Plan Review Notes
Plan Review Notes For Permit 20101143
Permit Number 20101143
Review Stop FIRE
Sequence Number 1
Notes
Date Text
2020-11-19 11:17:05THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE
 MARSHAL, WITH THE FOLLOWING COMMENTS:
  
  
 1) SHEET # 3.0 INDICATES THE FUEL TYPE AS NATURAL GAS;
 HOWEVER, THERE IS NO INDICATIONS OF A FUEL LINE TO THE
 GENERATOR.
  
 PLEASE PROVIDE DETAILS OF THE LOCATION AND SIZE OF THE
 FUEL LINE IN COMPLAINCE WITH THE REQUIRMENTS OF NFPA
 54.
  
 5.1 PIPING PLAN.
 5.1.1 INSTALLATION OF PIPING SYSTEM. WHERE REQUIRED BY
 THE
 AUTHORITY HAVING JURISDICTION, A PIPING SKETCH OR PLAN
 SHALL BE
 PREPARED BEFORE PROCEEDING WITH THE INSTALLATION. THE
 PLAN
 SHALL SHOW THE PROPOSED LOCATION OF PIPING, THE SIZE OF
 DIFFERENT
 BRANCHES, THE VARIOUS LOAD DEMANDS, AND THE LOCATION OF
 THE POINT OF DELIVERY.
  
 CHAPTER 7 GAS PIPING INSTALLATION
 7.1 PIPING UNDERGROUND.
 7.1.1 CLEARANCES. UNDERGROUND GAS PIPING SHALL BE
 INSTALLED
 WITH SUFFICIENT CLEARANCE FROM ANY OTHER UNDERGROUND
 STRUCTURE
 TO AVOID CONTACT THEREWITH, TO ALLOW MAINTENANCE, AND
 TO PROTECT
 AGAINST DAMAGE FROM PROXIMITY TO OTHER STRUCTURES. IN
 ADDITION,
 UNDERGROUND PLASTIC PIPING SHALL BE INSTALLED WITH
 SUFFICIENT
 CLEARANCE OR SHALL BE INSULATED FROM ANY SOURCE OF HEAT
 SO AS TO
 PREVENT THE HEAT FROM IMPAIRING THE SERVICEABILITY OF
 THE PIPE.
 7.1.2 PROTECTION AGAINST DAMAGE. MEANS SHALL BE
 PROVIDED TO
 PREVENT EXCESSIVE STRESSING OF THE PIPING WHERE
 VEHICULAR TRAFFIC IS
 HEAVY OR SOIL CONDITIONS ARE UNSTABLE AND SETTLING OF
 PIPING OR
 FOUNDATION WALLS COULD OCCUR. PIPING SHALL BE BURIED OR
 COVERED
 IN A MANNER SO AS TO PROTECT THE PIPING FROM PHYSICAL
 DAMAGE.
 PIPING SHALL BE PROTECTED FROM PHYSICAL DAMAGE WHERE IT
 PASSES
 THROUGH FLOWER BEDS, SHRUB BEDS, AND OTHER SUCH
 CULTIVATED AREAS
 WHERE SUCH DAMAGE IS REASONABLY EXPECTED.
 7.1.2.1 COVER REQUIREMENTS. UNDERGROUND PIPING SYSTEMS
 SHALL BE INSTALLED WITH A MINIMUM OF 12 IN. (300 MM) OF
 COVER.
  
 (A) THE MINIMUM COVER SHALL BE INCREASED TO 18 IN.
 (460MM)IF
 EXTERNAL DAMAGE TO THE PIPE OR TUBING FROM EXTERNAL
 FORCES IS
 LIKELY TO RESULT.*******LIKE A UNDER A PARKING
 LOT********
  
  
  
 2) SHEET E 1.0 - THERE ARE NO DIMENSIONS INDICATED
 AROUND THE LOCATION OF THE GENERATOR.
  
 7.2.6 THE EPS EQUIPMENT SHALL BE INSTALLED IN A
 LOCATION THAT
 PERMITS READY ACCESSIBILITY AND A MINIMUM OF 0.9M(36
 IN.) FROM
 THE SKID RAILS? OUTERMOST POINT IN THE DIRECTION OF
 ACCESS FOR INSPECTION,
 REPAIR, MAINTENANCE, CLEANING, OR REPLACEMENT. THIS
 REQUIREMENT
 SHALL NOT APPLY TO UNITS IN OUTDOOR HOUSINGS.
  
  
 PLEASE PROVIDE DETAILED DIMENSION FROM PROPERTY LINES,
 PAVEMENT EDGES AND BUIDLINGS OR PROVIDE THE SPECIFIC
 MANUFACTURES SPEC SHEETS INDICATING OUTDOOR HOUSING.
  
  
  
 3) SHEET E 1.0 & E 2.0 - THERE ARE NO ELEVATION
 DIMENSIONS OF THE FOUNDATION.
  
 PER NFPA 110
  
 7.4.1.1 SUCH FOUNDATIONS OR STRUCTURAL BASES SHALL
 RAISE THE
 ENGINE AT LEAST 150 MM (6 IN.) ABOVE THE FLOOR OR GRADE
 LEVEL
 AND BE OF SUFFICIENT ELEVATION TO FACILITATE
 LUBRICATING-OIL DRAINAGE
 AND EASE OF MAINTENANCE.
  
  
 4) WHEN RESUBMITTING, PLEASE PROVIDE PLAN SHEET
 REVISION CLOUDS OR NUMBERED NARRATIVE RESPONSES TO THE
 ABOVE.
  
  
 5) ADDITIONAL COMMENTS MAY BE PROVIDED ON THE
 RE-SUBMITTAL OF THE ABOVE.
  
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]
  