Plan Review Notes For Permit 19051062
Permit Number 19051062
Review Stop G
Sequence Number 1
Notes
Date Text
2019-05-24 15:43:3805/24/2019 1ST GAS REVIEW**DENIED** WITH COMMENTS NOTE
 - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS TIME
 AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE GENERATED
 UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS.
  
 1. THE ADDRESS OF THE PROJECT OR RESIDENCE MUST BE ON
 PLAN. WPB AMENDMENTS TO THE FBC SEC.107.2.1 INFORMATION
 ON CONSTRUCTION DOCUMENTS.
  
 2. INDICATE ON THE PLAN IF THE TANKLESS WATER HEATER IS
 THE ONLY GAS APPLIANCE IN THIS SYSTEM? IF NOT, SUBMIT A
 COMPLETE GAS RISER SHOWING ALL PIPE SIZES, TYPE OF
 PIPE, THE DEVELOPED LENGTH TO THE FURTHEST GAS OUTLET,
 THE BTU LOAD OF EACH APPLIANCE (REFER TO ITEM 9), THE
 PSI OF THE SYSTEM, THE TYPE OF GAS AND THE TOTAL BTU
 LOAD ON THE SYSTEM (REFER TO ITEM 13). THESE
 REQUIREMENTS ALSO APPLY TO A NEW GAS SYSTEM. WPB
 AMENDMENTS TO THE FBC SEC. 107.3.5.3 (12) RESIDENTIAL
 GAS.
  
 3. SUBMIT TWO COPIES OF A HOUSE PLAN SHOWING THE
 LOCATION OF THE TANKLESS WATER HEATER AND THE LOCATION
 AND DISTANCE OF ANY OPERABLE DOORS OR WINDOWS IN
 RELATION TO THE WATER HEATER. THE LOCATION OF THE WATER
 HEATER SHALL COMPLY WITH THE MANUFACTURER'S
 INSTALLATION INSTRUCTIONS. THE HOUSE PLAN CAN BE HAND
 DRAWN. WPB AMENDMENTS TO THE FBC SEC. 107.2.1.
 INFORMATION ON CONSTRUCTION DOCUMENTS.
  
 4. SUBMIT AN ISOMETRIC DRAWING THAT CLEARLY SHOWS THE
 LENGTH OF ALL CUT SECTIONS OF PIPE PER 2017 FBC FUEL
 GAS, SECS. 402.4.1, 402.4.2. OR 2017 FBC FUEL GAS RES
 SECS. G2413.4.1, G2413.4.2.
  
 5. SHOW THE TYPE OF PIPE MATERIAL BEING INSTALLED, ALL
 PIPE SIZES, AND THE CORRESPONDING EHD NUMBER OF THE
 CORRUGATED STAINLESS STEEL TUBING (IF APPLICABLE) FOR
 EACH PIPE SIZE. WPB AMENDMENTS TO THE FBC SEC.107.2.1
 INFORMATION ON CONSTRUCTION DOCUMENTS.
  
 6. TYPE OF GAS (LP OR NATURAL). WPB AMENDMENTS TO THE
 FBC SEC. 107.2.1 INFORMATION ON CONSTRUCTION DOCUMENTS.
  
  
 7. SHOW THE LOCATION OF ALL MP (STEP-DOWN) REGULATORS.
 A LISTED SHUTOFF VALVE SHALL BE INSTALLED IMMEDIATELY
 AHEAD OF EACH MP REGULATOR. 2017 FBC FUEL GAS RES. SEC.
 G2420.4.
  
 8. LIST THE BTU LOAD OF EACH APPLIANCE AND THE TOTAL
 BTU LOAD ON THE SYSTEM. REFER TO THE 2017 FBC FUEL GAS
 RES. SEC. G2413.
  
 9. SHOW THE DISTANCE FROM THE POINT OF DELIVERY, (GAS
 METER / MP REGULATOR / LP TANK) TO THE MOST REMOTE
 OUTLET IN THE BUILDING AND/OR SYSTEM PER THE 2017 FBC
 FUEL GAS SEC. 402.4.1 OR 2017 FBC FUEL GAS RES. SEC.
 G2413.4.1.
  
 10. SUBMIT MANUFACTURER?S SPECIFICATION
 SHEETS/INSTALLATION MANUAL FOR ALL GAS EQUIPMENT
 (RANGE, CLOTHE DRYER, POOL HEATER, TANKLESS HEATER AND
 OR STOVE) TO VERIFY COMPLIANCE WITH 2017 FBC FUEL GAS
 RES. SEC. G2408.1.
  
  
 11. GAS APPLIANCES SHALL BE LISTED AND LABELED. THE
 INSTALLATION MANUALS FOR ALL GAS APPLIANCES/EQUIPMENT
 SHALL BE ONSITE AT THE TIME OF INSPECTION 2017 FBC FUEL
 GAS RES. SEC. G2413.2 AND G2404.3.
  
 12. SUBMIT TWO COPIES OF THE SIZING TABLE USED IN THE
 DESIGN FOR THE GAS SYSTEM OR PLACE A NOTE ON BOTH SETS
 OF PLANS LISTING THE SIZING TABLES FROM GAS CODES OR
 ANOTHER STANDARD THAT WERE USED IN THE DESIGN OF THIS
 SYSTEM 2017 FBC FUEL GAS RES. SEC. G2413.3
  
 13. THE PLANS ON RECORD INDICATE AN EXISTING GAS METER.
 THE BTU LOAD OF THE EXISTING GAS SYSTEM MUST BE ADDED
 INTO THE TOTAL BTU LOAD ON THE SYSTEM TO ENSURE THE
 EXISTING SYSTEM IS PROPERLY SIZED. IF UNDERSIZED, THE
 EXISTING SYSTEM MUST BE REDONE TO ENSURE A SAFE
 OPERATING SYSTEM. SUBMIT A GAS PIPING RISER DIAGRAM
 THAT SHOWS THE TYPE OF EXISTING APPLIANCE, THE BTU LOAD
 OF EACH APPLIANCE, THE PIPE SIZE AND TYPE OF PIPE TO
 EACH APPLIANCE, AND THE DISTANCE OF THE LONGEST LENGTH
 OF PIPING FROM THE POINT OF DELIVERY TO THE MOST REMOTE
 OUTLET AND THE LOAD OF THE SECTION. NOTE: IF THE
 EXISTING SYSTEM IS LESS THAN A 2 PSI SYSTEM AND THE
 SYSTEM PRESSURE IS INCREASED TO 2 PSI, A LINE PRESSURE
 REGULATOR IS REQUIRED AT ALL THE EXISTING APPLIANCES
 2017 FBC FUEL GAS RES. SECS.G2412.4, G2412.8, G2413.1,
 G2413.2, G2413.3.
  
 14. THE CLAIMED VALUE APPEARS TO BE UNDERESTIMATED ON
 THE APPLICATION, PLEASE PROVIDE A BONA FIDE SIGNED
 CONTRACT. WPB AMENDMENTS TO THE FBC 109.3. BUILDING
 PERMITS VALUATIONS.
 15. A SUB ELECTRICAL PERMIT IS REQUIRED FOR THE SOURCE
 OF IGNITION, WPB AMENDMENTS TO THE FBC SEC. 105.1
  
 WHEN RESUBMITTING PLANS PLEASE INDICATE THE REVISION &
 REMOVE ANY VOIDED SHEETS & REPLACE ANY PAGES AS
 NECESSARY. A TRANSMITTAL LETTER LISTING THE ORIGINAL
 REVIEW COMMENT NUMBER, WITH A DESCRIPTION OF THE
 REVISION, MADE, IDENTIFYING THE SHEET OR SPECIFICATION
 PAGE WHERE THE CHANGES CAN BE FOUND WILL HELP TO
 EXPEDITE YOUR PERMIT. THANK YOU FOR YOUR ANTICIPATED
 COOPERATION.
  
 LUIS A. CRESPO
 PLUMBING INSPECTOR /
 PLUMBING PLAN REVIEW
 AVAILABLE FROM 1:00 PM TO 4:00 PM
 [email protected]
 561-805-6720
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved