Plan Review Notes
Plan Review Notes For Permit 19091100
Permit Number 19091100
Review Stop G
Sequence Number 1
Notes
Date Text
2019-10-02 06:47:071) ONE OF THE GAS PLANS HAS BEEN DRAWN IN PENCIL.
 PENCIL IS NOT AN ACCEPTABLE FORMAT. SUBMIT TWO COPIES O
 A GAS DRAWN IN A NON - ERASABLE FORMAT. WPB AMEND. TO
 FBC SEC. 107.1.
 2) THE PERMIT APPLICATION DESRCIBES THE SCOPE OF WORK
 AS INSTALLING A GAS LINE TO A POOL HEATER BUT THE GAS
 DRAWING SHOWS A GENERATOR. CLARIFY.
 3) SUBMIT TWO COPIES OF AN ISOMETRIC DRAWING THAT
 CLEARLY SHOWS THE LENGTH OF ALL CUT SECTIONS OF PIPE
 PER 2017 FBC-FUEL GAS, SECS. 402.4.1, 402.4.2. OR 2017
 FBC-R SEC. G2413.4.1, G2413.4.2.
 4) SHOW THE TYPE OF PIPE MATERIAL BEING INSTALLED, ALL
 PIPE SIZES, TYPE OF GAS (LP OR NATURAL).WPB AMEND. TO
 FBC SEC. 107.2.1.
 5) LIST THE BTU LOAD OF EACH APPLIANCE AND THE TOTAL
 BTU LOAD ON THE SYSTEM. REFER TO THE 2017 FBC-FUEL GAS
 SECS.401.8, 402.2, AND TABLES 402.4 (1) THRU 402.4 (37)
 OR 2017 FBC-RES. SEC. G2413.3, G2413.4 AND TABLES
 G2413.4 (1 ) THROUGH G2413.4 (21).
 6) SHOW THE DISTANCE FROM THE POINT OF DELIVERY, (GAS
 METER / MP REGULATOR / LP TANK) TO THE MOST REMOTE
 OUTLET IN THE BUILDING AND / OR SYSTEM PER THE 2017
 FBC-FUEL GAS SEC.402.4.1, 402.4.2, OR 2017 FBC-RES.
 SEC. G 2413.4.1, G2413.4.2.
 7) INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM
 ON THE PLAN PER 2017 FBC-FUEL GAS SEC.402.1, 402.4.3
 THRU 402.6 OR 2017 FBC RES. SEC. G2413.2, G2413.4.3.
 8) SUBMIT TWO COPIES OF THE MANUFACTURER'S
 SPECIFICATION SHEETS / INSTALLATION MANUAL FOR ALL GAS
 EQUIPMENT TO VERIFY COMPLIANCE WITH STANDARDS NFPA 54,
 NFPA 58, AND FBC-2017 FUEL GAS CODE SEC. 402.2, AND
 301.3 OR 2017 FBC-RES. SEC. G2404.3. GAS APPLIANCES
 SHALL BE LISTED AND LABELED. THE INSTALLATION MANUALS
 FOR ALL GAS APPLIANCES / EQUIPMENT SHALL BE ONSITE AT
 THE TIME OF INSPECTION. FGC SEC.305.1, FBC-RES.
 SEC.G2408.1.
 9) ) SUBMIT TWO COPIES OF THE APPLICABLE SIZING TABLES
 USED TO SIZE THE GAS SYSTEM OR PLACE A NOTE ON THE
 PLANS/DRAWINGS SPECIFYING WHICH SIZING TABLE(S) FROM
 THE GAS CODE OR OTHER STANDARD THAT WERE USED IN THE
 DESIGN OF THIS GAS SYSTEM. REFER TO THE 2017 FBC-FUEL
 GAS SECS. 401.4, 401.8, 402.3, AND TABLES 402.4 (1)
 THRU 402.4 (37) OR 2017 FBC-RES. SEC. G2413.3, G2412.8,
 G2413.1, G2413.2, & G2413.3.
 10) SUBMIT A SITE PLAN THAT SHOWS THE LOCATION OF THE
 POOL HEATER IN RELATION TO BUILDING OPENINGS (SOFFITS)
 AND OPERABLE DOORS AND WINDOWS. THE POOL HEATER EXHAUST
 SHALL BE LOCATED PER THE POOL HEATER INSTALLATION
 MANUAL.
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  
  
  
  
  
  