2021-01-20 13:34:16 | SFR ADDITION |
| REVIEWED BY ROGER MCPHERSON |
| 561-805-6716 |
| [email protected]. |
| CODE USED FOR REVIEW - 2017 FBC WITH WPB CHAPTER 1 |
| AMENDMENTS |
| |
| CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107 |
| 1) DRAWINGS SHOW THAT DESIGN PER 2017 FBC - PLEASE |
| REVISE THE CODE USED FOR DESIGN TO BE 2020 FBC. |
| 2) JOB VALUE SHOWN ON THE BUILDING PERMIT APPLICATION |
| APPEARS TO BE LOW - PLEASE PROVIDE A SIGNED CONTRACT TO |
| VERIFY THE JOB VALUE SHOWN - 109.3 BUILDING PERMIT |
| VALUATIONS. IF, IN THE OPINION OF THE BUILDING |
| OFFICIAL, THE CLAIMED VALUATION |
| OF BUILDING, ALTERATION, STRUCTURE, ELECTRICAL, GAS, |
| MECHANICAL OR PLUMBING SYSTEMS APPEARS TO BE |
| UNDERESTIMATED ON THE APPLICATION, THE PERMIT SHALL BE |
| DENIED, UNLESS THE APPLICANT CAN SHOW |
| DETAILED, QUANTITY ESTIMATES, AND/OR BONA FIDE SIGNED |
| CONTRACTS (EXCLUDING LAND VALUE) TO MEET THE |
| APPROVAL OF THE BUILDING OFFICIAL. FOR PERMITTING |
| PURPOSES, VALUATION OF BUILDINGS AND SYSTEMS SHALL |
| BE TOTAL REPLACEMENT VALUE TO INCLUDE STRUCTURAL, |
| ELECTRIC, PLUMBING, MECHANICAL, INTERIOR FINISH, |
| RELATIVE SITE WORK, ARCHITECTURAL AND DESIGN FEES, |
| MARKETING COSTS, OVERHEAD AND PROFIT; EXCLUDING |
| ONLY LAND VALUE. VALUATION REFERENCES MAY INCLUDE THE |
| LATEST PUBLISHED DATA OF NATIONAL |
| CONSTRUCTION COST ANALYSIS SERVICES (MARSHALL-SWIFT, |
| MEANS, ETC.), AS PUBLISHED BY INTERNATIONAL |
| CODE CONGRESS. FINAL BUILDING PERMIT VALUATION SHALL BE |
| SET BY THE BUILDING OFFICIAL. |
| 3) PLEASE SHOW THE ROOF SHEATHING ATTACHMENT DETAILS. |
| 4) PLEASE SHOW THE WALL SHEATHING ATTACHMENT DETAILS. |
| 5) PLEASE SHOW THE FLOOR JOIST ON CENTER SPACING. |
| 6) PLEASE SHOW THE FLOOR SHEATHING ATTACHMENT DETAILS. |
| 7) PLEASE SHOW THE ATTIC VENTILATION TO COMPLY WITH FBC |
| R806.1 |
| 8) DRAWING A1.0 SHOWS UTILITY ROOM "MODIFY FOUNDATION" |
| IS THERE A NEW FOUNDATION FOR THE NEW EXTERIOR WALLS |
| FOR THE UTILITY ROOM - PLEASE SHOW FOUNDATION DETAILS. |
| 9) PLEASE SHOW THE LOCATIONS OF THE REQUIRED SMOKE |
| ALARMS THROUGHOUT THE EXISTING HOUSE TO COMPLY WITH FBC |
| R314.2.2 ALTERATIONS, REPAIRS AND ADDITIONS. |
| WHERE ALTERATIONS, REPAIRS OR ADDITIONS REQUIRING A |
| PERMIT OCCUR, OR WHERE ONE OR MORE SLEEPING ROOMS ARE |
| ADDED OR CREATED IN EXISTING DWELLINGS, THE INDIVIDUAL |
| DWELLING UNIT SHALL BE EQUIPPED WITH SMOKE ALARMS |
| LOCATED AS REQUIRED FOR NEW DWELLINGS. |
| 10) PLEASE PROVIDE THE FRONT PAGES OF THE FLORIDA STATE |
| PRODUCT APPROVALS FOR THE FIXED GLASS AND THE SINGLE |
| HUNG WINDOWS (INSTALLATION INSTRUCTIONS HAVE BEEN |
| PROVIDED). |
| 11) ROOFING SYSTEM TO BE USED ON THE PROVIDED PRODUCT |
| APPROVAL REQUIRES ADDITIONAL SIGNED AND SEALED |
| ATTACHMENT DETAILS FROM AN ARCHITECT OR ENGINEER FOR |
| ROOF WIND ZONES 2 AND 3 WHICH REQUIRE A HIGHER PRESSURE |
| THAN THE MAXIMUM SHOWN ON THE PRODUCT APPROVAL (-60) - |
| SEE NOTE NUMBER 9 ON THE PRODUCT APPROVAL. |
| 12) ROOFING AND WINDOW AND DOOR PRODUCT APPROVALS MAY |
| BE DEFERRED SUBMITTALS BY LISTING ITEMS TO BE DEFERRED |
| ON THE CONSTRUCTION DOCUMENTS - 107.3.4.1 DEFERRED |
| SUBMITTALS. FOR THE PURPOSES OF THIS SECTION, DEFERRED |
| SUBMITTALS ARE DEFINED AS THOSE PORTIONS OF THE DESIGN |
| THAT ARE NOT SUBMITTED AT THE TIME OF THE APPLICATION |
| AND THAT ARE TO BE SUBMITTED TO THE BUILDING OFFICIAL |
| WITHIN A SPECIFIED PERIOD. DEFERRAL OF ANY SUBMITTAL |
| ITEMS SHALL HAVE THE PRIOR APPROVAL OF THE BUILDING |
| OFFICIAL. THE REGISTERED DESIGN PROFESSIONAL IN |
| RESPONSIBLE CHARGE SHALL LIST THE DEFERRED SUBMITTALS |
| ON THE CONSTRUCTION DOCUMENTS FOR REVIEW BY THE |
| BUILDING OFFICIAL. DOCUMENTS FOR DEFERRED SUBMITTAL |
| ITEMS SHALL BE SUBMITTED TO THE REGISTERED DESIGN |
| PROFESSIONAL IN RESPONSIBLE CHARGE WHO SHALL REVIEW |
| THEM AND FORWARD THEM TO THE BUILDING OFFICIAL WITH A |
| NOTATION INDICATING THAT THE DEFERRED SUBMITTAL |
| DOCUMENTS HAVE BEEN REVIEWED AND FOUND TO BE IN GENERAL |
| CONFORMANCE TO THE DESIGN OF THE BUILDING. THE DEFERRED |
| SUBMITTAL ITEMS SHALL NOT BE INSTALLED UNTIL THE |
| DEFERRED SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE |
| BUILDING OFFICIAL. |