Plan Review Notes
Plan Review Notes For Permit 20020953
Permit Number 20020953
Review Stop Z
Sequence Number 3
Notes
Date Text
2020-08-19 09:38:39FAILED
  
 PERMIT 20020953 - UNDERGROUND FIBER PBL & FORUM MCI
 PROJECT #1801CVFF.219 - 2ND RESUB
  
 PROVIDE WRITTEN RESPONSE TO COMMENTS.
  
 THE FOLLOWING ITEMS NEED TO BE ADDRESSED OR THE PERMIT
 WILL NOT BE APPROVED.
  
 1) ENGINEERING PLAN -
  
 A. THE ENGINEERING PLAN DOES NOT MATCH THE SURVEY IN
 SHOWING THE LOCATION OF THE RIGHT-OF-WAY LINE. HOWEVER,
 THE LOCATION OF THE FIBER INSTALL AND THE HANDHOLE ARE
 SHOWN ON THE ENGINEERING PLAN IN THE PARKWAY BETWEEN
 THE SIDEWALK AND THE EDGE OF PAVEMENT, WHICH THE SURVEY
 VERIFIES IS WITHIN THE RIGHT-OF-WAY. CORRECT THE
 RIGHT-OF-WAY LINE LOCATION ON THE RESUBMITTED
 ENGINEERING PLAN.
  
 B. THE BORE SHOWN AT 10 FEET BELOW GRADE IS AT A
 SUFFICIENT DEPTH TO AVOID PALM TREE DAMAGE.
  
 PLEASE NOTE:
  
 THE INSTALLATION CONTRACTOR MUST CONTACT SUNSHINE 811
 TO VERIFY THE LOCATION OF ALL UTILITIES AND VERIFY ALL
 DEPTHS PRIOR TO CONSTRUCTION. ALL CITY UTILITIES MUST
 BE LOCATED BY SOFT DIG METHODS BEFORE STARTING THE
 WORK.
  
 THE RIGHT-OF-WAY USE PERMIT REQUIRES YOU TO PROVIDE A
 CERTIFICATE OF LIABILITY INSURANCE, WHICH IN ACCORDANCE
 WITH SECTION 78-406 OF THE CITY CODE SPECIFICALLY NAMES
 THE CITY OF WEST PALM BEACH, ITS COMMISSIONERS,
 OFFICERS, EMPLOYEES AND AGENTS AS ADDITIONAL INSURED.
  
 CONTACT ERIC SCHNEIDER @ (561) 822-1446
 [email protected]
  