Date |
Text |
2018-12-28 15:17:56 | FAILED |
| |
| PROVIDE WRITTEN RESPONSES TO COMMENTS. |
| |
| 1) REPEAT COMMENT: THE STAIRWELL MULLIONS WERE APPROVED |
| WITH DEPTH ON THE EXTERIOR OF THE GLAZING. THE |
| SUBMITTED PLANS DO NOT DEMONSTRATE THAT THEY EXTEND |
| PAST THE GLAZING. ----- THE RESPONSE STATES THAT THE |
| MULLIONS ARE A "PRONOUNCED 1 INCH" BEYOND THE CURTAIN |
| WALL. ZONING STAFF STILL COULD NOT DETERMINE WHICH |
| DETAIL CLEARLY SHOWS THE 1 INCH PROJECTION. |
| ADDITIONALLY, THE RESPONSE STATES THAT BREAK METAL WILL |
| BE APPLIED TO THESE MULLIONS TO PROVIDE ADDITIONAL |
| DEPTH. THIS WAS ALSO NOT DEMONSTRATED ON THE |
| RESUBMITTED PLANS. |
| |
| 2) REPEAT COMMENT: PHOTOMETRICS TO THE EDGE OF THE SITE |
| ARE REQUIRED SINCE THERE IS EXTERIOR LIGHTING SHOWN. |
| ----- IT APPEARS THAT THIS PERMIT IS TO INCLUDE THE |
| ROOFTOP AND CANOPY LIGHTING, SO PHOTOMETRICS ARE |
| REQUIRED AS WELL AS DETAILS TO VERIFY THAT THE LIGHTING |
| MOUNTED UNDER THE CANOPIES MUST BE FLUSH MOUNTED IN THE |
| FIXTURES AND NOT EXTEND BELOW THE LOWEST POINT OF THE |
| CANOPY. IF THE LIGHTING WILL BE PART OF A SEPARATE |
| PERMIT SUBMITTAL, THEN THIS NEEDS TO BE CLEARLY STATED |
| ON THE PLANS AND THIS COMMENT CAN BE RESERVED FOR THE |
| LIGHTING PERMIT. |
| |
| 3) PLEASE REMEMBER THAT RESOLUTION NO. 68-18 REQUIRES |
| THAT PRIOR TO THE ISSUANCE OF THE CERTIFICATE OF |
| OCCUPANCY FOR THE VALET GARAGE, THE KRAVIS CENTER MUST: |
| A. PAY THE CITY FOR THE REMOVAL OF ANY STANDARD PARKING |
| SPACES ALONG IRIS STREET. THE TWO ADA SPACES ARE BEING |
| REPLACED BY THE RELOCATED TROLLEY STOP AND THUS NO |
| COMPENSATION IS REQUIRED FOR THESE SPACES. |
| B. SECURE CITY RIGHT-OF-WAY PERMITS FOR THE SAPODILLA |
| AVENUE AND IRIS STREET IMPROVEMENTS, TO INCLUDE |
| CURBING, APRONS, STREET TREES, TREE GRATES, |
| LANDSCAPING, IRRIGATION AND LIGHTING. |
| C. COMPLETE AND PASS INSPECTIONS FOR THE SAPODILLA |
| AVENUE AND IRIS STREET IMPROVEMENTS, INCLUDING CURBING, |
| APRONS, STREET TREES, TREE GRATES, LANDSCAPING, |
| IRRIGATION, LIGHTING AND THE TROLLEY STOP. |
| D. AGREE TO A RIGHT-OF-WAY MAINTENANCE AGREEMENT WITH |
| THE CITY FOR ALL OF THE SAPODILLA AVENUE AND IRIS |
| STREET IMPROVEMENTS. BY THIS RESOLUTION, THE CITY |
| COMMISSION AUTHORIZES THE MAYOR TO EXECUTE A |
| RIGHT-OF-WAY MAINTENANCE AGREEMENT WITH THE KRAVIS |
| CENTER FOR THE PERFORMING ARTS. |
| |
| 4) DUE TO THE CHANGES TO THE PLANS APPROVED AS PART OF |
| RESOLUTION NO. 68-18, AN AS BUILT MINOR PLANNED |
| DEVELOPMENT AMENDMENT FOR ANY CHANGED PLANS IS REQUIRED |
| PRIOR TO CO. |
| |
| 5) THE SURFACE LOT REQUIRES SEPARATE PERMIT WITH PLANS. |
| |
| CONTACT ERIC SCHNEIDER @ (561) 822-1446 |
| [email protected] |
| |