2020-07-01 14:45:08 | 1) SHOW THE TYPE OF PIPE MATERIAL BEING INSTALLED. WPB | | AMENDMENTS TO FBC SEC.107.2.1. | | 2) SUBMIT CALCULATIONS FOR COMBUSTION AIR FOR THE GAS | | RANGE PER THE 2017 FBC-RES. SEC. G 2407.1. | | 3) INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM | | ON THE PLAN PER 2017 FBC-FUEL GAS SEC.402.1, 402.4.3 | | THRU 402.6 OR 2017 FBC RES. SEC. G2413.2, G2413.4.3. | | 4) INDICATE ON THE PLAN THE DISTANCE OF THE TANKLESS | | WATER HEATER TO ANY OPERABLE DOORS OR WINDOWS. THE | | MANUFACTURER REQUIRES A MINIMUM OF 4 FEET. | | 5) SUBMIT TWO COPIES OF THE APPLICABLE SIZING TABLES | | USED TO SIZE THE GAS SYSTEM OR PLACE A NOTE ON THE | | PLANS/DRAWINGS SPECIFYING WHICH SIZING TABLE(S) FROM | | THE GAS CODE OR OTHER APPROVED STANDARD THAT WERE USED | | IN THE DESIGN OF THIS GAS SYSTEM. REFER TO THE 2017 | | FBC-FUEL GAS SECS. 401.4, 401.8, 402.3, AND TABLES | | 402.4 (1) THRU 402.4 (37) OR 2017 FBC-RES. SEC. | | G2413.3, G2412.8, G2413.1, G2413.2, & G2413.3. | | | | TIM LARGE | | CHIEF PLUMBING INSPECTOR | | PLUMBING PLAN REVIEW | | 561-805-6692 | | [email protected] | | | | |
|