Plan Review Notes For Permit 19080991 |
Permit Number |
19080991 |
|
Review Stop |
FIRE |
Sequence Number |
1 |
|
Notes |
Date |
Text |
2019-08-21 14:46:54 | THIS PLAN WAS REVIEWED AND APPROVED BY PETER LEDUC, | | FIRE MARSHAL, WITH THE FOLLOWING COMMENTS: | | | | PLEASE CONSIDER THE FOLLOWING AS PROVISO: | | | | THESE PROVISO COMMENTS WILL BE VERIFIED AND CONFIRMED | | AT THE TIME OF FIRE INSPECTION. FAILURE TO FOLLOW THESE | | PROVISO COMMENTS WILL RESULT IN A FAILED FIRE | | INSPECTION. | | | | | | 1) ANY REMOVAL OF WALLS, NEW WALLS OR A RECONSTRUCTION | | OF AREAS PROTECTED BY FIRE SPRINKLERS REQUIRES A REVIEW | | OF THE FIRE SPRINKLER PROTECTION. | | | | | | | | 2) ANY AND ALL WORK ON THE FIRE SPRINKLER SYSTEM SHALL | | BE DONE UNDER SEPARATE SHOP DRAWINGS AND BY CERTIFIED | | FIRE SPRINKLER CONTRACTORS. | | | | | | | | PETER LEDUC | | FIRE MARSHAL | | 561-804-4709 | | [email protected] | | |
|