Plan Review Notes
Plan Review Notes For Permit 19120519
Permit Number 19120519
Review Stop B
Sequence Number 1
Notes
Date Text
2019-12-12 14:21:14PLAN REVIEW - BUILDING
  
 CODES IN EFFECT:
 2017 FLORIDA BUILDING CODE, 6TH EDITION W/2017 WEST
 PALM BEACH AMENDMENTS TO THE FLORIDA BUILDING CODE,
 CHAPTER 1 ADMINISTRATION
 FBC RE = FLORIDA RESIDENTIAL CODE 2017 6TH EDITION
 FBC CE = FLORIDA BUILDING CODE ENERGY CONSERVATION 2017
 6TH EDITION
  
 CHRISTOPHER S. THROOP, C.B.O.
 BUILDING PLANS EXAMINER, PX3169
 1&2 FAMILY PLANS EXAMINER, SFP306
 CONSTRUCTION SERVICES DIVISION
 TEL: 561-805-6726
 FAX: 561-805-6676
 E-MAIL: [email protected]
  
 1ST REVIEW
  
 RESULTS: DENIED
  
 YOUR SUBMITTAL IS DEFICIENT FOR THE REASONS LISTED
 BELOW.
 ADDRESS THE ATTACHED COMMENTS AND RE-SUBMIT
  
 2017 FBC 6TH CHPT. 1
 TEMPORARY MEMBRANE STRUCTURES
 (TENTS)
 CHPT. 1 FBC
  
 SECTION 108
 TEMPORARY STRUCTURES AND USES
  
 108.1 GENERAL. THE BUILDING OFFICIAL IS AUTHORIZED TO
 ISSUE A PERMIT FOR TEMPORARY STRUCTURES AND TEMPORARY
 USES. SUCH PERMITS SHALL BE LIMITED AS TO TIME OF
 SERVICE, BUT SHALL NOT BE PERMITTED FOR MORE THAN
 6MONTHS. THE BUILDING OFFICIAL IS AUTHORIZED TO GRANT
 EXTENSIONS FOR
 DEMONSTRATED CAUSE.
  
 108.2 CONFORMANCE. TEMPORARY STRUCTURES AND USES SHALL
 CONFORM TO THE STRUCTURAL STRENGTH, FIRE SAFETY, MEANS
 OF EGRESS, ACCESSIBILITY, LIGHT, VENTILATION AND
 SANITARY REQUIREMENTS OF THIS CODE AS NECESSARY TO
 ENSURE PUBLIC HEALTH, SAFETY AND GENERAL WELFARE.
  
 108.3 TEMPORARY POWER. THE BUILDING OFFICIAL IS
 AUTHORIZED TO GIVE PERMISSION TO TEMPORARILY SUPPLY AND
 USE POWER IN PART OF AN ELECTRIC INSTALLATION BEFORE
 SUCH INSTALLATION HAS BEEN FULLY COMPLETED AND THE
 FINAL CERTIFICATE OF COMPLETION HAS BEEN ISSUED. THE
 PART COVERED BY THE TEMPORARY CERTIFICATE SHALL COMPLY
 WITH THE REQUIREMENTS SPECIFIED FOR TEMPORARY LIGHTING,
 HEAT OR
 POWER IN CHAPTER 27 OF THE FLORIDA BUILDING CODE,
 BUILDING.
  
 108.4 TERMINATION OF APPROVAL. THE BUILDING OFFICIAL IS
 AUTHORIZED TO TERMINATE SUCH PERMIT FOR A TEMPORARY
 STRUCTURE OR USE AND TO ORDER THE TEMPORARY STRUCTURE
 TO BE REMOVED OR USE TO BE DISCONTINUED.
  
 2017 FBC 6TH CHPT. 31
 SPECIAL CONSTRUCTION
  
 SECTION 3103
 TEMPORARY STRUCTURES
  
 3103.1 GENERAL. THE PROVISIONS OF SECTIONS 3103.1
 THROUGH 3103.4 SHALL APPLY TO STRUCTURES ERECTED FOR A
 PERIOD OF LESS THAN 180 DAYS. TENTS AND OTHER MEMBRANE
 STRUCTURES ERECTED FOR A PERIOD OF LESS THAN 180 DAYS
 SHALL COMPLY WITH THE FLORIDA FIRE PREVENTION CODE.
 THOSE ERECTED FOR A LONGER PERIOD SHALL COMPLY WITH
 APPLICABLE SECTIONS OF THIS CODE.
 3103.1.1 CONFORMANCE. TEMPORARY STRUCTURES AND USES
 SHALL CONFORM TO THE STRUCTURAL STRENGTH, FIRE SAFETY,
 MEANS OF EGRESS, ACCESSIBILITY, LIGHT, VENTILATION AND
 SANITARY REQUIREMENTS OF THIS CODE AS NECESSARY TO
 ENSURE PUBLIC HEALTH, SAFETY AND GENERAL WELFARE.
 3103.1.2 PERMIT REQUIRED. TEMPORARY STRUCTURES THAT
 COVER AN AREA GREATER THAN 120 SQUARE FEET (11.16 M2),
 INCLUDING CONNECTING AREAS OR SPACES WITH A COMMON
 MEANS OF EGRESS OR ENTRANCE THAT ARE USED OR INTENDED
 TO BE USED FOR THE GATHERING TOGETHER OF 10 OR MORE
 PERSONS, SHALL NOT BE ERECTED, OPERATED OR MAINTAINED
 FOR ANY PURPOSE WITHOUT OBTAINING A PERMIT FROM THE
 BUILDING OFFICIAL.
 3103.2 CONSTRUCTION DOCUMENTS. A PERMIT APPLICATION AND
 CONSTRUCTION DOCUMENTS SHALL BE SUBMITTED FOR EACH
 INSTALLATION OF A TEMPORARY STRUCTURE. THE CONSTRUCTION
 DOCUMENTS SHALL INCLUDE A SITE PLAN INDICATING THE
 LOCATION OF THE TEMPORARY STRUCTURE AND INFORMATION
 DELINEATING THE MEANS OF EGRESS AND THE OCCUPANT LOAD.
 3103.3 LOCATION. TEMPORARY STRUCTURES SHALL BE LOCATED
 IN ACCORDANCE WITH THE REQUIREMENTS OF TABLE 602 BASED
 ON THE FIRE-RESISTANCE RATING OF THE EXTERIOR WALLS FOR
 THE PROPOSED TYPE OF CONSTRUCTION.
 3103.4 MEANS OF EGRESS. TEMPORARY STRUCTURES SHALL
 CONFORM TO THE MEANS OF EGRESS REQUIREMENTS OF CHAPTER
 10 AND SHALL HAVE AN EXIT ACCESS TRAVEL DISTANCE OF 100
 FEET (30 480 MM) OR LESS.
  
 APPLICANTION CHECKLIST
 ALL STRUCTURES INSTALLED FOR LESS THAN 180 DAYS,
 GREATER THAN 120 SQ. FT. WITH 10 OR MORE OCCUPANTS
 * APPLICATION NEEDS TO BE SUBMITTED AT LEAST TWO WEEKS
 PRIOR TO EVENT
 1. PERMIT APPLICATION
 A. PROVIDE EVENT FUNCTION
  B. ADDRESS OF EVENT
  C. WORK DESCRIPTION ? I.E. NUMBER AND SIZE OF TENTS
 D. OWNER AND CONTRACTOR INFO.
  E. VALUE ? ATTACH COPY OF CONTRACT WITH OWNER
  F. SPECIFY DATES OF INSTALLATION AND REMOVAL
 2. SITE PLAN
  A. SHOW TO SCALE THE SIZE AND LOCATION OF NEW
 CONSTRUCTION AND EXISTING
 STRUCTURES ON THE SITE?
  B. SHOW DISTANCE TO LOT LINES AND OTHER STRUCTURES PER
 FBC CHPT. 6, SEC. 602
  C. PROVIDE SQUARE FOOTAGE
  D. PROVIDE ESTIMATED OCCUPANCY CONTENT OF EACH TENT
  E. PROVIDE ACCESSIBLE ROUTE FROM PARKING TO TENT
 ENTRANCE
  F. IDENTIFY MEANS OF EGRESS PER CHPT. 10
  G. PROVIDE ACCESSIBLE ROUTE FROM TENT TO ACCESSIBLE
 RESTROOMS
  H. ACCESSIBLE RESTROOMS SHALL BE LOCATED WITHIN 500
 FEET OF TENT
 2. FOUNDATION/TIE DOWN
  A. PROVIDE DETAIL OF TIE DOWN FOR UPLIFT
  B. PROVIDE DETAIL OF ANCHORS FOR TENT LEG LATERAL
 MOVEMENT
 3. CONFORMANCE PER SECTION 3103.1.1
 TEMPORARY STRUCTURES AND USES SHALL CONFORM TO THE
 STRUCTURAL STRENGTH, FIRE SAFETY, MEANS OF EGRESS,
 ACCESSIBILITY, LIGHT, VENTILATION AND SANITARY
 REQUIREMENTS OF THIS CODE AS NECESSARY TO ENSURE PUBLIC
 HEALTH, SAFETY AND GENERAL WELFARE.
 A. STRUCTURAL STRENGTH PER FBC CHPT. 16 ? FOR
 STRUCTURES WITH SPANS OF 30 FEET OR GREATER.
 B. FIRE SAFETY ? PROVIDE FLAME SPREAD TEST REPORTS PER
 NFPA 701 FOR EACH TENT
 C. MEANS OF EGRESS 1) OPEN SIDES ? NO LIFE SAFETY PLAN
 REQUIRED.
  2) CLOSED SIDES ? PROVIDE LIFE SAFETY PLAN
  A) STATE OCCUPANT LOAD.
  B) IDENTIFY MEANS OF EGRESS.
  C) IDENTIFY PATH OF TRAVEL ? 100 FT. OR LESS TO
 EXIT.
  D) PROVIDE FLOOR LAYOUT OF EVENT.
  D. ACCESSIBILITY 1) IDENTIFY ACCESSIBLE ROUTE ON SITE
 PLAN
  E. LIGHT 1) OPEN SIDES ? N/A
  2) CLOSED SIDES ? PER SEC. 1008.2.1 > 1 FOOT CANDLE
  F. VENTILATION 1) OPEN SIDES ? N/A
  2) CLOSED SIDES ? PER SEC. 1203
  G. SANITARY 1) IDENTIFY EXISTING PERMANENT FACILITIES
 ON SITE PLAN
  2) PROVIDE PORTABLE FACILITIES PER TABLE 2902.
 _______________________________________________________
 _________________
  
  
 *ADDITIONAL REQUIREMENTS
 FOR TEMPORARY MEMBRANE STRUCTURES (TENTS) WITH A SPAN
 OF 30 FEET OR GREATER IN ANY DIRECTION:
  
 A. PROVIDE DETAILS OF STRUCTURAL CONNECTIONS. INCLUDE
 BASEPLATE/TIEDOWN DETAILS.
 B. PROVIDE STRUCTURAL EVALUATION OF STRUCTURE.
  
 THESE DOCUMENTS SHALL BE REVIEWED, SIGNED AND SEALED BY
 A DESIGN PROFESSIONAL.
  
 OPTION TO ABOVE REQUIREMENT ?
 YOU MAY PLACE A STATEMENT ON YOUR PLAN THAT THE TENT
 WILL BE REMOVED IF WINDS ARE EXPECTED TO EXCEED 30 MPH
  
 _______________________________________________________
 _________________
  
  
 **ADDITIONAL REQUIREMENTS
 FOR TEMPORARY MEMBRANE STRUCTURES (TENTS) WITH A SPAN
 OF 40 FEET OR GREATER IN ANY DIRECTION:
  
 A. PROVIDE DETAILS OF STRUCTURAL CONNECTIONS. INCLUDE
 BASEPLATE/TIEDOWN DETAILS.
 B. PROVIDE STRUCTURAL EVALUATION OF STRUCTURE.
  
 THESE DOCUMENTS SHALL BE REVIEWED, SIGNED AND SEALED BY
 A DESIGN PROFESSIONAL.
  
 NO EXCEPTIONS
  
 _______________________________________________________
 _________
  
 ***ADDITIONAL REQUIREMENTS
 FOR TEMPORARY MEMBRANE STRUCTURES (TENTS) WITH AN
 ?ASSEMBLY OCCUPANCY CLASSIFICATION AS DEFINED IN THE
 FLORIDA BUILDING CODE WHICH EXCEEDS 5,000 SQ. FT. IN
 AREA AND AN OCCUPANT CONTENT OF GREATER THAN 500
 PERSONS?.
  
 FLORIDA STATUTE 553.79 ?THREHOLD STRUCTURE? SHALL APPLY
  
  A. PROVIDE THRESHOLD INSPECTOR AGREEMENT ? WILL BE
 PROVIDED TO APPLICANT
 B. PROVIDE THRESHOLD INSPECTION PLAN
 C. PROVIDE AFFIDAVIT ?CERTIFICATE OF CODE COMPLIANCE?
 _______________________________________________________
 _______________
  
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved