Plan Review Notes For Permit 20120697 |
Permit Number |
20120697 |
|
Review Stop |
B |
Sequence Number |
2 |
|
Notes |
Date |
Text |
2021-01-12 08:21:20 | PLAN | | REVIEW COMMENTS | | | | 2ND REVIEW: FBC SIXTH EDITION (2017) | | ROBERT MCDOUGAL, CBO | | COMMERCIAL COMBINATION PLANS EXAMINER | | (561) 805-6714 | | [email protected] | | | | DENIED BY BUILDING | | PLEASE ADDRESS THE ITEMS NOTED BELOW: | | | | THE FOLLOWING COMMENT WAS NOT ADDRESSED. PLEASE CORRECT | | THE SPANS FOR THE OPENINGS ON THE INSTALLATION SCHEDULE | | FOR THE ARMOR SCREEN. | | | | 1) THE SPAN FOR THE ARMOR SCREEN IS SPECIFIED AS 80" | | FOR ALL OF THE OPENINGS IN THE STORM PANEL SCHEDULE. | | THE SPAN FOR THE FABRIC SCREENS IS THE CENTER TO CENTER | | DISTANCE BETWEEN THE GROMMETS (ANCHORS) ON EACH SIDE OF | | THE OPENING. PLEASE CORRECT. | | | | |
|