2021-02-22 13:57:35NEW 8 STORY APT BUILDING
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected]
 CODE USED FOR REVIEW - 2017 FBC WITH WPB CHAPTER 1
 AMENDMENTS
  
 CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107
 1) PLEASE SHOW THE PROTECTED OPENING CALCULATIONS FOR
 THE NORTH EAST CORNER OF THE APT BUILDING PER FBC 705.8
 2) PLEASE SHOW THE TRASH CHUTE (ROOM OR COMPARTMENT)
 WALL AND DOOR FIRE RATING FROM THE CORRIDORS PER FBC
 713.13.3 CHUTE ACCESS ROOMS.
 ACCESS OPENINGS FOR WASTE OR LINEN CHUTES SHALL BE
 LOCATED IN ROOMS OR COMPARTMENTS ENCLOSED BY NOT LESS
 THAN 1-HOUR FIRE BARRIERS CONSTRUCTED IN ACCORDANCE
 WITH SECTION 707 OR HORIZONTAL ASSEMBLIES CONSTRUCTED
 IN ACCORDANCE WITH SECTION 711, OR BOTH. OPENINGS INTO
 THE ACCESS ROOMS SHALL BE PROTECTED BY OPENING
 PROTECTIVES HAVING A FIRE PROTECTION RATING OF NOT LESS
 THAN 3/4 HOUR. DOORS SHALL BE SELF- OR
 AUTOMATIC-CLOSING UPON THE DETECTION OF SMOKE IN
 ACCORDANCE WITH SECTION 716.5.9.3.
 3) DRAWING S-3.1 SHOW BEAM ELEVATION USING NGVD OTHER
 DRAWINGS USE NAVD ELEVATIONS - PLEASE CLARIFY.
 4) DRAWING A-3.10 SHOWS THE GARAGE FLOOR ELEVATION AT
 50' 6" AND THE PARAPET HEIGHT AT 53' - DOES NOT MEET
 THE REQUIRED GUARD HEIGHT PER FBC 1015.3
 5) DRAWING A-5.1 SHOULD SHOW A GUARD RAIL AT SECTION
 "B" - FBC 1015
 6) PLEASE PROVIDE A HANDRAIL DETAIL FOR THE RAMPS FBC
 1012.8
 7) PLEASE SHOW THE POOL AREA AND THE OUTSIDE A3
 PAVILION/MULTI PURPOSE LAWN EXIT GATE WIDTHS FBC
 1010.1.1 AND OPENING HARDWARE TO COMPLY WITH FBC
 1010.1.9.1 - 1010.1.10 PANIC AND FIRE EXIT HARDWARE.
 DOORS SERVING A GROUP H OCCUPANCY AND DOORS SERVING
 ROOMS OR SPACES WITH AN OCCUPANT LOAD OF 50 OR MORE IN
 A GROUP A OR E OCCUPANCY SHALL NOT BE PROVIDED WITH A
 LATCH OR LOCK OTHER THAN PANIC HARDWARE OR FIRE EXIT
 HARDWARE.
 8) PLEASE SHOW THE DISCERNIBLE PATH THROUGH THE OUTDOOR
 FITNESS GYM AREA FROM THE OUTDOOR PAVILION/COURT YARD
 AREA FBC 1016.2 EGRESS THROUGH INTERVENING SPACES. (2.)
 EGRESS FROM A ROOM OR SPACE SHALL NOT PASS THROUGH
 ADJOINING OR INTERVENING ROOMS OR AREAS, EXCEPT WHERE
 SUCH ADJOINING ROOMS OR AREAS AND THE AREA SERVED ARE
 ACCESSORY TO ONE OR THE OTHER, ARE NOT A GROUP H
 OCCUPANCY AND PROVIDE A DISCERNIBLE PATH OF EGRESS
 TRAVEL TO AN EXIT.
 9) APT UNIT B3 SHOWN ON DRAWING A-10.2 - BATH TYPE "B"
 PLEASE SHOW THE 30X48 DOOR SWING CLEAR FLOOR SPACE FBC
 ACCESSIBILITY FHA REQUIREMENT NUMBER 7 USEABLE
 BATHROOMS - (I)WHERE THE DOOR SWINGS INTO THE BATHROOM,
 THERE IS A CLEAR SPACE (APPROXIMATELY 2?6" BY 4?0")
 WITHIN THE ROOM TO POSITION A WHEELCHAIR OR OTHER
 MOBILITY AID CLEAR OF THE PATH OF THE DOOR AS IT IS
 CLOSED AND TO PERMIT USE OF FIXTURES. THIS CLEAR SPACE
 CAN INCLUDE ANY KNEESPACE AND TOESPACE AVAILABLE BELOW
 BATHROOM FIXTURES.
 10) APT. UNIT B1 SHOWN ON DRAWING A-10.2 - THE SHOWER
 DOOR SHOULD BE ON THE OPPOSITE SIDE TO ALLOW THE SHOWER
 CONTROLS TO BE REACHED FROM OUTSIDE THE SHOWER FBC
 ACCESSIBILITY FHA REQUIREMENT NUMBER 7 USEABLE
 BATHROOMS (VII)STALL SHOWERS IN THE BATHROOM MAY BE OF
 ANY SIZE OR CONFIGURATION. A MINIMUM CLEAR FLOOR SPACE
 2'6" WIDE BY 4'0" SHOULD BE AVAILABLE OUTSIDE THE
 STALL. (SEE FIGURE FHAG-7(D).)
 11) ALL UNIT DOORS - PLEASE SHOW THE REQUIRED
 MANEUVERING SPACE (18" BESIDE THE DOOR) TO EXIT THE
 UNIT OR ROOM. FBC ACCESSIBILITY FHA REQUIREMENT ANSI
 4.13.6
 12) PLEASE PROVIDE AN ORIGINAL SIGNED AND SEALED COPY
 OF THE SOIL REPORT.
 13) PLEASE PROVIDE COMPLETE COPIES OF THE EXTERIOR
 WINDOWS, DOORS, LOUVERS ETC AS LISTED ON THE DRAWINGS.
 14) PLEASE PROVIDE COMPLETE COPIES OF THE ROOFING
 SYSTEM PRODUCT APPROVALS.
 15) ALL PRODUCT APPROVALS NEED TO BE REVIEWED AND
 MARKED APPROVED BY THE BUILDING DESIGNER OF RECORD OR
 BE LISTED ON THE DRAWINGS.
 16) PLEASE PROVIDE THE FOLLOWING ACOUSTICAL TEST
 REPORTS
 A. FBC 1207.2, FLOOR/CEILING ASSEMBLIES SEPARATING
 DWELLING UNITS FROM EACH OTHER OR FROM PUBLIC OR
 SERVICE AREAS SHALL HAVE A SOUND TRANSMISSION CLASS
 (STC) OF NOT LESS THAN 50 (45 IF FIELD TESTED) FOR AIR
 BORNE NOISE WHEN TESTED IN ACCORDANCE WITH ASTM E 90.
 THE TEST REPORT CANNOT INCLUDE A DROPPED GYPSUM
 CEILING. PROVIDE A COPY OF THE TEST REPORT.
  
 B. FBC 1207.3, FLOOR/CEILING ASSEMBLIES BETWEEN
 DWELLING UNITS OR BETWEEN A DWELLING UNIT AND A PUBLIC
 OR SERVICE AREA WITHIN THE STRUCTURE SHALL HAVE AN
 IMPACT INSULATION CLASS (IIC) RATING OF NOT LESS THAN
 50 (45 IF FIELD TESTED) WHEN TESTED IN ACCORDANCE WITH
 ASTM E 492. THE TEST REPORT CANNOT INCLUDE A DROPPED
 GYPSUM CEILING. PROVIDE A COPY OF THE TEST REPORT.
  
 C. FBC 603.1, ALLOWABLE MATERIALS IN NON COMBUSTIBLE
 BUILDINGS, SEE ITEM 2, EXCEPTION 2, ACOUSTICAL
 INSULATION INSTALLED BETWEEN A FINISHED FLOOR AND SOLID
 DECKING WITHOUT INTERVENING AIRSPACE SHALL BE ALLOWED
 TO HAVE A FLAME SPREAD INDEX OF NOT MORE THAN 200. SEE
 803.1.1, PROVIDE TEST DATA IN ACCORDANCE WITH ASTM E 84
 OR UL 723.
  
 17) PLEASE PROVIDE THE REQUIRED THRESHOLD INSPECTION
 FORMS AND DOCUMENTS DESCRIBED IN "GUIDELINES AND
 POLICIES FOR PROJECTS CONCERNING THRESHOLD/SPECIAL
 INSPECTORS AND RESIDENT INSPECTORS". PLEASE E MAIL
 ([email protected]) FOR A COPY OF THE GUIDELINES.
 18) TOWNHOUSE BUILDING, PAVILION, POOL AND FENCING
 SHALL BE A SEPARATE PERMIT - PLEASE ACKNOWLEDGE THIS.
 19) PLEASE USE A DIFFERENT LANGUAGE FOR THE TOWNHOUSE
 BUILDING - TOWNHOUSE AS DEFINED IN THE FBC - [A]
 TOWNHOUSE. A SINGLE-FAMILY DWELLING UNIT NOT EXCEEDING
 THREE STORIES IN HEIGHT CONSTRUCTED IN A GROUP OF TWO
 OR MORE ATTACHED UNITS WITH PROPERTY LINES SEPARATING
 SUCH UNITS IN WHICH EACH UNIT EXTENDS FROM THE
 FOUNDATION TO ROOF AND WITH A YARD OR PUBLIC WAY ON NOT
 LESS THAN TWO SIDES.
 20) LIFE SAFETY PLAN SHOWS THE SAME SQUARE FOOTAGE FOR
 FLOOR 3 AND 4 - NOT CORRECT 4TH FLOOR AND ABOVE SHOULD
 BE LESS - PLEASE SHOW THE CORRECT SQUARE FOOTAGE FOR
 EACH FLOOR. SHOW THE GARAGE SQUARE FOOTAGE FOR EACH
 FLOOR SEPARATELY.
 21) PLEASE CLEARLY SHOW THE REQUIRED POOL BARRIER AND
 ALL COMPONENTS GATES, LOCKS, HARDWARE, DOOR OPERATION
 FROM BUILDING ETC TO COMPLY WITH FBC 454.1.3.1.9
 22) ROOFING SYSTEMS, WINDOW, DOOR AND LOUVER PRODUCT
 APPROVALS MAY BE DEFERRED SUBMITTALS BY LISTING ITEMS
 TO BE DEFERRED ON THE CONSTRUCTION DOCUMENTS -
 107.3.4.1 DEFERRED SUBMITTALS. FOR THE PURPOSES OF THIS
 SECTION, DEFERRED SUBMITTALS ARE DEFINED AS THOSE
 PORTIONS OF THE DESIGN THAT ARE NOT SUBMITTED AT THE
 TIME OF THE APPLICATION AND THAT ARE TO BE SUBMITTED TO
 THE BUILDING OFFICIAL WITHIN A SPECIFIED PERIOD.
 DEFERRAL OF ANY SUBMITTAL ITEMS SHALL HAVE THE PRIOR
 APPROVAL OF THE BUILDING OFFICIAL. THE REGISTERED
 DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST
 THE DEFERRED SUBMITTALS ON THE CONSTRUCTION DOCUMENTS
 FOR REVIEW BY THE BUILDING OFFICIAL. DOCUMENTS FOR
 DEFERRED SUBMITTAL ITEMS SHALL BE SUBMITTED TO THE
 REGISTERED DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE
 WHO SHALL REVIEW THEM AND FORWARD THEM TO THE BUILDING
 OFFICIAL WITH A NOTATION INDICATING THAT THE DEFERRED
 SUBMITTAL DOCUMENTS HAVE BEEN REVIEWED AND FOUND TO BE
 IN GENERAL CONFORMANCE TO THE DESIGN OF THE BUILDING.
 THE DEFERRED SUBMITTAL ITEMS SHALL NOT BE INSTALLED
 UNTIL THE DEFERRED SUBMITTAL DOCUMENTS HAVE BEEN
 APPROVED BY THE BUILDING OFFICIAL.
  
  
  
  