Plan Review Notes
Plan Review Notes For Permit 21010248
Permit Number 21010248
Review Stop B
Sequence Number 3
Notes
Date Text
2021-04-15 10:49:59NEW SFR
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected].
 CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1
 AMENDMENT
  
 CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107
 1) 2ND FLOOR ELECTRICAL PLAN SHOWS ONLY CARBON MONOXIDE
 DETECTORS OUTSIDE THE BEDROOMS - A COMBINATION SMOKE
 AND CARBON MONOXIDE DETECTOR CAN BE SHOWN - R314.7.4
 2) SHEET 1 WAS NOT REVISED AS NOTED ON THE COMMENT
 DRAWING. PLEASE SHOW A BATH/TOILET ROOM DOOR WIDTH OF A
 CLEAR OPENING OF 29 INCHES ON THE FIRST FLOOR TO COMPLY
 WITH FBC R320.1.1 - FBC ACCESSIBILITY 404.2.3 CLEAR
 WIDTH. CLEAR OPENINGS OF DOORWAYS WITH SWINGING DOORS
 SHALL BE MEASURED BETWEEN THE FACE OF THE DOOR AND THE
 STOP, WITH THE DOOR OPEN 90 DEGREES.
 3) SHEET 1 WAS NOT REVISED AS NOTED ON THE COMMENT
 DRAWING. PLEASE SHOW THE GARAGE CEILING FIRE PROTECTION
 FROM HABITABLE ROOMS ABOVE THE GARAGE PER FBC R302.6
 (5/8 TYPE X DRYWALL).
 4) SHEET 1 WAS NOT REVISED AS NOTED ON THE COMMENT
 DRAWING. PLEASE SHOW THE REQUIRED DRYWALL UNDER THE
 ENCLOSED STAIR TO COMPLY WITH FBC R302.7 UNDER-STAIR
 PROTECTION.
 ENCLOSED SPACE UNDER STAIRS THAT IS ACCESSED BY A DOOR
 OR ACCESS PANEL SHALL HAVE WALLS, UNDER-STAIR SURFACE
 AND ANY SOFFITS PROTECTED ON THE ENCLOSED SIDE WITH
 1/2-INCH (12.7 MM) GYPSUM BOARD.
 5) WINDOW AND DOOR PRODUCT APPROVALS WILL BE DEFERRED
 AS PER NOTE ON THE DRAWINGS COVER PAGE.
 6) PRODUCT APPROVAL PROVIDED FOR THE METAL ROOFING
 SYSTEM (-82.5) DOES NOT MEET THE REQUIRED WIND DESIGN
 PRESSURES FOR ROOF WIND ZONES 2R PER DRAWING MARKED
 COVER PAGE (-102.7)
 7) DRAWINGS NEED TO BE SIGNED AND SEALED BY THE
 ENGINEER.
 8) NEED THE ORIGINAL SIGNED AND SEALED SOIL REPORT.
 SIGNED AND SEALED DRAWINGS IN PROJECTDOX NEED TO BE
 DIGITALLY/ELECTRONICALLY SIGNED BY THE ENGINEER OR
 ARCHITECT TO BE USED IN ELECTRONIC PLAN REVIEW. IF YOUR
 ARCHITECT OR ENGINEER DOES NOT HAVE AN ELECTRONIC OR
 DIGITAL SIGNATURE - YOU CAN MAIL IN OR DROP OFF THE
 ORIGINAL SIGNED AND SEALED DRAWINGS/DOCUMENTS TO THE
 FRONT DESK IN THE BUILDING DEPT. AT THE CITY HALL
 9) DRAWINGS SHOW THE ROOFING AND WINDOW AND DOOR
 PRODUCT APPROVALS ARE TO BE DEFERRED - YET NEW PRODUCT
 APPROVALS HAVE BEEN SUBMITTED FOR THE ROOFING. IS THE
 ROOFING TO BE DEFERRED? ROOFING SYSTEM AND WINDOW AND
 DOOR PRODUCT APPROVALS MAY BE DEFERRED SUBMITTALS BY
 LISTING ITEMS TO BE DEFERRED ON THE CONSTRUCTION
 DOCUMENTS - 107.3.4.1 DEFERRED SUBMITTALS. FOR THE
 PURPOSES OF THIS SECTION, DEFERRED SUBMITTALS ARE
 DEFINED AS THOSE PORTIONS OF THE DESIGN THAT ARE NOT
 SUBMITTED AT THE TIME OF THE APPLICATION AND THAT ARE
 TO BE SUBMITTED TO THE BUILDING OFFICIAL WITHIN A
 SPECIFIED PERIOD. DEFERRAL OF ANY SUBMITTAL ITEMS SHALL
 HAVE THE PRIOR APPROVAL OF THE BUILDING OFFICIAL. THE
 REGISTERED DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE
 SHALL LIST THE DEFERRED SUBMITTALS ON THE CONSTRUCTION
 DOCUMENTS FOR REVIEW BY THE BUILDING OFFICIAL.
 DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE
 SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN
 RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD
 THEM TO THE BUILDING OFFICIAL WITH A NOTATION
 INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE
 BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO
 THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL
 ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED
 SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE BUILDING
 OFFICIAL.
  