Date |
Text |
2021-04-15 10:49:59 | NEW SFR |
| REVIEWED BY ROGER MCPHERSON |
| 561-805-6716 |
| [email protected]. |
| CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1 |
| AMENDMENT |
| |
| CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107 |
| 1) 2ND FLOOR ELECTRICAL PLAN SHOWS ONLY CARBON MONOXIDE |
| DETECTORS OUTSIDE THE BEDROOMS - A COMBINATION SMOKE |
| AND CARBON MONOXIDE DETECTOR CAN BE SHOWN - R314.7.4 |
| 2) SHEET 1 WAS NOT REVISED AS NOTED ON THE COMMENT |
| DRAWING. PLEASE SHOW A BATH/TOILET ROOM DOOR WIDTH OF A |
| CLEAR OPENING OF 29 INCHES ON THE FIRST FLOOR TO COMPLY |
| WITH FBC R320.1.1 - FBC ACCESSIBILITY 404.2.3 CLEAR |
| WIDTH. CLEAR OPENINGS OF DOORWAYS WITH SWINGING DOORS |
| SHALL BE MEASURED BETWEEN THE FACE OF THE DOOR AND THE |
| STOP, WITH THE DOOR OPEN 90 DEGREES. |
| 3) SHEET 1 WAS NOT REVISED AS NOTED ON THE COMMENT |
| DRAWING. PLEASE SHOW THE GARAGE CEILING FIRE PROTECTION |
| FROM HABITABLE ROOMS ABOVE THE GARAGE PER FBC R302.6 |
| (5/8 TYPE X DRYWALL). |
| 4) SHEET 1 WAS NOT REVISED AS NOTED ON THE COMMENT |
| DRAWING. PLEASE SHOW THE REQUIRED DRYWALL UNDER THE |
| ENCLOSED STAIR TO COMPLY WITH FBC R302.7 UNDER-STAIR |
| PROTECTION. |
| ENCLOSED SPACE UNDER STAIRS THAT IS ACCESSED BY A DOOR |
| OR ACCESS PANEL SHALL HAVE WALLS, UNDER-STAIR SURFACE |
| AND ANY SOFFITS PROTECTED ON THE ENCLOSED SIDE WITH |
| 1/2-INCH (12.7 MM) GYPSUM BOARD. |
| 5) WINDOW AND DOOR PRODUCT APPROVALS WILL BE DEFERRED |
| AS PER NOTE ON THE DRAWINGS COVER PAGE. |
| 6) PRODUCT APPROVAL PROVIDED FOR THE METAL ROOFING |
| SYSTEM (-82.5) DOES NOT MEET THE REQUIRED WIND DESIGN |
| PRESSURES FOR ROOF WIND ZONES 2R PER DRAWING MARKED |
| COVER PAGE (-102.7) |
| 7) DRAWINGS NEED TO BE SIGNED AND SEALED BY THE |
| ENGINEER. |
| 8) NEED THE ORIGINAL SIGNED AND SEALED SOIL REPORT. |
| SIGNED AND SEALED DRAWINGS IN PROJECTDOX NEED TO BE |
| DIGITALLY/ELECTRONICALLY SIGNED BY THE ENGINEER OR |
| ARCHITECT TO BE USED IN ELECTRONIC PLAN REVIEW. IF YOUR |
| ARCHITECT OR ENGINEER DOES NOT HAVE AN ELECTRONIC OR |
| DIGITAL SIGNATURE - YOU CAN MAIL IN OR DROP OFF THE |
| ORIGINAL SIGNED AND SEALED DRAWINGS/DOCUMENTS TO THE |
| FRONT DESK IN THE BUILDING DEPT. AT THE CITY HALL |
| 9) DRAWINGS SHOW THE ROOFING AND WINDOW AND DOOR |
| PRODUCT APPROVALS ARE TO BE DEFERRED - YET NEW PRODUCT |
| APPROVALS HAVE BEEN SUBMITTED FOR THE ROOFING. IS THE |
| ROOFING TO BE DEFERRED? ROOFING SYSTEM AND WINDOW AND |
| DOOR PRODUCT APPROVALS MAY BE DEFERRED SUBMITTALS BY |
| LISTING ITEMS TO BE DEFERRED ON THE CONSTRUCTION |
| DOCUMENTS - 107.3.4.1 DEFERRED SUBMITTALS. FOR THE |
| PURPOSES OF THIS SECTION, DEFERRED SUBMITTALS ARE |
| DEFINED AS THOSE PORTIONS OF THE DESIGN THAT ARE NOT |
| SUBMITTED AT THE TIME OF THE APPLICATION AND THAT ARE |
| TO BE SUBMITTED TO THE BUILDING OFFICIAL WITHIN A |
| SPECIFIED PERIOD. DEFERRAL OF ANY SUBMITTAL ITEMS SHALL |
| HAVE THE PRIOR APPROVAL OF THE BUILDING OFFICIAL. THE |
| REGISTERED DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE |
| SHALL LIST THE DEFERRED SUBMITTALS ON THE CONSTRUCTION |
| DOCUMENTS FOR REVIEW BY THE BUILDING OFFICIAL. |
| DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE |
| SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN |
| RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD |
| THEM TO THE BUILDING OFFICIAL WITH A NOTATION |
| INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE |
| BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO |
| THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL |
| ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED |
| SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE BUILDING |
| OFFICIAL. |
| |