2021-01-26 10:05:12PLAN REVIEW BUILDING DEMO
  
 2017 FLORIDA BUILDING CODE, 6TH EDITION W/2017 WEST
 PALM BEACH AMENDMENTS TO THE FLORIDA BUILDING CODE,
 CHAPTER 1 ADMINISTRATION
  
 CHRISTOPHER S. THROOP, C.B.O.
 BUILDING PLANS EXAMINER, PX3169
 1&2 FAMILY PLANS EXAMINER, SFP306
 CONSTRUCTION SERVICES DIVISION
 TEL: 561-805-6726
 FAX: 561-805-6676
 E-MAIL: [email protected]
  
  
 DEMO CHECKLIST
  
  
 THE FOLLOWING ITEMS ARE REQUIRED PRIOR TO ISSUANCE OF A
 DEMO PERMIT PER FLORIDA BUILDING CODE, BUILDING 3303:
  
 1. FPL OPEN. RCV'D LETTER FROM GRID ONE ELCTRICAL
 CONTRACTORS ON 1/26/2021. NO DEDICATED METER AT BLDG.
 COMPLETE
  
 2. FPU COMPLETE. RCV'D RELEASE ON 1/26/2021.
  
 3. CITY OF WEST PALM BEACH WATER DEPARTMENT, REQUEST
 FOR METER PULL, ON THEIR FORM "DEMOLITION APPLICATION".
 OPEN AS OF 1/26/2021.
  
 IF A HYDRANT METER OR BACKFLOW PREVENTER IS DESIRED,
 THEN A PARTIAL RELEASE WILL BE NOTED ON THEIR FORM.
  
 FAX THE COMPLETED "DEMOLITION APPLICATION" FORM TO
 561-822-2183. AFTER THEY FAX THE RELEASE TO YOU, SEND A
 COPY VIA EMAIL TO [email protected] WITH THE PERMIT
 NUMBER IN THE SUBJECT LINE.
  
 4. SEWER LATERAL OPEN. PERMIT ISSUED. NO INSPECTION
 SCHEDULED AS OF 1/26/2021.
  
 5. EXTERMINATION LETTER RCV'D ON 1/26/2021 IS NOT
 SIGNED.
  
 6. DEMO DEBRIS FORM: COMPLETE. RCV'D 1/26/2021
  
 7. PROVIDE A SITE PLAN COMPLETE. RCV'D ON 1/26/2021.
  
 8. STORMWATER POLLUTION COMPLETE. RCV'D ON 1/26/2021.
  
 9.ASBESTOS. OPEN. ACKNOWLEDGEMENT LETTER RCV'D ON
 1/26/2021 IS NOT SIGNED.
  
 3,4,5 & 9
  