Plan Review Notes For Permit 19071443 |
Permit Number |
19071443 |
|
Review Stop |
P |
Sequence Number |
1 |
|
Notes |
Date |
Text |
2019-08-08 04:18:38 | 1) SHT. 3 OF 3 SHOWS A MAIN DRAIN IN THE SPA AND THE | | PIPING SCHEMATIC SHOWS ONE BUT NOT ON THE PLAN VIEW ON | | SHT. 1. CLARIFY. | | 2) SUBMIT TOTAL DYNAMIC HEAD CALCULATIONS FOR THE | | MAXIMUM SYSTEM FLOW FOR THE SPA.. THE MAXIMUM FLOW OF | | THE PUMP FROM ITS PUMP CURVE AND THE SIMPLIFIED TOTAL | | DYNAMIC HEAD CALCULATION IS NO LONGER ALLOWED TO BE | | USED IN DETERMINING MAXIMUM SYSTEM FLOW RATE PER | | ANSI/APSP/ICC 7 - 2013 SECS. 4.4.9, 4.4.9.1. THE 2013 | | EDITION ADDRESSES FLOW RATE IN GALLONS PER MINUTE | | (GPM). IT REQUIRES THAT MAXIMUM SYSTEM FLOW RATE DOES | | NOT EXCEED THE LISTED MAXIMUM FLOW RATE OF THE SUCTION | | OUTLET FITTING ASSEMBLY (DRAIN COVER).THE TDH | | CALCULATIONS MUST INCLUDE ALL OF THE SYSTEM COMPONENTS | | INCLUDING SUCTION AND RETURN PIPING, FITTINGS, VALVES, | | HEATER, FILTER, AND CHLORINATOR. ALL SYSTEM COMPONENTS | | EXCEPT THE PUMP. | | 3) SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE MAIN | | DRAINS. WPB AMEND. TO FBC SEC. 107.2.1. | | 4) IDENTIFY ON THE PUMP CURVE WHICH CURVE KEY IS | | SPECIFIC TO THE PUMP BEING INSTALLED ON THIS POOL. THIS | | IS NEEDED TO CONFIRM THE MAXIMUM SYSTEM FLOW FROM THE | | TDH CALCULATIONS. ANSI/APSP/ICC 7 - 2013 SECS. 4.4.9, | | 4.4.9.1. | | 5) THE PROJECT SPECIFIC DETAILS ON SHT. 1CALL OUT A VS | | PENTAIR PUMP BUT THE SUBMITTED SPECS ARE FOR A VF PUMP. | | CLARIFY. | | | | TIM LARGE | | CHIEF PLUMBING INSPECTOR | | PLUMBING PLAN REVIEW | | 561-805-6692 | | [email protected] | | | | | | |
|