2019-08-26 15:51:19 | 08/26/2019 1ST PLUMBING REVIEW **DENIED** WITH COMMENTS |
| |
| NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS |
| TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE |
| GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS. |
| |
| 1. ON RISER DIAGRAM MP-1 FIRST FLOOR GUEST BATH SHOWER |
| LABELED AS LAV AND LAV NOT LABELED PLEASE MAKE CHANGES, |
| WPB AMENDMENTS TO THE FBC SEC. 107.3.5.3 (11) |
| RESIDENTIAL PLUMBING. |
| |
| 2. BATH 2 SHOWER IS NOT VENTED CORRECTLY, WET VENT |
| REQUIRED BETWEEN WATER CLOSET AND SHOWER, WPB |
| AMENDMENTS TO THE FBC SEC. 107.3.5.3 (11) RESIDENTIAL |
| PLUMBING. |
| |
| 3. BATH 3 DIAGRAM HAS A WASHING MACHINE ON A 2" DRAIN, |
| PER MANUFACTURE SPECIFICATION ON MOST UNITS REQUIRE A |
| 3" DRAIN LINE, PLEASE SUBMIT SPECS ON WASHING MACHINE |
| OR MAKE CHANGES ON PIPE SIZE, WPB AMENDMENTS TO THE FBC |
| SEC. 107.3.5.3 (11) RESIDENTIAL PLUMBING. |
| |
| 4. SANITARY RISER DIAGRAM MC-1C FOR CABANA BATH FIRST |
| FLOOR STACK TO THE SECOND FLOOR MUST BE ON ITS OWN |
| SYSTEM AND CANNOT VENT ON STACK, NEED KITCHEN ON ITS |
| OWN STACK AND LAV ON ITS OWN BATHROOM GROUP, WILL NEED |
| A AIR ADMITTANCE OR A VENT THROUGH ROOF FOR KITCHEN AND |
| BATHROOM GROUP DOWNSTAIRS, WPB AMENDMENTS TO THE FBC |
| SEC. 107.3.5.3 (11) RESIDENTIAL PLUMBING. |
| |
| 5. SANITARY RISER DIAGRAM MC-1C FOR CABANA BATH SECOND |
| FLOOR WAS LABELED AS 1ST FLOOR PLEASE CHANGE TO 2ND |
| FLOOR AND WASHING MACHINE STACK MUST BE 3" (REFER TO |
| COMMENT 3), SHOWER NEEDS WET VENT BETWEEN WC AND |
| SHOWER, PLEASE CHANGE, WPB AMENDMENTS TO THE FBC SEC. |
| 107.3.5.3 (11) RESIDENTIAL PLUMBING. |
| |
| 6. A BACKFLOW DEVICE (REDUCED PRESSURE ZONE PRINCIPAL |
| BACKLFOW ASSEMBLY) MAY BE REQUIRED PER CITY OF WEST |
| PALM BEACH UTILITIES DEPARTMENT CROSS CONNECTION MANUAL |
| AND ORD #2853-95, PLEASE CALL 561-822-2240 FOR MORE |
| INFORMATION SINCE THIS IS A DUAL DWELLING. |
| |
| 7. A SEPARATE GAS PLAN REVIEW WILL BE REQUIRED A GAS, A |
| GAS PLAN HAS NOT BEEN INCLUDED IN THIS SUBMITTAL |
| PACKAGE. A GAS PLAN REVIEW HAS NOT BEEN PERFORMED AT |
| THIS TIME. A SEPARATE GAS PERMIT AND PLANS WILL BE |
| REQUIRED FOR A CONTRACTOR TO PERFORM THE RELATED WORK. |
| PROVIDE COMPLETE PLANS AND GAS RISER THAT REFLECTS THE |
| ENTIRE SCOPE OF GAS WORK TO BE DONE AT THIS TIME PER |
| THE WPB AMENDMENTS TO FBC SEC. 107.2.1. |
| |
| 8. SHOWER PAN DETAIL REFERS TO PLB 471.5.2 WHICH IS NOT |
| THE RESIDENTIAL CODE 2017 FBC RES. SEC 2709.2 LINING |
| REQUIRED, PLEASE REVISE TO REFLECT RESIDENTIAL CODE, |
| WPB AMENDMENTS TO THE FBC SEC. 107.2.1.4 QUALITY OF |
| BUILDING PLANS. |
| |
| WHEN RESUBMITTING PLANS PLEASE INDICATE THE REVISION & |
| REMOVE ANY VOIDED SHEETS & REPLACE ANY PAGES AS |
| NECESSARY. A TRANSMITTAL LETTER LISTING THE ORIGINAL |
| REVIEW COMMENT NUMBER, WITH A DESCRIPTION OF THE |
| REVISION, MADE, IDENTIFYING THE SHEET OR SPECIFICATION |
| PAGE WHERE THE CHANGES CAN BE FOUND WILL HELP TO |
| EXPEDITE YOUR PERMIT. THANK YOU FOR YOUR ANTICIPATED |
| COOPERATION. |
| |
| LUIS A. CRESPO |
| PLUMBING INSPECTOR / |
| PLUMBING PLAN REVIEW |
| AVAILABLE FROM 1:00 PM TO 4:00 PM |
| [email protected] |