Plan Review Notes
Plan Review Notes For Permit 20120803
Permit Number 20120803
Review Stop B
Sequence Number 1
Notes
Date Text
2021-02-10 10:39:02NEW 8 STORY APT AND 6 STORY PARKING GARAGE
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected]
 CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1
 AMENDMENTS
  
 CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107
 1) PLEASE CLARIFY ROOF TRUSS DESIGN - ARCHITECTURAL
 SHOWS METAL TRUSS - STRUCTURAL DRAWINGS SHOW WOOD
 TRUSS.
 2) PLEASE SHOW WALL TO TRUSS STRAPPING DETAILS TO METAL
 OR WOOD TRUSSES.
 3) PLEASE SHOW PLYWOOD ATTACHMENT DETAILS TO METAL
 TRUSSES.
 4) PLEASE SHOW WOOD TRUSSES AS FIRE RETARDANT PER FBC
 603.1
 5) PLEASE SHOW CLEARLY THE REQUIREMENT OF FIRE
 RETARDANT ROOF SHEATHING FBC 603.1
 6) PLEASE SHOW THE FIRE RATING DETAILS FOR THE STEEL
 COLUMNS PER FBC TABLE 601 (2 HRS)
 7) PLEASE SHOW THE GARAGE AS OPEN OR ENCLOSED AND
 PROVIDE THE CALCULATIONS FOR THE OPEN GARAGE PER FBC
 406.5.2 OR VENTILATION REQUIREMENTS FOR ENCLOSED GARAGE
 PER FBC 406.6.2
 8) PLEASE SHOW THE DOOR MANEUVERING CLEARANCE TO OPEN
 THE DOOR FROM THE INSIDE OF ALL DOORS - TO EXIT THE
 UNIT, BATHROOM ETC (18' CLEARANCE BESIDE THE DOOR). FBC
 ACCESSIBILITY FHA REQUIREMENT 3.USABLE DOORS.
 SECTION 100.205(C)(2) PROVIDES THAT COVERED MULTIFAMILY
 DWELLINGS WITH A BUILDING ENTRANCE ON AN ACCESSIBLE
 ROUTE SHALL BE DESIGNED IN SUCH A MANNER THAT ALL THE
 DOORS DESIGNED TO ALLOW PASSAGE BY HANDICAPPED PERSONS
 IN WHEELCHAIRS. ANSI 4.3 ANSI 4.13.6
 9) DRAWING A-4.9 "UNISEX AND POWDER ROOM" KEY NOTES DO
 NOT MATCH THE LEGEND ON THE SAME DRAWING - PLEASE
 CORRECT.
 10) DRAWING A-4.8 - THE FINISH SCHEDULE IS BLANK -
 PLEASE CORRECT.
 11) PLEASE PROVIDE COMPLETE MIAMI DADE OR FLORIDA STATE
 PRODUCT APPROVALS FOR THE EXTERIOR WINDOWS. DOORS AND
 ROOFING SYSTEMS. ALL PRODUCT APPROVALS AND SHOP
 DRAWINGS NEED TO BE REVIEWED AND MARKED APPROVED BY THE
 BUILDING DESIGNER OF RECORD OR LISTED BY PRODUCT
 APPROVAL NUMBER ON THE DRAWINGS.
 12) PLEASE PROVIDE A SIGNED AND SEALED SOIL REPORT AS
 NOTED ON THE DRAWINGS.
 13) PLEASE PROVIDE THE FLOOR/CEILING ACOUSTICAL TEST
 REPORTS - THE FOLLOWING ACOUSTICAL TEST REPORTS ARE
 REQUIRED:
  
 MANUFACTURER SPEC SHEETS ARE NOT ACCEPTABLE DUE TO
 DISCREPANCIES BETWEEN SPEC SHEETS/BROCHURES AND TEST
 REPORTS FOR SOME MANUFACTURERS (NOT NECESSARILY THE
 MANUFACTURER SELECTED; THIS IS A GENERAL COMMENT)
  
 A. FBC 1207.2, FLOOR/CEILING ASSEMBLIES SEPARATING
 DWELLING UNITS FROM EACH OTHER OR FROM PUBLIC OR
 SERVICE AREAS SHALL HAVE A SOUND TRANSMISSION CLASS
 (STC) OF NOT LESS THAN 50 (45 IF FIELD TESTED) FOR AIR
 BORNE NOISE WHEN TESTED IN ACCORDANCE WITH ASTM E 90.
 THE TEST REPORT CANNOT INCLUDE A DROPPED GYPSUM
 CEILING. PROVIDE A COPY OF THE TEST REPORT.
  
 B. FBC 1207.3, FLOOR/CEILING ASSEMBLIES BETWEEN
 DWELLING UNITS OR BETWEEN A DWELLING UNIT AND A PUBLIC
 OR SERVICE AREA WITHIN THE STRUCTURE SHALL HAVE AN
 IMPACT INSULATION CLASS (IIC) RATING OF NOT LESS THAN
 50 (45 IF FIELD TESTED) WHEN TESTED IN ACCORDANCE WITH
 ASTM E 492. THE TEST REPORT CANNOT INCLUDE A DROPPED
 GYPSUM CEILING. PROVIDE A COPY OF THE TEST REPORT.
  
 C. FBC 603.1, ALLOWABLE MATERIALS IN NON COMBUSTIBLE
 BUILDINGS, SEE ITEM 2, EXCEPTION 2, ACOUSTICAL
 INSULATION INSTALLED BETWEEN A FINISHED FLOOR AND SOLID
 DECKING WITHOUT INTERVENING AIRSPACE SHALL BE ALLOWED
 TO HAVE A FLAME SPREAD INDEX OF NOT MORE THAN 200. SEE
 803.1.1, PROVIDE TEST DATA IN ACCORDANCE WITH ASTM E 84
 OR UL 723.
  
 14) JOB VALUE SHOWN ON THE BUILDING PERMIT APPLICATION
 APPEARS TO BE LOW - PLEASE PROVIDE A CONTRACT, COST
 BREAKDOWN ETC TO VERIFY THE JOB VALUE SHOWN ON THE
 BUILDING PERMIT APPLICATION - FBC WPB AMENDMENTS ? FOR
 PERMITTING PURPOSES THE VALUE OF ALL LABOR AND
 MATERIALS REQUIRED TO COMPLETE THE PROJECT ARE REQUIRED
 TO BE INCLUDED IN THE COST. FBC 109.3 BUILDING PERMIT
 VALUATION. FOR PERMITTING PURPOSES, VALUATION OF
 BUILDINGS AND SYSTEMS SHALL BE TOTAL REPLACEMENT VALUE
 TO INCLUDE STRUCTURAL, ELECTRIC, PLUMBING, MECHANICAL,
 INTERIOR FINISH, RELATIVE SITE WORK, ARCHITECTURAL AND
 DESIGN FEES, MARKETING COST, OVERHEAD AND PROFIT;
 EXCLUDING ONLY LAND VALUE. VALUATION REFERENCES MAY
 INCLUDE THE LATEST PUBLISHED DATA OF NATIONAL
 CONSTRUCTION COST ANALYSIS SERVICES (MARSHALL ? SWIFT,
 MEANS, ETC.) AS PUBLISHED BY INTERNATIONAL CODE
 CONGRESS. FINAL BUILDING PERMIT VALUATION SHALL BE SET
 BY THE BUILDING OFFICIAL.
 15) PLEASE FILL OUT THE THRESHOLD INSPECTOR FORMS AND
 PROVIDE THE REQUIRED DOCUMENTS - SEE THE "GUIDELINES
 AND POLICIES FOR PROJECTS CONCERNING THRESHOLD/SPECIAL
 INSPECTORS AND RESIDENT INSPECTORS" - YOU CAN EMAIL
 ([email protected]) FOR A COPY OF THE GUIDELINES.
 16) ROOFING SYSTEMS, WINDOW / DOOR PRODUCT APPROVALS
 AND FLOOR/CEILING ASSEMBLY ACOUSTICAL TEST REPORTS MAY
 BE DEFERRED SUBMITTALS BY LISTING ITEMS TO BE DEFERRED
 ON THE CONSTRUCTION DOCUMENTS - FBC WPB 107.3.4.1
 DEFERRED SUBMITTALS. FOR THE PURPOSES OF THIS SECTION,
 DEFERRED SUBMITTALS ARE DEFINED AS THOSE PORTIONS OF
 THE DESIGN THAT ARE NOT SUBMITTED AT THE TIME OF THE
 APPLICATION AND THAT ARE TO BE SUBMITTED TO THE
 BUILDING OFFICIAL WITHIN A SPECIFIED PERIOD. DEFERRAL
 OF ANY SUBMITTAL ITEMS SHALL HAVE THE PRIOR APPROVAL OF
 THE BUILDING OFFICIAL. THE REGISTERED DESIGN
 PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST THE
 DEFERRED SUBMITTALS ON THE CONSTRUCTION DOCUMENTS FOR
 REVIEW BY THE BUILDING OFFICIAL. DOCUMENTS FOR DEFERRED
 SUBMITTAL ITEMS SHALL BE SUBMITTED TO THE REGISTERED
 DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE WHO SHALL
 REVIEW THEM AND FORWARD THEM TO THE BUILDING OFFICIAL
 WITH A NOTATION INDICATING THAT THE DEFERRED SUBMITTAL
 DOCUMENTS HAVE BEEN REVIEWED AND FOUND TO BE IN GENERAL
 CONFORMANCE TO THE DESIGN OF THE BUILDING. THE DEFERRED
 SUBMITTAL ITEMS SHALL NOT BE INSTALLED UNTIL THE
 DEFERRED SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE
 BUILDING OFFICIAL.
  


Account Summary | Usage Policy | Privacy Policy