2019-10-21 11:42:46 | 1) REMOVE ALL OLD DOCUMENTS FROM THE APPLICATION |
| PACKAGE THAT ARE NOT TO BE USED FOR THIS INSTALLATION. |
| DOCUMENTS SHALL BE IN TWO COMPLETE SETS FOR SUBMITTAL |
| AND REVIEW. WPB AMEND. TO FBC SEC. 107.1. |
| 2) ALL PLUMBING PRODUCTS AND MATERIALS SHALL BE LISTED |
| BY A THIRD- PARTY CERTIFICATION AGENCY AS COMPLYING |
| WITH THE REFERENCED STANDARDS. THE SUBMITTED |
| SPECIFICATION SHEETS FOR THE SHOWER DO NOT SHOW ANY |
| TYPE OF LISTING OR CERTIFICATION.SUBMIT SPECIFICATION |
| SHEETS THAT COMPLY. 2017 FBC-PLUMBING SEC. 303.4. 2ND |
| REQUEST. |
| 3) SHT. L3.11 - DETAIL "E" - THERE IS A NOTE ON THE |
| DRYWELL DETAIL THAT STATES" 4 INCH DRAIN PIPE FROM |
| DRINKING FOUNTAIN.NOT REQUIRED FOR SHOWER DRAIN" YET |
| THE SUBMITTED NARRATIVE FOR THE ALTERNATE APPROVAL |
| STATES THAT THE DRINKING FOUNTAIN AND SHOWER WILL |
| DISCHARGE TO THE DRYWELL. HOW IS THE SHOWER DRAINING TO |
| THE DRYWELL? THE INFORMATION ON THE DRAWING AND IN THE |
| NARRATIVE MUST CORRELATE.CLARIFY AND ENSURE THE |
| NARRATIVE AND DRAWING CLEARLY EXPLAIN AND REFLECCT THE |
| SCOPE OF WORK.WPB AMEND. TO FBC SEC. 107.2.1. |
| 4) SUBMIT TWO COPIES OF THE NARRATIVE FOR THE ALTERNATE |
| APPROVAL REQUEST ALONG WITH THE DRYWELL DETAIL. BOTH |
| COPIES SHALL BEAR THE SIGNATURE AND SEAL OF THE DESIGN |
| PROFESSIONAL OF RECORD. FL. ADMIN. CODE RULE |
| 61G15-23.001. |
| |