2020-11-30 16:06:45 | 1ST REVIEW FBC-2017 RES. |
| PERMIT- 20110342 |
| 11/30/2020 |
| |
| CODES IN EFFECT: |
| FBC RES- FLORIDA RESIDENTIAL BUILDING CODE SIXTH |
| EDITION 2017 |
| FBC P- FLORIDA PLUMBING CODE SIXTH EDITION 2017 |
| FBC B- FLORIDA BUILDING CODE SIXTH EDITION 2017 |
| FBC M- FLORIDA MECHANICAL CODE SIXTH EDITION 2017 |
| FBC EC- FLORIDA ENERGY CONSERVATION CODE SIXTH EDITION |
| 2017 |
| FBC FG- FLORIDA FUEL GAS CODE SIXTH EDITION 2017 |
| FBC EX- FLORIDA EXISTING BUILDING CODE SIXTH |
| FS- FLORIDA STATUTES |
| FAC- FLORIDA ADMINISTRATIVE CODE |
| WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH |
| EDITION 2017 |
| |
| PLAN REVIEW RESULTS: DENIED. |
| |
| 1) PLEASE NOTE SEPARATE PERMITS ARE REQUIRED FOR THE |
| GAS PIPING, WATER SERVICE BACKFLOW PREVENTER, POOL, AND |
| IRRIGATION SYSTEM- SECTIONS 105.1 & 107.2.1 WPB. |
| COMPLETE PLANS AND SPECIFICATIONS ARE REQUIRED. |
| |
| A) THE GAS PIPING LAYOUT AND RISER DRAWING SHOWN ON THE |
| PLANS WERE NOT REVIEWED AT THIS TIME. PLEASE SUBMIT THE |
| DRAWINGS UNDER A SEPARATE PERMIT AND INCLUDE |
| MANUFACTURER'S SPECIFICATIONS FOR ALL GAS APPLIANCES |
| AND EQUIPMENT. |
| |
| B) BACKFLOW PREVENTER: A FLORIDA LICENSED PLUMBING |
| CONTRACTOR SHALL OBTAIN A SEPARATE PERMIT FOR |
| INSTALLATION OF THE POTABLE WATER SERVICE BACKFLOW |
| PREVENTER IN ACCORDANCE WITH SECTION 105.1 WPB AND |
| SECTION 90-33 WPB CODE OF ORDINANCES. THE DEVICE SHALL |
| BE TESTED AND CERTIFIED BY THE WPB UTILITIES DEPARTMENT |
| PRIOR TO FINAL INSPECTION BY THE WPB BUILDING |
| DEPARTMENT. PLEASE CONTACT THE WPB UTILITIES CENTRAL |
| OPERATIONS DEPT. AT 561-822-2210 FOR FURTHER |
| INFORMATION. |
| |
| 2) THE ENERGY FORM R405-2017 INDICATES THE TANKLESS |
| WATER HEATER TO BE 50 GALLONS AND 0.97 EFFICIENCY. |
| CORRECT THE GALLON SIZE DATA AND SUBMIT MANUFACTURER'S |
| SPECIFICATIONS TO CONFIRM THE EFFICIENCY RATING- TABLE |
| C404.1 FBC- EC. |
| |
| 3) SHEET PS.1.1: THE LOCATION OF THE 2-WAY CLEANOUT |
| SHALL BE AT THE JUNCTION OF THE BUILDING DRAIN AND |
| BUILDING SEWER OR WITHIN 10 FT. UPSTREAM OF THE |
| JUNCTION. PLEASE NOTE THAT BUILDING DRAIN BY DEFINITION |
| EXTENDS 30 INCHES BEYOND THE EXTERIOR WALL AT WHICH |
| POINT IT TRANSITIONS INTO THE BUILDING SEWER- SECTIONS |
| R202 & P3005.2.3 FBC RES. |
| |
| 4) SHEET P0.3 & P1.0B: CLEANOUTS AND ACCESS TO THE |
| CLEANOUTS ARE REQUIRED WHERE THE VERTICAL RAIN WATER |
| LEADERS CONNECT WITH THE HORIZONTAL UNDERSLAB STORM |
| DRAINS- SEE SECTIONS 1101.8, 708.1.4, 708.1.10 FBC P |
| AND P3005.2.4, AND P3005.2.10 FBC RES. |
| |
| 5) P1.1A: PROVIDE WATER HAMMER ARRESTORS FOR SUPPLY |
| LINES TO THE DISHWASHER, ICE MAKER, AND WASHING |
| MACHINE- SECTION P2903.5 FBC RES. |
| |
| 6) P1.1A: PROVIDE A BACKFLOW PREVENTER FOR THE SUPPLY |
| LINE TO THE ICE MAKER- SECTION P2902.1 FBC RES. |
| |
| 7) P1.1A: INDICATE HOW THE SUPPLY LINES UNDER THE SLAB |
| WILL BE PROTECTED FROM CORROSION- SECTION P2603.3 FBC |
| RES. |
| |
| 8) A1-101.2 & A-102: PROVIDE THE DIMENSIONS OF THE |
| SHOWERS- SECTION P2708.1 FBC RES. |
| |
| 9) P0.2: PROVIDE A SHOWER PAN DETAIL- SECTIONS P2709.1 |
| & P2709.2 FBC RES. |
| |
| 10) P1.3: PLEASE NOTE UPON COMPLETION OF THE NEW STORM |
| DRAINAGE SYSTEMS AS SHOWN ON THE PLAN A CERTIFICATION |
| FROM A LICENSED PROFESSIONAL SHALL BE SUBMITTED TO THE |
| INSPECTOR IN ORDER TO RECEIVE FINAL APPROVAL- SECTION |
| 110.9 IMPACT OF CONSTRUCTION WPB. |
| |
| 11) P1.3: THE ROOF DRAINAGE SYSTEMS SHALL BE IN |
| COMPLIANCE WITH SECTIONS R903.4.1 FBC RES AND 1101.2 |
| FBC P: |
| |
| A) VERIFY THE ROOF IS DESIGNED FOR THE MAXIMUM POSSIBLE |
| DEPTH OF WATER THAT WILL POND THEREON AS DETERMINED BY |
| THE RELATIVE LEVELS OF ROOF DECK AND OVERFLOW WEIRS, |
| SCUPPERS, EDGES OR SERVICEABLE DRAINS IN COMBINATION |
| WITH THE DEFLECTED STRUCTURAL ELEMENTS. IN DETERMINING |
| THE MAXIMUM POSSIBLE DEPTH OF WATER, ALL PRIMARY ROOF |
| DRAINAGE MEANS SHALL BE ASSUMED TO BE BLOCKED- SECTION |
| 1101.7 FBC P. |
| |
| B) PROVIDE THE ROOF DRAIN FLOW RATE BASED ON SECTION |
| 1105.2, AND CALCULATIONS FOR SIZING THE PRIMARY |
| VERTICAL CONDUCTORS AND LEADERS AND HORIZONTAL BRANCHES |
| BASED ON SECTIONS 1106.1, FIGURE 1106.1 AND SECTION |
| 1108.3. |
| |
| C) PROVIDE A PRIMARY ROOF DRAIN INSTALLATION DETAIL. |
| SHOW THE MAKES AND MODELS OF THE PRIMARY ROOF DRAINS, |
| AND SUBMIT PRODUCT SPECIFICATION SHEETS- SECTIONS |
| 1102.6 AND 1108.1. |
| |
| D) PROVIDE AN OVERFLOW SCUPPER DETAIL PER SECTIONS |
| R903.4.1 FBC RES. AND 1108.3 FBC P. |
| |
| E) SHOW THE LOCATIONS OF GUTTERS FOR THE SLOPED ROOFS |
| AND PROVIDE VERTICAL LEADER AND HORIZONTAL GUTTER SIZES |
| IN ACCORDANCE WITH TABLES 1106.3 AND 1106.6. |
| |
| 12) PROVIDE A PLUMBING SUB-PERMIT APPLICATION- SECTION |
| 105.1 WPB. |
| |
| WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| RE-SUBMITTAL FORM. |
| |
| CHRISTOPHER L. COLE |