2021-02-04 15:37:02NEW SFR
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected].
 CODE USED FOR REVIEW - 2017 FBC WITH WPB CHAPTER 1
 AMENDMENTS
  
 CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107
 1) ONLY ROOMS USED FOR "STORAGE", "PARKING", AND
 "BUILDING ACCESS" CAN HAVE THE FLOOR ELEVATION BELOW
 THE "LOWEST FLOOR" ELEVATION. THE ROOM MARKED
 "MECHANICAL ROOM" WILL NEED TO HAVE THE LOWEST FLOOR
 ELEVATION AT 8.00 NAVD - FLOOD ZONE IS SHOWN ON DRAWING
 A-003 AS AE 6 - THE BUILDING "LOWEST FLOOR" (FBC
 R322.1.5) WILL NEED TO BE 8.00 NAVD PER CITY ORDINANCE
 4729-17 SEC. 18-33 (1). BUILDINGS AND STRUCTURES IN
 FLOOD HAZARD AREAS NOT DESIGNATED AS COASTAL A ZONES
 SHALL HAVE THE LOWEST FLOORS ELEVATED TO OR ABOVE THE
 BASE FLOOD ELEVATION PLUS TWO FEET OR THE DESIGN FLOOD
 ELEVATION, WHICHEVER IS HIGHER. (IF THE ROOM
 DESIGNATION IS CHANGED TO "STORAGE" IT CAN REMAIN AT
 THE PROPOSED FLOOR ELEVATION BUT WILL REQUIRE FLOOD
 VENTS - YOU WILL NEED TO SHOW THAT THE AC EQUIPMENT
 WILL BE ELEVATED TO THE REQUIRED ELEVATION FBC R322.1.6
 - YOU MAY ALSO NEED TO REVISE THE ELEVATION CERTIFICATE
 IF YOU ADD MORE FLOOD VENTS)
 2) PLEASE PROVIDE COMPLETE MIAMI DADE OR FLORIDA STATE
 PRODUCT APPROVAL FOR THE OVERHEAD GARAGE DOOR THAT IS
 LISTED BY PRODUCT APPROVAL NUMBER ON THE DRAWINGS.
 3) PLEASE PROVIDE A COMPLETE MIAMI DADE OR FLORIDA
 STATE METAL ROOFING PRODUCT APPROVAL FOR THE METAL
 ROOFING PRODUCT APPROVAL LISTED ON THE DRAWINGS.
 4) PRODUCT APPROVAL FOR THE FLAT DECK ROOFING = PLEASE
 CIRCLE THE ROOFING SYSTEM TO BE USED IN THE PRODUCT
 APPROVAL - IF NEEDED PLEASE PROVIDE SIGNED AND SEALED
 ADDITIONAL ATTACHMENT DETAILS FROM AN ARCHITECT OR
 ENGINEER FOR THE ROOF ZONES 2 AND 3 WHICH MAY REQUIRE A
 HIGHER WIND PRESSURE - SEE NOTES ON THE PRODUCT
 APPROVAL.
 5) PRODUCT APPROVAL FOR THE MULL BAR (18-0205.05) HAS
 EXPIRED - PLEASE PROVIDE AN UPDATED MULL BAR PRODUCT
 APPROVAL.
 6) DRAWING "C1" SHOWS THE FFE AT 7.63 NAVD - PLEASE
 REVISE AS THE FLOOR PLANS WERE REVISED TO SHOW 8.13
 NAVD
  
 7) ROOFING SYSTEM AND WINDOW AND DOOR PRODUCT APPROVALS
 MAY BE DEFERRED SUBMITTALS BY LISTING ITEMS TO BE
 DEFERRED ON THE CONSTRUCTION DOCUMENTS - 107.3.4.1
 DEFERRED SUBMITTALS. FOR THE PURPOSES OF THIS SECTION,
 DEFERRED SUBMITTALS ARE DEFINED AS THOSE PORTIONS OF
 THE DESIGN THAT ARE NOT SUBMITTED AT THE TIME OF THE
 APPLICATION AND THAT ARE TO BE SUBMITTED TO THE
 BUILDING OFFICIAL WITHIN A SPECIFIED PERIOD. DEFERRAL
 OF ANY SUBMITTAL ITEMS SHALL HAVE THE PRIOR APPROVAL OF
 THE BUILDING OFFICIAL. THE REGISTERED DESIGN
 PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST THE
 DEFERRED SUBMITTALS ON THE CONSTRUCTION DOCUMENTS FOR
 REVIEW BY THE BUILDING OFFICIAL. DOCUMENTS FOR DEFERRED
 SUBMITTAL ITEMS SHALL BE SUBMITTED TO THE REGISTERED
 DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE WHO SHALL
 REVIEW THEM AND FORWARD THEM TO THE BUILDING OFFICIAL
 WITH A NOTATION INDICATING THAT THE DEFERRED SUBMITTAL
 DOCUMENTS HAVE BEEN REVIEWED AND FOUND TO BE IN GENERAL
 CONFORMANCE TO THE DESIGN OF THE BUILDING. THE DEFERRED
 SUBMITTAL ITEMS SHALL NOT BE INSTALLED UNTIL THE
 DEFERRED SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE
 BUILDING OFFICIAL.
  
  
  