2019-09-11 17:45:3709/11/2019 1ST GAS/LP/TANK REVIEW **DENIED** WITH
 COMMENTS
  
 NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS
 TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE
 GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS.
  
 1. GAS RISER DIAGRAM REQUIRED WPB AMENDMENTS TO THE FBC
 SEC. 107.3.5.3 (12) RESIDENTIAL GAS.
 2. SUBMIT AN ISOMETRIC DRAWING THAT CLEARLY SHOWS THE
 LENGTH OF ALL CUT SECTIONS OF PIPE PER 2017 FBC RES.
 SECS. G2413.4.1, G2413.4.2.
 3. SHOW THE TYPE OF PIPE MATERIAL BEING INSTALLED, ALL
 PIPE SIZES, AND THE CORRESPONDING EHD NUMBER OF THE
 CORRUGATED STAINLESS-STEEL TUBING (IF APPLICABLE) FOR
 EACH PIPE SIZE. WPB AMENDMENTS TO THE FBC SEC.107.2.1
 INFORMATION ON CONSTRUCTION DOCUMENTS.
 4. TYPE OF GAS (LP OR NATURAL). WPB AMENDMENTS TO THE
 FBC SEC. 107.2.1 INFORMATION ON CONSTRUCTION DOCUMENTS.
 5. INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM
 ON THE PLAN PER 2017 FBC RES. SEC. G2413.2.
 6. PLEASE SHOW SHUTOFF VALVES, UNIONS, DRIP LEGS, BTU'S
 AND REGULATORS ON ISOMETRIC PER THE 2017 FBC RES. SEC.
 G2420.4.
 7. PLEASE SHOW ALL UNIONS IN FRONT OF REGULATOR 1? OF
 EITHER SIDE PER THE 2017 FBC FG SEC 410.2.
 8. SHOW THE DISTANCE FROM THE POINT OF DELIVERY, (GAS
 METER / MP REGULATOR / LP TANK) TO THE MOST REMOTE
 OUTLET IN THE BUILDING AND/OR SYSTEM PER THE 2017 FBC
 RES. SEC. G2413.4.1.
 9. SUBMIT TWO COPIES OF THE SIZING TABLE USED IN THE
 DESIGN FOR THE GAS SYSTEM OR PLACE A NOTE ON BOTH SETS
 OF PLANS LISTING THE SIZING TABLES FROM GAS CODES OR
 ANOTHER STANDARD THAT WERE USED IN THE DESIGN OF THIS
 SYSTEM PER THE 2017 FBC RES. SEC. G2413.3.
 10. SUBMIT TWO COPIES OF THE FOR INSTALLATION
 CLEARANCES FROM THE TANKLESS INSTALLATION MANUAL. THE
 MANUAL REQUIRES A CLEARANCE OF EITHER 4 FEET OR 12
 INCHES FROM ANY OPERABLE WINDOWS OR DOORS. SHOW THE
 LOCATION OF ALL OPERABLE WINDOWS AND DOORS ON THE PLAN
 AND THE DISTANCE OF THE TANKLESS WATER HEATER FROM
 EACH. WPB AMENDMENTS TO THE FBC SEC. 107.2.1.
 INFORMATION ON CONSTRUCTION DOCUMENTS.
 11. IF THIS TANKLESS UNIT CALL FOR 10.5? WATER COLUMN
 AND THE SERVICE METER DISCHARGES IS A 12? WATER COLUMN
 REQUIRING A REGULATOR FOR THIS UNIT AS PER
 MANUFACTURER'S SPECIFICATION. SUBMIT MANUFACTURER?S
 SPECIFICATIONS FOR THE PRESSURE REGULATORS. REGULATORS
 INSTALLED ON THE EXTERIOR OF THE BUILDING SHALL BE
 APPROVED FOR OUTDOOR INSTALLATION PER THE 2017 FBC RES.
 SEC. G2421.1.
 12. GAS APPLIANCES SHALL BE LISTED AND LABELED. THE
 INSTALLATION MANUALS FOR ALL GAS APPLIANCES/EQUIPMENT
 SHALL BE ONSITE AT THE TIME OF INSPECTION PER THE 2017
 FBC RES. SEC. G2413.2 AND G2404.3.
 13. SUBMIT COMPLETE MANUFACTURER'S SPECIFICATIONS FOR
 THE GAS DRYER, STOVE AND TANKLESS. THE GAS DRYER SHALL
 BE LISTED AND LABELED PER THE 2017 FBC FG RES. SEC.
 G2404.3. THE MANUFACTURER'S SPECIFICATIONS SHALL NOTE
 THE CFM'S THAT ARE BEING EXHAUSTED BY THE DRYER.
 14. TOTAL BTU?S OF ALL APPLIANCES NOT ON PLAN IN P.1B
 FOR THE GAS TOTAL LOAD PER THE WPB AMENDMENTS TO THE
 FBC SEC. 107.2.1 INFORMATION ON CONSTRUCTION DOCUMENTS.
 15. SHOW THE SIZE OF THE LOUVER(S) ON THE DRYER ON
 PLANS AND LOCATION PER THE WPB AMENDMENTS TO THE FBC
 SEC. 107.2.1 INFORMATION ON CONSTRUCTION DOCUMENTS.
  
 WHEN RESUBMITTING PLANS PLEASE INDICATE THE REVISION &
 REMOVE ANY VOIDED SHEETS & REPLACE ANY PAGES AS
 NECESSARY. A TRANSMITTAL LETTER LISTING THE ORIGINAL
 REVIEW COMMENT NUMBER, WITH A DESCRIPTION OF THE
 REVISION, MADE, IDENTIFYING THE SHEET OR SPECIFICATION
 PAGE WHERE THE CHANGES CAN BE FOUND WILL HELP TO
 EXPEDITE YOUR PERMIT. THANK YOU FOR YOUR ANTICIPATED
 COOPERATION.
  
  
 LUIS A. CRESPO
 PLUMBING INSPECTOR /
 PLUMBING PLAN REVIEW
 AVAILABLE FROM 1:00 PM TO 4:00 PM
 [email protected]
 561-805-6720
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved