Plan Review Notes
Plan Review Notes For Permit 19060025
Permit Number 19060025
Review Stop FIRE
Sequence Number 1
Notes
Date Text
2019-06-27 13:27:44THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE
 MARSHAL, WITH THE FOLLOWING COMMENTS:
  
  
 1) IT APPEARS THAT THE FUEL SUPPY IS NATURAL GAS.
  
 THERE ARE NO NATURAL GAS LINS INDICATED. A SEPARATE
 PERMIT IS REQUIRED FOR THE NATURAL GAS LINES INCULDING
 EQUIPEMT SPECIFICATIONS.
  
 PLEASE SHOW THE PROPOSED NATURAL GAS LINES ON THE SITE
 PLAN AND PROVIDE A NOTE STATING UNDER SEPARATE PERMIT.
  
  
  
 2) THERE IS SITE PLAN SHOWING THE SPECIFIC LOCATION OF
 THE GENERATOR INCLUDING ALL DIMENSIONS TO AREA
 BUILDINGS, INCLUDING NEIGHBORING PROPERTIES, AND WINDOW
 AND DOOR AND OTHER OPENINGS.
  
 PER NFPA 110
  
 7.2.2 OUTDOOR EPS INSTALLATIONS.
 7.2.2.1 THE EPS SHALL BE INSTALLED IN A SUITABLE
 ENCLOSURE LOCATED
 OUTSIDE THE BUILDING AND CAPABLE OF RESISTING THE
 ENTRANCE
 OF SNOW OR RAIN AT A MAXIMUM WIND VELOCITY AS REQUIRED
 BY LOCAL BUILDING CODES.
  
 PLEASE PROVIDE SPECIFIC SITE PLAN DETAILS.
  
  
  
 3) THERE IS NO INDICATION OF GENERATOR CLASSIFICATION
 NOR TYPE PER NFPA 110
  
 PER NFPA 110
  
 CHAPTER 4 CLASSIFICATION OF EMERGENCY POWER SUPPLY
 SYSTEMS (EPSSS)
 4.1* GENERAL. THE EPSS SHALL PROVIDE A SOURCE OF
 ELECTRICAL
 POWER OF REQUIRED CAPACITY, RELIABILITY, AND QUALITY TO
 LOADS FOR
 A LENGTH OF TIME AS SPECIFIED IN TABLE 4.1(A) AND
 WITHIN A SPECIFIED
 TIME FOLLOWING LOSS OR FAILURE OF THE NORMAL POWER
 SUPPLY
 AS SPECIFIED IN TABLE 4.1(B).
 4.2* CLASS. THE CLASS DEFINES THE MINIMUM TIME, IN
 HOURS, FOR
 WHICH THE EPSS IS DESIGNED TO OPERATE AT ITS RATED LOAD
 WITHOUT
 BEING REFUELED OR RECHARGED. [SEE TABLE 4.1(A).]
 4.3 TYPE. THE TYPE DEFINES THE MAXIMUM TIME, IN
 SECONDS,
 THAT THE EPSS WILL PERMIT THE LOAD TERMINALS OF THE
 TRANSFER
 SWITCH TO BE WITHOUT ACCEPTABLE ELECTRICAL POWER. TABLE
 4.1(B)
 PROVIDES THE TYPES DEFINED BY THIS STANDARD.
 4.4* LEVEL. THIS STANDARD RECOGNIZES TWO LEVELS OF
 EQUIPMENT
 INSTALLATION, PERFORMANCE, AND MAINTENANCE.
 4.4.1* LEVEL 1 SYSTEMS SHALL BE INSTALLED WHERE FAILURE
 OF THE
 EQUIPMENT TO PERFORM COULD RESULT IN LOSS OF HUMAN LIFE
 OR
 SERIOUS INJURIES.
 4.4.2* LEVEL 2 SYSTEMS SHALL BE INSTALLED WHERE FAILURE
 OF THE
 EPSS TO PERFORM IS LESS CRITICAL TO HUMAN LIFE AND
 SAFETY.
 4.4.3 ALL EQUIPMENT SHALL BE PERMANENTLY INSTALLED.
 4.4.4* LEVEL 1 AND LEVEL 2 SYSTEMS SHALL ENSURE THAT
 ALL LOADS
 SERVED BY THE EPSS ARE SUPPLIED WITH ALTERNATE POWER
 THAT
 MEETS ALL THE FOLLOWING CRITERIA:
 (1) OF A QUALITY WITHIN THE OPERATING LIMITS OF THE
 LOAD
 (2) FOR A DURATION SPECIFIED FOR THE CLASS AS DEFINED
 IN TABLE
 4.1(A)
 (3) WITHIN THE TIME SPECIFIED FOR THE TYPE AS DEFINED
 IN TABLE
 4.1(B)
  
 PLEASE PROVIDE DETAILS AS THIS IS HOW IT WILL INSPECTED
 AND THE ACCEPTANCE TESTING.
  
  
  
  
 4) WHEN RESUBMITTING, PLEASE PROVIDE PLAN SHEET
 REVISION CLOUDS OR NUMBERED NARRATIVE RESPONSES TO THE
 ABOVE.
  
  
  
  
 5) ADDITIONAL COMMENTS MAY BE PROVIDED ON THE
 RE-SUBMITTAL OF THE ABOVE.
  
  
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]
  