Date |
Text |
2019-10-02 13:22:54 | |
| 1) THIS PROPOSED BUILDING IS GOING TO BE BUILT IN A AE |
| FLOOD ZONE WITH THE BASE FLOOD BFE: 12.7 FEET NAV88. |
| DURING THE PERMITTING OF THIS STRUCTURE THERE WILL BE |
| REQUIRED (3) DIFFERENT FLOOD ZONE CERTIFICATES |
| REQUIRED: |
| (1) A FLOOD ZONE CERTIFICATE IS REQUIRED AS PART OF THE |
| PLAN REVIEW DOCUMENTS WITH THE PROPOSED FINISH FLOOR |
| HEIGHT. W. P. B. ADMINISTRATIVE CODE 107.3.5.1.1 |
| BUILDING MINIMUM PLAN REVIEW CRITERIA FOR COMMERCIAL |
| BUILDINGS. (8) FLOOD REQUIREMENTS ELEVATIONS, |
| ENCLOSURES, FLOOD DAMAGE-RESISTANT MATERIALS. |
| |
| (2) ONCE THE FIRST FLOOR SLAB IS POURED THE 2ND |
| ELEVATION CERTIFICATE IS REQUIRED. W. P. B. |
| ADMINISTRATIVE CODE 110.3 REQUIRED INSPECTIONS 1.2 |
| FLOOR/ SLAB INSPECTION. IN FLOOD HAZARD AREAS, UPON |
| PLACEMENT OF THE LOWEST FLOOR, INCLUDING BASEMENT, AND |
| PRIOR TO FURTHER VERTICAL CONSTRUCTION, THE ELEVATION |
| CERTIFICATION, REQUIRED IN SECTION 1612.5, SHALL BE |
| SUBMITTED TO THE BUILDING OFFICIAL. |
| |
| (3) BEFORE THE ISSUANCE OF A CERTIFICATE OF OCCUPANCY |
| OR A CERTIFICATE OF COMPLETION THE 3RD FLOOD ZONE |
| CERTIFICATE IS REQUIRED WITH THE HEIGHT OF ALL EXTERIOR |
| ATTENDANTS A/C PADS OR OTHER SLABS FOR GENERATORS. |
| W. P. B. ADMINISTRATIVE CODE 110.3 REQUIRED INSPECTIONS |
| (6) FINAL INSPECTION. TO BE MADE AFTER THE BUILDING IS |
| COMPLETED AND READY FOR OCCUPANCY. 6.1. LOWEST FLOOR |
| ELEVATION. IN FLOOD HAZARD AREAS, AS PART OF THE FINAL |
| INSPECTION, A FINAL CERTIFICATION OF THE LOWEST FLOOR |
| ELEVATION SHALL BE SUBMITTED TO THE AUTHORITY HAVING |
| JURISDICTION. |