Plan Review Notes
Plan Review Notes For Permit 20101096
Permit Number 20101096
Review Stop B
Sequence Number 3
Notes
Date Text
2020-12-16 08:20:21ELEVATION CERTIFICATE
 REVIEW COMMENTS
  
 2ND REVIEW: FBC SIXTH EDITION (2017)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
 ELEVATION CERTIFICATE ( UNDER CONSTRUCTION)
  
 1) THE ELEVATION FOR THE ATTACHED GARAGE IS SPECIFIED
 AS 13.8' NAVD 88 IN C2 (D). THIS IS AN ISSUE BECAUSE
 THE GARAGE IS BELOW THE REQUIRED 14.1' DFE. THE
 PRE-CONSTRUCTION EC AND THE PLANS SPECIFY THE FINISH
 FLOOR ELEVATION AS 14.1' NAVD 88. THIS ISSUE WILL NEED
 TO BE CORRECTED BEFORE THE EC WILL BE APPROVED.
 POSSIBLE SOLUTIONS ARE RAISING THE FLOOR OF THE GARAGE
 OR THE INSTALLATION OF FLOOD VENTS.