THE POINT OF |
| DISCHARGE AND AWAY FROM THE STRUCTURE IS PROVIDED AT |
| ALL LOCATIONS ON THE SITE. |
| |
| |
| |
| PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED |
| MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. |
| |
| |
| |