Plan Review Notes
Plan Review Notes For Permit 20110914
Permit Number 20110914
Review Stop G
Sequence Number 1
Notes
Date Text
2020-12-22 11:12:2212/22/20 1ST GAS REVIEW**DENIED** WITH COMMENTS
  
 NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS
 TIME, AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE
 GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS.
  
 1. CITY RECORDS SHOW AN EXISTING GAS SYSTEM AT THIS
 PROPERTY. THE BTU LOAD OF THE CURRENT GAS SYSTEM MUST
 BE ADDED TO THE TOTAL BTU LOAD ON THE SYSTEM TO ENSURE
 THE EXISTING SYSTEM IS SIZED CORRECTLY. IF UNDERSIZED,
 THE EXISTING SYSTEM MUST BE REDONE TO ENSURE A SAFE
 OPERATING SYSTEM. SUBMIT A GAS PIPING RISER DIAGRAM
 THAT SHOWS THE TYPE OF EXISTING APPLIANCE, THE BTU LOAD
 OF EACH APPLIANCE, THE PIPE SIZE AND TYPE OF PIPE TO
 EACH APPLIANCE, AND THE DISTANCE OF THE LONGEST LENGTH
 OF PIPING FROM THE POINT OF DELIVERY TO THE MOST REMOTE
 OUTLET AND THE LOAD OF THE SECTION. NOTE: IF THE
 EXISTING SYSTEM IS PRESSURE IS 2 PSI, A LINE PRESSURE
 REGULATOR IS REQUIRED AT ALL THE EXISTING APPLIANCES
 PER THE 2017 FBC R SECS. G2412.4, G2412.8, G2413.1,
 G2413.2, G2413.3.
  
 2 INDICATE THE PLAN IN WHICH THE GAS CODE'S SIZING
 TABLES ARE BEING USED FOR THE SYSTEM PER THE WPB
 AMENDMENTS TO THE FBC SEC. 107.2.1 INFORMATION ON
 CONSTRUCTION DOCUMENTS.
  
 3. THE TYPE OF PIPE MENTION IS NOT APPROVED TO BE
 INSTALLED UNDERGROUND. YOU MAY USE TRAC PIPE OR PE FOR
 UNDERGROUND AND CSST OR METAL PIPE ABOVE GROUND, SO
 PLEASE CLARIFY PER THE WPB AMENDMENTS TO THE FBC SEC.
 107.2.1 INFORMATION ON CONSTRUCTION DOCUMENTS.
  
 4. GAS RISER DIAGRAM REQUIRED, SO PLEASE SUBMIT AN
 ISOMETRIC DRAWING THAT CLEARLY SHOWS THE LENGTH OF ALL
 CUT SECTIONS OF PIPE PER 2017 FBC RES. SECS. G2413.4.1,
 G2413.4.2.
  
 5. SHOW THE TYPE OF PIPE MATERIAL BEING USED, ALL PIPE
 SIZES, AND THE CORRESPONDING EHD NUMBER OF THE
 CORRUGATED STAINLESS-STEEL OR TRAC PIPE TUBING (IF
 APPLICABLE) FOR EACH PIPE SIZE PER THE WPB AMENDMENTS
 TO THE FBC SEC.107.2.1 INFORMATION ON CONSTRUCTION
 DOCUMENTS.
 6. A LICENSED CONTRACTOR MUST REQUIRE A SUB GAS PERMIT
 FOR THE SCOPE OF WORK PER THE WPB AMENDMENTS TO THE FBC
 SEC. 105.1.
  
 7. TYPE OF GAS (LP OR NATURAL) PER THE WPB AMENDMENTS
 TO THE FBC SEC. 107.2.1 INFORMATION ON CONSTRUCTION
 DOCUMENTS.
  
 8. SHOW ALL MP (STEP-DOWN) REGULATORS' LOCATION. A
 LISTED SHUTOFF VALVE SHALL BE INSTALLED IMMEDIATELY
 AHEAD OF EACH MP REGULATOR. 2017 FBC RES. SEC. G2420.4.
  
 9. SHOW THE DISTANCE FROM THE POINT OF DELIVERY (GAS
 METER / MP REGULATOR / LP TANK) TO THE MOST REMOTE
 OUTLET IN THE BUILDING AND OR SYSTEM PER THE 2017 FBC
 RES. SEC. G2413.4.1.
  
 10. IF THIS TANKLESS UNIT CALL FOR A 10.5" WATER COLUMN
 AND THE SERVICE METER DISCHARGES IS A 12" WATER COLUMN
 REQUIRING A REGULATOR FOR THIS UNIT AS PER
 MANUFACTURER'S SPECIFICATION. SUBMIT MANUFACTURER'S
 SPECIFICATIONS FOR THE PRESSURE REGULATORS. REGULATORS
 INSTALLED ON THE BUILDING'S EXTERIOR SHALL BE APPROVED
 FOR OUTDOOR INSTALLATION PER THE 2017 FBC RES. SEC.
 G2421.1.
  
 10. INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM
 ON THE PLAN PER THE 2017 FBC RES. SEC. G2413.2.
  
 11. SUBMIT MANUFACTURER'S SPECIFICATION
 SHEETS/INSTALLATION MANUAL FOR GAS TANK-LESS TO VERIFY
 COMPLIANCE WITH 2017 FBC RES. SEC. G2408.1.
  
 12. PLEASE SHOW ALL REGULATORS, UNIONS IN FRONT OF
 REGULATOR 1' OF EITHER SIDE, DRIP LEG, LABEL SHUT OFF
 VALVES WITH THEM LABELED PER THE 2017 FBC RES. SEC
 G2421.2
  
 13. ON THE PLAN, PLEASE THE LOCATION OF THE TANK-LESS
 WATER HEATER AND THE LOCATION AND DISTANCE OF ANY
 OPERABLE DOORS OR WINDOWS IN RELATION TO THE WATER
 HEATER. THE LOCATION OF THE WATER HEATER SHALL COMPLY
 WITH THE MANUFACTURER'S INSTALLATION INSTRUCTIONS. THE
 HOUSE PLAN CAN BE HAND-DRAWN PER THE WPB AMENDMENTS TO
 THE FBC SEC. 107.2.1. INFORMATION ON CONSTRUCTION
 DOCUMENTS.
  
 NOTE: YOU MAY CHOOSE TO HAVE A GAS REVIEW DONE THIS
 TIME AND ADDRESS THE COMENTS ABOVE. THIS WILL HAVE THE
 GAS APPROVE FOR A SUB PERMIT, OR IF YOU DECIDED NOT TO
 ADDRESS THESE COMMENTS, PLEASE PUT A NOTE ON THE GAS
 HEATER ( A SEPARATE PERMIT BY A LICENSED CONTRACTOR FOR
 THE GAS SYSTEM). THEN PLEASE TAKE OFF ANY GAS SHOWN ON
 PLANS; THESE COMMENTS CAN BE FORWARD TO THE GAS
 CONTRACTOR FOR REFERENCE. AN N WILL BE PUT ON THIS
 REVIEW, WHICH STANDS FOR NOT REQUIRED BUT, A SUB PERMIT
 WON'T BE ISSUED UNIT A REVIEW IS DONE FOR THAT SUB
 PERMIT, SO PLEASE BE ADVISED ON THIS PROCEDURE.
  
 WHEN RESUBMITTING PLANS, PLEASE INDICATE THE REVISION &
 REMOVE ANY VOIDED SHEETS & REPLACE ANY NECESSARY PAGES.
 A TRANSMITTAL LETTER LISTING THE ORIGINAL REVIEW
 COMMENT NUMBER, WITH A DESCRIPTION OF THE REVISION
 MADE, IDENTIFYING THE SHEET OR SPECIFICATION PAGE WHERE
 THE CHANGES CAN BE FOUND WILL HELP TO EXPEDITE YOUR
 PERMIT. THANK YOU FOR YOUR ANTICIPATED COOPERATION.
  
 HTTPS://CODES.ICCSAFE.ORG/CODES/FLORIDA
  
 LUIS A. CRESPO
 PLUMBING PLAN EXAMINER / INSPECTOR