Notes
Date Text
2020-09-23 16:38:24PLAN REVIEW / NFIP
  
 CHRISTOPHER S. THROOP, C.B.O.
 PLANS EXAMINER BUILDING - PX3169
 PLANS EXAMINER 1&2 FAMILY - SFP306
 CONSTRUCTION SERVICES DIVISION
 TEL: 561-805-6726
 FAX: 561-805-6676
 E-MAIL: [email protected]
  
 CODES IN EFFECT:
 2017 FLORIDA BUILDING CODE, 6TH EDITION W/2017 WEST
 PALM BEACH AMENDMENTS TO THE FLORIDA BUILDING CODE,
 CHAPTER 1 ADMINISTRATION
 CITY ORDINANCE NO. 4658-16
  
 1ST REVIEW
  
 RESULTS: DENIED
 ADDRESS THE ATTACHED COMMENTS AND RE-SUBMIT
  
 ELEVATION CERTIFICATE REQUIRED
  
 THIS PROJECT IS LOCATED IN A SPECIAL FLOOD HAZARD AREA
 (SFHA). THE SPECIFIC ZONE DESIGNATION FOR THIS SITE IS
 AE WITH A BASE FLOOD ELEVATION (BFE) OF 7.0 FEET. THE
 CITY OF WEST PALM BEACH (THROUGH ORDINANCE) REQUIRES AN
 ADDITIONAL 24 INCHES OF FREEBOARD REQUIRING THE DESIGN
 FLOOD ELEVATION (DFE) TO BE 9. 0 FEET. PLEASE NOTE THIS
 INFORMATION ON YOUR PLANS.
  
 3 EC'S REQUIRED
  
 1) A CONSTRUCTION DRAWING ELEVATION CERTIFICATE IS
 REQUIRED AT TIME OF PERMIT APPLICATION.
  
 2) A BUILDING UNDER CONSTRUCTION ELEVATION CERTIFICATE
 IS REQUIRED AT PLACEMENT OF 1ST FLOOR.
 NOTE: PROVIDE THIS EC TO CITY BUILDING INSPECTOR.
  
 3) A FINISHED CONSTRUCTION ELEVATION CERTIFICATE IS
 REQUIRED AND SHALL BE SUBMITTED FOR REVIEW AND APPROVAL
 PRIOR TO THE ISSUANCE OF THE CERTIFICATE OF OCCUPANCY.
 NOTE: THIS EC MAY BE SUBMITTED FOR REVIEW AFTER FINAL
 GRADE AND PRIOR TO FINAL.
  
 NOTE: RE: EC SECTION C2E LOCAL FLOODPLAIN MANAGEMENT
 OFFICIALS ARE REQUIRED TO ENSURE THAT ALL MACHINERY AND
 EQUIPMENT SERVICING THE BUILDING ARE PROTECTED FROM
 FLOODING PER R322.1.6 PROTECTION OF MECHANICAL,
 PLUMBING AND ELECTRICAL SYSTEMS.
 MACHINERY OR EQUIPMENT SERVICING THE BUILDING SHALL BE
 LOCATED AT OR ABOVE THE DESIGN FLOOD ELEVATION (DFE).
  
 FLOOD VENTS REQUIRED
  
 FBC APPENDIX G FLOOD RESISTANR CONSTRUCTION AND FBC R
 322.2.2 ENCLOSED AREA BELOW DESIGN FLOOD ELEVATION.
 FULLY ENCLOSED AREAS BELOW THE DESIGN FLOOD ELEVATION
 SHALL BE AT OR ABOVE GRADE ON ALL SIDES AND CONFORM TO
 THE FOLLOWING:
  
 1) IN FLOOD HAZARD AREAS NOT SUBJECT TO HIGH-VELOCITY
 WAVE ACTION, ENCLOSED AREAS SHALL HAVE FLOOD OPENINGS
 TO ALLOW FOR THE AUTOMATIC INFLOW AND OUTFLOW OF
 FLOODWATERS.
  
 OPTIONS:
 1A) PROVIDE FLOOD OPENINGS DESIGNED BY A DESIGN
 PROFESSIONAL PER R322.2.2 ENCLOSED AREA BELOW DESIGN
 FLOOD ELEVATION.
 SIGNATURE AND SEAL OF DESIGNER IS REQUIRED.
  
 1B) PROVIDE ENGINEERED FLOOD VENTS. (SMART VENTS)
 ATTACH A COPY OF THE INDIVIDUAL ENGINEERED FLOOD
 OPENING CERTIFICATION OR EVALUATION REPORT ISSUED BY
 THE INTERNATIONAL CODE COUNCIL EVALUATION SERVICE (ICC
 ES).
  
 PROVIDE FLORIDA PRODUCT APPROVALS FOR PROPOSED SMART
 VENTS.
 FBC 107.3.4 PROVIDE PRODUCT APPROVALS FOR THOSE
 PRODUCTS WHICH ARE REGULATED BY FAC RULE 9N-3 REVIEWED
 AND APPROVED IN WRITING BY THE DESIGNER OF RECORD.
  
 1C) FLOOD OPENINGS SHALL BE INSTALLED PER
 R322.2.2.1INSTALLATION OF OPENINGS.
 SHOW NUMBER AND LOCATION OF FLOOD OPENINGS ON
 FOUNDATION PLAN.
  
 INFORMATION ONLY: CITY ORDINANCE NO. 4658-16
  
 CITY OF WEST PALM BEACH ORDINANCE NO. 4658-16
 AS OF OCTOBER 5, 2017, THE FEDERAL EMERGENCY MANAGEMENT
 AGENCY (FEMA) ESTABLISHED A NEW FLOOD INSURANCE RATE
 MAP (FIRM) UTILIZING THE RECENTLY COMPLETED FLOOD
 HAZARD DETERMINATION (FHD) FOR THE CITY OF WEST PALM
 BEACH, FL.
 ALL NEW BASE FLOOD ELEVATIONS (BFE) SHALL BE BASED ON
 NAVD88 DATUM. ON AUGUST 23, 2017, THE CITY OF WEST PALM
 BEACH, BY ORDINANCE, NO. 4658-16, ESTABLISHED A
 TWO-FOOT FREEBOARD ABOVE THE (BFE).
  
 PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED
 MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS.
  
  
  
  