2019-11-21 14:40:15 | 1) THE DESCRIPTION OF WORK ON THE PERMIT APPLICATION |
| STATES" REMODEL MASTER BATH" YET GAS PLANS HAVE BEEN |
| SUBMITTED. CLARIFY. REVISE THE DESCRIPTION OF WORK ON |
| THE PERMIT APPLICATION.THE APPLICATION SHALL CLEARLY |
| REFLECT THE SCOPE OF WORK TO BE PERFORMED. WPB AMEND. |
| TO FBC SEC. 107.2.1.2ND REQUEST. |
| 2) WHAT SIZING TABLE IS BEING USED FOR THE LOW PRESSURE |
| SYSTEM. THE PLANS REFER TO TABLE 402.4(5) FOR PIPING IN |
| WALLS. THIS TABLE IS FOR A 2 PSI SYSTEM YET THE GAS |
| PLAN SHOW THIS AS LOW PRESSURE PIPING. CLARIFY. |
| 3) SIZE THE PIPING DDOWNSTREAM OF THE REGULATOR FOR THE |
| EXTERIOR TANKLESS WATER HEATER, AND THE POOL HEATER. |
| 4) SUBMIT TWO COPIES OF A HOUSE PLAN / FLOOR PLAN |
| SHOWING THE LOCATION OF THE TANKLESS WATER HEATER AND |
| THE LOCATION AND DISTANCE OF ANY OPERABLE DOORS OR |
| WINDOWS IN RELATION TO THE TANKLESS WATER HEATER. THE |
| LOCATION OF THE TANKLESS WATER HEATER SHALL COMPLY WITH |
| THE MANUFACTURER'S INSTALLATION INSTRUCTIONS. THE HOUSE |
| PLAN / FLOOR PLAN CAN BE HAND DRAWN. WPB AMEND. TO FBC |
| SEC. 107.2.1. |
| 5) SUBMIT TWO COPIES OF A FLOOR PLAN SHOWING THE |
| LOCATION OF ALL OF THE GAS APPLICANCES. |
| 6) SUBMIT CALCULATIONS FOR COMBUSTION AIR FOR THE STOVE |
| AND THE DRYER PER THE 2017 FBC-RES. SEC.G 2407.1 AND |
| G2439.4 (CLOTHES DRYERS). 2ND REQUEST. |
| |