Plan Review Notes
Plan Review Notes For Permit 20030982
Permit Number 20030982
Review Stop Z
Sequence Number 3
Notes
Date Text
2021-10-15 16:55:23FAILED
  
 PROVIDE WRITTEN RESPONSES TO COMMENTS.
  
 1) REPEAT COMMENT: RESOLUTION 13-19, WHICH APPROVED THE
 PROJECT INCLUDED THE REQUIREMENT THAT CERTAIN ITEMS
 REQUIRED PRIOR TO THE SUBMITTAL OF THE BUILDING PERMIT
 FOR SITE IMPROVEMENTS, WHICH INCLUDES THE FOUNDATION
 PERMIT. PROVIDE EVIDENCE THAT THE FOLLOWING HAS BEEN
 COMPLETED:
  
 A. ABANDON OR RELOCATE THE FPL EASEMENT ALONG THE SOUTH
 PROPERTY LINE. THE DEVELOPER, BASED ON DISCUSSIONS WITH
 FPL, PRESENTED A TEMPORARY POWER ROUTING PLAN TO CITY
 STAFF; HOWEVER, THE FINAL PLAN AND FPL'S SIGN OFF ARE
 NOT INCLUDED WITH THE RESUBMITTAL. SHEET E1.050 DOES
 NOT SPECIFY WHEN THE EASEMENT WILL BE ABANDONED.
  
 2) REPEAT COMMENT: PROVIDE INFORMATION ON THE REQUIRED
 CONDITION SURVEY: RESOLUTION 13-19 REQUIRES THAT THE
 DEVELOPER SHALL PERFORM A CONDITION SURVEY OF THE
 ADJOINING PROPERTIES PRIOR TO THE COMMENCEMENT OF ANY
 CONSTRUCTION OR DEMOLITION ACTIVITIES. THE DEVELOPER
 SHALL CONFORM TO THE APPROPRIATE INDUSTRY STANDARDS
 APPROVED BY THE CITY'S BUILDING DIVISION IN MONITORING
 THE VIBRATION EFFECTS ON THE ADJOINING PROPERTIES; THIS
 MAY INCLUDE, BUT IS NOT LIMITED TO, THE PLACEMENT OF
 SEISMIC METERS, INSPECTIONS, AND SIMILAR ACTIVITIES.
  
 3) REPEAT COMMENT: EV PROVISIONS - ZONING STAFF HAS
 REVIEWED AND NEEDS CLARIFICATION NARRATIVE ON THE EV
 PROVISION. COMMENTS BELOW MAY CHANGE BASED ON THE
 NARRATIVE. THE NARRATIVE SHALL VERIFY THE RESOLUTION
 NO. 13-19 EV REQUIREMENTS.
  
 A. IT APPEARS THAT THE GUEST SPACES ARE ONLY GETTING EV
 LEVEL 1, INSTEAD OF THE LEVEL 2 THAT ARE REQUIRED.
  
 4) REPEAT COMMENT: THE SURVEY PREPARED BY MILLER LAND
 SURVEYING PROVIDED WITH THE PERMIT IS NOT THE LATEST
 SURVEY THAT WAS PROVIDED FOR THE SITE PLAN APPROVAL.
 THE SURVEY PROVIDED BY GEOPOINT SURVEYING DOES NOT
 MATCH WHAT WAS PRESENTED AS THE ACCURATE PROPERTY
 BOUNDARIES SHOWN ON THE MILLER LAND SURVEYING SURVEY.
 THE CORRECT, ACCURATE SURVEY IS REQUIRED.
  
 5) THE FOLLOWING DIMENSIONS PROVIDED ON SHEET A1.100
 (SITE PLAN) DO NOT MATCH THE SAME DIMENSIONS ON SHEET
 A1.01 (GROUND FLOOR PLAN) SUBMITTED WITH THE MINOR
 PLANNED DEVELOPMENT AMENDMENT ? WEST SETBACK OF 5 FEET
 3 INCHES FOR THE GENERATOR PIT, NORTH SETBACK OF 20
 FEET 2 INCHES VIOLATES THE APPROVED SETBACK (ALSO DOES
 NOT MATCH PERMIT SHEET A1.1B1), SOUTH B1 WALL IS
 INCONSISTENT WITH DIMENSION ON SHEET A1.1B1.
 ADDITIONALLY, THE DIMENSIONS TO THE COLUMNS TO THE
 AMENITY DECK HAVE NOT BEEN PROVIDED. NOTE: CHECK ALL
 SETBACKS FOR CONSISTENCY. PERMIT PLAN SHET A1.101 IS
 INCONSISTENT WITH PERMIT PLANS AND THE SAME PLAN
 SUBMITTED WITH THE MINOR AMENDMENT.
  
 6) THE CIVIL PLANS UPLOADED ON MAY 7, 2021, ARE NOT THE
 LATEST VERSION OF THE CIVIL PLANS THAT HAVE BEEN
 SUBMITTED TO THE CITY. THE MOST CURRENT PLANS NEED TO
 BE WITH THE PERMIT.
  
 7) THE ABOVE GRADE IMPROVEMENTS REQUIRE REVIEW AS
 SEPARATE PERMITS WITH PLANS:
  
 A. THE WALLS, FENCES, GATES AND COLUMNS REQUIRE A
 SEPARATE PERMIT WITH PLANS.
 B. HARDSCAPE, INCLUDING PAVERS, ARTIFICIAL TURF, DOG
 PARK ITEMS, BENCHES/PLAZA AREA, ETC.
 C. LANDSCAPE
 D. IRRIGATION
 E. GENERATOR - PLEASE NOTE THAT THE FULL HEIGHT OF THE
 GENERATOR DOES NOT APPEAR TO BE SCREENED AS REQUIRED BY
 RESOLUTION NO. 13-19. HEDGES MAY NOT EXCEED 10 FEET IN
 HEIGHT, SO YOU WILL NEED TO LOWER THE GENERATOR
 PROFILE.
 F. WATER FEATURES
 G. PARKING STRIPING
 H. SITE LIGHTING, INCLUDING BOLLARDS, NOTE: SINCE
 ACACIA ROAD IS A SEPARATE PARCEL, IT REQUIRES ITS OWN
 PERMIT FOR THE LIGHTING, BUT MAY BE INCLUDED ON ONE SET
 OF PLANS FOR BOTH PERMIT NUMBERS. PHOTOMETRIC PLANS ARE
 REQUIRED WITH THE PERMITS.
 I. BICYCLE RACKS, INCLUDES THE BICYCLE STORAGE ROOM.
  
 CONTACT ERIC SCHNEIDER @ (561) 822-1446
 [email protected]
  