Date |
Text |
2019-09-09 06:50:21 | 9/9/2019 1ST GAS REVIEW**DENIED** WITH COMMENTS NOTE - |
| A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS TIME |
| AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE GENERATED |
| UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS. |
| |
| 1-SUBMIT 2 COPIES OF THE GENERATORS MANUFACTURES |
| INSTALLATION WPB AMENDMENTS TO THE FBC SEC. 107.2.1. |
| INFORMATION ON CONSTRUCTION DOCUMENTS. |
| |
| 2-PROVIDE COPY OF THE UL LISTING FOR THE GENERATOR, IT |
| SHALL MEET UL 2200 |
| |
| 3-THE BTU LOAD OF THE EXISTING GAS SYSTEM MUST BE ADDED |
| INTO THE TOTAL BTU LOAD ON THE SYSTEM TO ENSURE THE |
| EXISTING SYSTEM IS PROPERLY SIZED. IF UNDERSIZED, THE |
| EXISTING SYSTEM MUST BE REDONE TO ENSURE A SAFE |
| OPERATING SYSTEM. 2017 FBC FUEL GAS SEC. 401.4, 401.8, |
| 402.1, 402.2, 402.3 OR 2017 FBC FUEL GAS SECS.G2412.4, |
| G2412.8, G2413.1, G2413.2, G2413.3. |
| |
| 4-GAS PLAN REVIEW, A GAS PLAN HAS NOT BEEN INCLUDED IN |
| THIS SUBMITTAL PACKAGE. A GAS PLAN REVIEW HAS NOT BEEN |
| PERFORMED AT THIS TIME. A SEPARATE GAS PERMIT AND PLANS |
| WILL BE REQUIRED FOR A CONTRACTOR TO PERFORM THE |
| RELATED WORK. PROVIDE COMPLETE PLANS AND GAS RISER THAT |
| REFLECTS THE ENTIRE SCOPE OF GAS WORK TO BE DONE. AT |
| THIS TIME. WPB AMENDMENTS TO FBC SEC. 107.2.1. |
| |
| 5-WHEN RESUBMITTING PLANS PLEASE INDICATE THE REVISION |
| & REMOVE ANY VOIDED SHEETS & REPLACE ANY PAGES AS |
| NECESSARY. A TRANSMITTAL LETTER LISTING THE ORIGINAL |
| REVIEW COMMENT NUMBER, WITH A DESCRIPTION OF THE |
| REVISION, MADE, IDENTIFYING THE SHEET OR SPECIFICATION |
| PAGE WHERE THE CHANGES CAN BE FOUND WILL HELP TO |
| EXPEDITE YOUR PERMIT. THANK YOU FOR YOUR ANTICIPATED |
| COOPERATION. |
| |
| ATELYO BELISLE |
| PLUMBING INSPECTOR / |
| PLUMBING PLANS EXAMINER |
| AVAILABLE FROM 1:00 PM TO 4:00 PM |
| [email protected] |
| 561-805-6695 |
| |