Plan Review Notes
Plan Review Notes For Permit 20121101
Permit Number 20121101
Review Stop P
Sequence Number 1
Notes
Date Text
2021-04-22 09:02:141) SHT. A-1.3.01 - ONE OF THE TREATMENT ROOMS AND ONE
 OF THE COUPLE'S SUITES AT THE SPA SHALL COMPLY WITH
 FBC-ACCESSIBILITY SEC. 201.1 AND THE SINK IN THESE
 ROOMS SHALL COMPLY WITH FBC-ACCESSIBILITY SECS.212.3,
 606.1.
 2) SHT.A-1.3.01 - THE MEN'S AND WOMEN'S STEAM ROOMS
 (M-1206 & W-1224) SHALL COMPLY WITH THE
 FBC-ACCESSIBILITY SEC.241 & 612. CONTROLS FOR THE STEAM
 ROOM SHALL COMPLY WITH FBC=ACCESS. SEC.309.
 3) SHT. A-1.3.0.7 - THE SIZING OF THE DOWNSPOUTS AND
 GUTTERS IS BASED ON THE GALLONS PER MINUTE FLOW THROUGH
 THE GUTTER AND DOWNSPOUT PER THE FBC-PLUMBING SECS.
 1106.3, 1106.6 AND TABLES 1106.3 & 1106.6. SUBMIT
 SIZING CALLCULATIONS BASED ON THESE TABLES.THE
 DOWNSPOUTS SHALL DISCHARGE A MINIMUM OF 1 FOOT FROM THE
 EXTERIOR BUILDING WALL. FBC-BUILDING SEC. 1503.7. SHOW
 THE DIMENSIONS OF THE GUTTERS & DOWNSPOUTS ON SHTS.
 A-1.3.07 & A-4.4.0.3.
 4) THE PLUMBING SHEETS SHALL BEAR THE DIGITAL SIGNATURE
 AND SEAL OF THE DESIGN PROFESSIONAL PER F.A.C.
 61G15-23.001, 61G15-23.004.
 5) SHT.P-1.1.00 - INDDICATE ON THE PLAN WHAT STANDARD
 WAS USED FOR THE SIZING OF THE GREASE
 INTERCEPTOR.FBC-PLUMBING SECS.1003.2, 1003.3.4,
 6) SHT. P-1.1.00 - SPECIFY ON THE PLAN THE SPECIFIC
 CIVIL DRAWING FOR THE CCONTINUATION OF THE STORM AND
 SANITARY LINES. WPB AMEND. TO FBC SEC. 107.2.1.
 7) SHT. P-1.3.01A - THERE IS A NOTE ON THE PLAN THAT
 STATES "NOT FOR CONSTRUCTION.' CLARIFY.
 8) PLACE MATCHLINES ON THE PLUMBING DRAWINGS FOR THE
 CONTINUATION OF THE PLUMBING SYSTEMS. WPB AMEND. TO FBC
 SEC. 107.2.1.
 9)) SHT. P-1.5.0.1 - ENLARGED GUESTROOM - DOUBLE 7 -
 CLEAN UP THE DRAWING AS THERE ARE SSTRUCTURAL ELEMENT
 OVERLAYS ON THE PLUMBING SYTEM AND IS DIFFICULT TO
 REVIEW. WPB AMEND. TO FBC SEC. 107.2.1.
 10) SHT.P-1.5.04 - DETAIL #2 - THERE ARE SECTIONS OF
 PIPING MISSING FROM YHE SANITARY RISER. CLARIFY.
 11) SHT.P-1.5.05 - THE SANITARY RISER SHOWS THE HAND
 SINKS DISCHARGING TO THE GREASE WASTE SYSTEM. THE HAND
 SINKS SHALL DISCHARGE TO THE SANITARY SYSTEM
 FBC-PLUMBING SEC. 1003.3.1.
 12) SHT. P-1.5.05 - A HOT WATER RECIRCULATION LINE IS
 REQUIRED IN THE BANQUET KITCHEN. FFBC-PLUMBING
 SEC.607.2.
 13) SHT.P-1.05.06 - DETAIL #4 SHOWS AN ISLAND VENT FOR
 A FLLOR SINK. ISLAND VENTS ARE ONLY PERMITTED TO BE
 USED ON SINKS AND LAVATORIES, NOT ON FLOOR
 SINKS.ANOTHER METHOD OF VENTING SHALL BE USED.
 FBC-PLUMBING SEC.916.1.THIS COMMENT APPLIES TO ALL
 FLOOR SINKS WITH AN ISLAND VENT.
 14) SHT. P-1.5.06 - THE COFFEE/TEA BREWERS AND WATER
 FILTER SHALL BE EQUIPPED WITH BACKFLOW DEVICES
 COMPLYING WITH ASSE 1024. THE SODA DISPENSER SHALL BE
 EQUIPPED WITH A BACFLOW PREVENTER COMPLYING WITH ASSE
 1022.
 15) SHT. P-1.5.07 - DETAIL #2 - ENLARGED 1129 KITCHEN -
 THERE IS AN ARROW AT THE TOP LEFT CORNER OF THE PLAN
 THAT STATES "2 INCH FORCE MAIN FROM SUMP PUMP" BUT
 THERE IS NO PIPING SHOWN. CLARIFY.
 16) SHT. P-1.5.07 - DETAILS #2 & #3 - THE HAND SINKS
 SHALL DISCHARGE TO THE SANITARY, NOT TO THE GREASE
 WASTE SYSTEM.FBC-PLUMBING SEC. 1003.3.1.
 17) SHT. P-1.5.07 - DETAILL #4 - ITEM #304 IS NOT SHOWN
 ON THE PRESSURE RISER DIAGRAM. CLARIFY.
 18) SHT. P-1.5.09 - DETAIL #4 - THERE AR SECTIONS OF
 PIPING MISSING FROM THE GRAVITY RISER. REFER TO L-2,
 FLOR DRAINS,SANITARY AND VENT PIPING FOR LAVATORIES.
 CLARIFY.
 19) SHT. P-1.5.10 - DETAIL #4 - WHERE DOES THE DRAIN
 FROM FIXTURE L-2 CONNECT O THE SYSTEM?
 20) SHT. P-1.5.06.1 - DETAIL #4 - ITEMS C202, C203 &
 C204 ARE NOT SHOWN ON THE WATER DISTRIBUTION ISOMETRIC.
 CLARIFY.
 21) SHT. P-1.5.06.1 - DETAIL #1 APPEARS TO SHOW A FLOOR
 SINK IN THE CLUBROOM PANTRY DISCHARGING TO THE
 SANITARY. CLARIFY. WHAT IS BEING DISCHARGED INTO THIS
 FLOOR SINK? ALSO, HAND SINKS SHALL DISCHARGE TO THE
 SANITARY, NOT THE GREASE WASTE SYSTEM.
 22) SHT. P-3.0.00 - SPECIFY THE SPECIFIC CIVIL DRAWING
 ON THE PLAN FOR THE CONTINUATION OF THE 6 INCH SANITARY
 LINE. WPB AMEND. TO FBC SEC. 107.2.1.
 23) SHT. P-3.0.00 - THE RISER DIAGRAM DOES NOT SHOW THE
 BRANCH DRAINS FOR ROOMS F-1108 & M-1107. CLARIFY.
 24) SHT.P-3.0.00 - ONE BRANCCH DRAIN IS SHOWN UPSTREAM
 OF THE GREASE INTERCEPTORS ON THE RISER DIAGRAM BBUT
 TWO ARE SHOWN ON SHT. P-1.3.01A. CLARIFY.
 25) SHT.P-3.0.01 - THE 3 INCH FLOOR SINK ON THE GREASE
 WASTE AND FLOOR DRAIN IN WHAT APPEARS TO BE THE
 DISPENSER AREAARE NOT SHOWN ON SHT. P-1.3.01B. CLARIFY.
 26) SHT. P-3.0.01 SHOWS A 3 INCH FLOOR DRAIN ON THE
 EXTERIOR OF THE BUILDING BY STAIR 3 (#300) DISCHARGING
 TO THE GREASE WASTE SYSTEM. THIS FLOOR DRAIN WILL
 COLLLECT STORMWATER IF IT IS LOCATED ON THE EXTERIOR OF
 THE BUILDING WHICH VIOLATES FBC-PLUMBING SEC.1101.3.
 27) SHT. P-3.0.09 - SPECIFY THE SPECIFIC CIVIL DRAWING
 ON THE PLAN FOR THE CONTINUATION OF THE STORM DRAINS.
 WPB AMEND. TO FBC SEC. 107.2.1.
 28) SHT. P-3.0.09 - THE PIPING IS MISSING FOR THE
 TRENCH DRAINS. CLARIFY.
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  
  
  