2019-03-18 17:07:5103/18/19 3RD GAS REVIEW (NEW CONTRACTOR)**DENIED***
  
  
 1) THIS APPLICATION HAS DOCUMENTS FROM THE OLD AND NEW
 CONTRACTOR MAKING IT DIFFICULT TO DETERMINE WHAT IS
 WHAT. PLEASE REMOVE ALL PAPERWORK THATS NOT NEEDED. FBC
 107.1
  
 2) VALVE TOO LOW. THE TOTAL VALVE OF THIS JOB MUST
 INCLUDE THE COST OF THE RANGE AND TANKLESS. PLEASE
 ADVISED IF THESE APPLIANCES ARE NEW. 109.3 BUILDING
 PERMIT VALUATIONS. IF, IN THE OPINION OF THE BUILDING
 OFFICIAL, THE CLAIMED VALUATIONOF BUILDING, ALTERATION,
 STRUCTURE, ELECTRICAL, GAS, MECHANICAL OR PLUMBING
 SYSTEMS APPEARS TO BEUNDERESTIMATED ON THE APPLICATION,
 THE PERMIT SHALL BE DENIED, UNLESS THE APPLICANT CAN
 SHOWDETAILED, QUANTITY ESTIMATES, AND/OR BONA FIDE
 SIGNED CONTRACTS (EXCLUDING LAND VALUE) TO MEET THE
 APPROVAL OF THE BUILDING OFFICIAL. FOR PERMITTING
 PURPOSES, VALUATION OF BUILDINGS AND SYSTEMS SHALLBE
 TOTAL REPLACEMENT VALUE TO INCLUDE STRUCTURAL,
 ELECTRIC, PLUMBING, MECHANICAL, INTERIOR
 FINISH,RELATIVE SITE WORK, ARCHITECTURAL AND DESIGN
 FEES, MARKETING COSTS, OVERHEAD AND PROFIT;
 EXCLUDINGONLY LAND VALUE. VALUATION REFERENCES MAY
 INCLUDE THE LATEST PUBLISHED DATA OF
 NATIONALCONSTRUCTION COST ANALYSIS SERVICES
 (MARSHALL-SWIFT, MEANS, ETC.), AS PUBLISHED BY
 INTERNATIONALCODE CONGRESS. FINAL BUILDING PERMIT
 VALUATION SHALL BE SET BY THE BUILDING OFFICIAL.
  
 3) SUBMIT COMPLETE MANUFACTURER?S SPECIFICATION SHEETS
 / INSTALLATION MANUAL FOR ALL GAS EQUIPMENT TO VERIFY
 COMPLIANCE WITH STANDARDS NFPA 54, NFPA 58, AND
 FBC-2017 FUEL GAS CODE SEC. 402.2, AND 301.3 OR 2017
 FBC-RES. SEC. G2404.3. GAS APPLIANCES SHALL BE LISTED
 AND LABELED. THE INSTALLATION MANUALS FOR ALL GAS
 APPLIANCES / EQUIPMENT SHALL BE ONSITE AT THE TIME OF
 INSPECTION. FGC SEC.305.1, FBC-RES. SEC.G2408.1.
  
 4) SUBMIT TWO COPIES OF A HOUSE PLAN SHOWING THE
 LOCATION OF THE TANKLESS WATER HEATER AND THE LOCATION
 AND DISTANCE OF ANY OPERABLE DOORS OR WINDOWS IN
 RELATION TO THE WATER HEATER. THE LOCATION OF THE WATER
 HEATER SHALL COMPLY WITH THE MANUFACTURER'S
 INSTALLATION INSTRUCTIONS. THE HOUSE PLAN CAN BE HAND
 DRAWN. WPB AMEND. TO FBC SEC. 107.2.1.
  
 5 )SUBMIT COMBUSTION AIR CALCULATIONS FOR THE ADDED GAS
 STOVE. WHERE COMBUSTION AIR IS PROVIDED BY THE
 BUILDING?S MECHANICAL VENTILATION SYSTEM, THE SYSTEM
 SHALL PROVIDE THE SPECIFIED COMBUSTION AIR RATE IN
 ADDITION TO THE REQUIRED VENTILATION AIR. 2017 FBC-FUEL
 GAS SEC.304.9.3 OR FBCR G2407.9.3.
  
 6) BY CHANGING THE GAS SYSTEM FROM .5LB TO 2LB PLEASE
 PROVIDE THE MANUFACTURER?S SPECIFICATIONS FOR THE
 PRESSURE REGULATORS. REGULATORS INSTALLED ON THE
 EXTERIOR OF THE BUILDING SHALL BE APPROVED FOR OUTDOOR
 INSTALLATION. 2014 FGC SEC.410.1, 2017 FBC-RES. SEC.
 G2421.1.
  
 NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS
 TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE
 GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS
  
 TIM HUNT
 PLUMBING INSPECTOR/PLUMBING PLAN EXAMINER
 BUILDING DIVISION
 CITY OF WEST PALM BEACH
 561-248-2703
 [email protected]
  
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved