Date |
Text |
2020-12-16 12:56:34 | 1ST REVIEW FBC-2017 PLUMBING |
| PERMIT- 20110271 |
| 12/15/2020 |
| |
| CODES IN EFFECT: |
| FBC P- FLORIDA PLUMBING CODE SIXTH EDITION 2017 |
| FBC ACC- FLORIDA ACCESSIBILITY CODE SIXTH ADDITION 2017 |
| FBC B- FLORIDA BUILDING CODE SIXTH EDITION 2017 |
| FBC M- FLORIDA MECHANICAL CODE SIXTH EDITION 2017 |
| FBC EC- FLORIDA ENERGY CONSERVATION CODE SIXTH EDITION |
| 2017 |
| FBC FG- FLORIDA FUEL GAS CODE SIXTH EDITION 2017 |
| FBC EX- FLORIDA EXISTING BUILDING CODE SIXTH EDITION |
| 2017 |
| FS- FLORIDA STATUTES |
| FAC- FLORIDA ADMINISTRATIVE CODE |
| WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH |
| EDITION 2017 |
| |
| PLAN REVIEW RESULTS: DENIED |
| |
| 1) SHEETS C13, L05-L08: PLEASE NOTE SEPARATE PERMITS |
| AND PLANS ARE REQUIRED FOR THE POTABLE WATER SERVICE |
| BACKFLOW PREVENTER, GREASE INTERCEPTOR, AND THE |
| IRRIGATION SYSTEM. COMPLETE SETS OF PLANS AND |
| SPECIFICATIONS ARE REQUIRED FOR REVIEW AND PERMIT |
| ISSUANCE- SECTION 107.2.1 WPB. |
| |
| 2) SHEET CS: PLEASE INCLUDE THE REQUIRED SERVICE SINK |
| IN THE PLUMBING FIXTURE DATA- TABLE 403.3 FBC P. |
| |
| 3) EQ-1, P1 & P4: THE MOP SINK AND FLOOR DRAIN BY THE |
| WATER HEATER, THE FLOOR SINKS AND HUB DRAINS RECEIVING |
| CONDENSATE DRAINAGE FROM REFRIGERATORS AND ICE MAKERS |
| IN THE COFFEE AND TRASH AREAS, AND THE F5 HAND SINKS |
| SHALL NOT CONNECT INTO THE GREASE WASTE LINE IN |
| COMPLIANCE WITH SECTION 1003.3.1 FBC P. PLEASE NOTE |
| THAT GREASE INTERCEPTORS AND AUTOMATIC GREASE REMOVAL |
| DEVICES SHALL RECEIVE WASTE ONLY FROM FIXTURES AND |
| EQUIPMENT THAT ALLOW FATS, OILS, OR GREASE TO BE |
| DISCHARGED. BASED ON THE PLAN THE RESTRICTED FIXTURES |
| DO NOT APPEAR TO BE SIGNIFICANT GREASE CONTRIBUTORS. |
| PLEASE REVIEW THE INTERNATIONAL PLUMBING CODE- 2015 |
| COMMENTARY ON GREASE INTERCEPTORS FOR FURTHER |
| CLARIFICATION. |
| |
| 4) P2 & P4: PROVIDE A FULL OPEN TYPE SHUTOFF VALVE FOR |
| THE 2 IN. CW WATER SERVICE/DISTRIBUTION LINE AT THE |
| ENTRANCE OF THE BUILDING- SECTION 606.1(2) FBC P. |
| |
| 5) P2 & P4: IN ACCORDANCE WITH SECTION 608.3 INDICATE |
| HOW THE CSR AND FREESTYLE FILTERING SYSTEMS WILL BE |
| PROTECTED AGAINST CONTAMINATION. WILL BACKFLOW |
| PREVENTERS BE INSTALLED ON THE WATER SUPPLY AND FILTER |
| LINES? |
| |
| 6) P2 & P4: PROVIDE SYMBOLS TO SHOW THE LOCATIONS OF |
| BACKFLOW PREVENTERS FOR SUPPLY LINES TO THE VARIOUS |
| BEVERAGE DISPENSERS, ICE MAKERS, COFFEE AND CAPPUCCINO |
| MACHINES, AND OTHER FIXTURES OR EQUIPMENT PERFORMING A |
| SPECIAL INCLUDING THE SANITIZING EQUIPMENT AT THE MOP |
| SINK- SECTION 608.3 FBC P. PLEASE NOTE THAT DETAIL |
| 2/P2.0 DOES NOT SHOW BACKFLOW PREVENTERS FOR THE CSRX |
| LINES TO THE ICE MACHINES. |
| |
| 7) P2, P4 & P5: PLEASE DEFINE OR EXPLAIN THE |
| ABBREVIATIONS CSR AND CSRX TO CLARIFY THE FUNCTIONS OF |
| THE PLUMBING LINES- SECTION 107.2.1 WPB. |
| |
| 8) P2 & P4: PROVIDE WATER HAMMER ARRESTOR SYMBOLS FOR |
| SUPPLY LINES TO THE DRINKING FOUNTAINS, ICE MAKERS, |
| BEVERAGE DISPENSERS, COFFEE MACHINES, AND OTHER |
| FIXTURES OR EQUIPMENT WITH QUICK CLOSING VALVES- |
| SECTION 604.9 FBC P. |
| |
| 9) P4: PROVIDE SYMBOLS TO SHOW THE REQUIRED TRAP |
| PRIMERS AT FLOOR DRAINS- SECTION 1002.4.1 FBC P. PLEASE |
| ADD THE DEVICES TO THE FIXTURE SPECIFICATIONS SCHEDULE |
| ON P5 AND PROVIDE A DETAIL- SECTION 107.2.1 WPB. |
| |
| 10) P2 & P4: PROVIDE A SHUT OFF VALVE FOR THE WATER |
| FEED UP TO THE WCH ON THE ROOF- SECTION 606.1(4) FBC P. |
| |
| 11) P5: PROVIDE THE EFFICIENCY RATING OF THE WATER |
| HEATER AND ADD THE DATA TO THE ENERGY COMPLIANCE REPORT |
| SUBMITTAL- TABLE C404.2 FBC EC. |
| |
| 12) P1 & P5: PLEASE INCLUDE THE WATER SOFTENER AND |
| BRINE TANK IN THE PLUMBING FIXTURE SPEC SCHEDULE- |
| SECTION 107.2.1 WPB. |
| |
| 13) P3 ROOF DRAIN PLAN- FBC P. |
| |
| A) PROVIDE ROOF DRAIN, ROOF SCUPPER, AND OVERFLOW |
| SCUPPER INSTALLATION DETAILS- SECTIONS 1105.1, 1106.5, |
| & 1108.1. |
| |
| B) PROVIDE A DETAIL SHOWING HOW THE MAIN BUILDING |
| DOWNSPOUTS WILL CONNECT TO THE STORM DRAINS- 1101.6. |
| |
| C) SHOW THE SLOPED ROOF B AND E HORIZONTAL GUTTER RUNS |
| AND SIZES- 1106.6. |
| |
| D) SHOW HOW THE ROOF B DOWNSPOUTS WILL TERMINATE AT THE |
| ROOF SURFACES AT A1 AND A2, AND IF SOME FORM OF |
| PROTECTION WILL BE PROVIDED TO MITIGATE EROSION OR |
| DEGRADATION FROM THE CONCENTRATED FLOW OF WATER FROM |
| DOWNSPOUTS- 1101.2, 1101.6, & 1101.7. |
| |
| E) PROVIDE A SIZING SCHEDULE FOR THE SECONDARY ROOF |
| DRAINS- 1108.3. |
| |
| F) SHOW HOW THE DRAINAGE FROM ROOF E DOWNSPOUT WILL |
| EITHER CONNECT TO THE STORM DRAIN SYSTEM OR TO AN |
| APPROVED PLACE OF DISPOSAL- 1101.2. |
| |
| 14) C02 SYSTEM- SECTION 107.2.1 WPB AND SECTION 1203.1 |
| FBC P. |
| |
| A) PROVIDE A C02 BOX INSTALLATION DETAIL. CLARIFY IF |
| THE BOX CONTAINS THE C02 TANKS OR IF THE BOX IS A |
| TRANSFER STATION FOR THE TANKS. SHOW HOW THE BOX AND |
| TANKS WILL BE SECURED AND SUPPORTED. |
| |
| B) PLEASE SHOW THE C02 LINE RUNS THROUGH THE BUILDING |
| AND HOW THE LINES WILL BE CHASED AND PROTECTED AGAINST |
| DAMAGE OR LEAKAGE. |
| |
| C) PROVIDE A PRODUCT SUBMITTAL PACKAGE FOR THE SYSTEM. |
| |
| 15) AC1-0 & EQ2-0: PLEASE SHOW COMPLIANCE WITH SECTIONS |
| 904.5.1 AND 308 (REACH RANGES) FBC ACC FOR ALL |
| SELF-SERVICE SHELVES AND DISPENSING DEVICES FOR |
| TABLEWARE, DISHWARE, CONDIMENTS, FOOD AND BEVERAGES, |
| |
| 16) PLEASE PROVIDE A PRODUCT SUBMITTAL PACKAGE THAT |
| INCLUDES BUT NOT IS NOT LIMITED TO THE WATER HEATER AND |
| EXPANSION TANK, THE CSR AND FREESTYLE FILTERING SYSTEMS |
| AND PIPING, THE WATER SOFTENER AND BRINE TANK, AND THE |
| 3-COMPARTMENT SINK. PLEASE NOTE THAT MANUFACTURER'S |
| SPECIFICATIONS AND INSTALLATION MANUALS FOR ALL |
| PLUMBING FIXTURES, EQUIPMENT, AND DEVICES MAY BE |
| DEFERRED SUBMITTALS OR BE ONSITE AT TIME OF INSPECTION- |
| SECTIONS 107.2.1 AND 107.3.4.1 WPB. |
| |
| 17) ADVISORIES FOR SEPARATE PERMIT SUBMITTALS. |
| |
| A) BACKFLOW PREVENTER: PLEASE NOTE THAT A FL. LICENSED |
| PLUMBING CONTRACTOR SHALL OBTAIN A SEPARATE PERMIT FOR |
| INSTALLATION OF THE BACKFLOW PREVENTER IN ACCORDANCE |
| WITH SECTION 105.1 WPB AND SEC. 90-33 WPB CODE OF |
| ORDINANCES. THE DEVICE SHALL BE TESTED AND CERTIFIED BY |
| THE WPB UTILITIES DEPARTMENT PRIOR TO FINAL INSPECTION |
| BY THE BUILDING DEPARTMENT. PLEASE CONTACT THE WPB |
| UTILITIES CENTRAL OPERATIONS DEPT.AT 561-822-2210 FOR |
| FURTHER INFORMATION. |
| |
| B) GREASE INTERCEPTOR: SUBMITTED PLANS SHALL INCLUDE |
| GREASE WATER CALCULATIONS IN ACCORDANCE WITH SECTION |
| 1003.3.4 FOR HYDROMECHANICAL INTERCEPTORS OR 1003.3.6 |
| FOR GRAVITY TYPE INTERCEPTORS. MANUFACTURER'S |
| SPECIFICATIONS AND INSTALLATION MANUALS SHALL ALSO BE |
| SUBMITTED FOR REVIEW. |
| |
| WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| RE-SUBMITTAL FORM. |
| |
| CHRISTOPHER L. COLE |
| MECHANICAL/PLUMBING PLANS EXAMINER |
| 401 CLEMATIS STREET |
| WEST PALM BEACH FL 33401 |
| 561-805-6719 |
| [email protected] |
| |