2018-09-14 15:20:48 | THIS PLAN WAS REVIEWED AND APPROVED BY PETER LEDUC, |
| FIRE MARSHAL, WITH THE FOLLOWING COMMENTS: |
| |
| PLEASE CONSIDER THE FOLLOWING AS PROVISO: |
| |
| THESE PROVISO COMMENTS WILL BE VERIFIED AND CONFIRMED |
| AT THE TIME OF FIRE INSPECTION. FAILURE TO FOLLOW THESE |
| PROVISO COMMENTS WILL RESULT IN A FAILED FIRE |
| INSPECTION. |
| |
| |
| |
| 1) THERE ARE NO CLEAR INDICATIONS OF LIGHTNING |
| PROTECTION. |
| |
| LIGHTNING PROTECTION SHALL COMPLY WITH NFPA 780, |
| INSTALLATION OF LIGHTNING PROTECTION SYSTEMS |
| |
| CHAPTER 12 PROTECTION FOR SOLAR ARRAYS |
| 12.1 GENERAL. THE INTENT OF THIS CHAPTER SHALL BE TO |
| PROVIDE |
| LIGHTNING PROTECTION REQUIREMENTS FOR ROOF-MOUNTED OR |
| GROUND-MOUNTED SOLAR (PHOTOVOLTAIC AND THERMAL) PANELS. |
| 12.2 FUNDAMENTAL PRINCIPLES OF PROTECTION. |
| 12.2.1 ROOF-MOUNTED OR GROUND-MOUNTED SOLAR PANELS |
| SUBJECT |
| TO DIRECT LIGHTNING STRIKE SHALL BE PROTECTED IN |
| ACCORDANCE |
| WITH CHAPTER 4 AND AS SUPPLEMENTED IN THIS CHAPTER. |
| 12.2.2 PROTECTION SHALL BE PROVIDED BY ONE OR MORE OF |
| THE |
| FOLLOWING METHODS: |
| (1) DIRECT MOUNTING OF STRIKE TERMINATION DEVICES TO |
| THE SOLAR |
| PANEL |
| (2) DIRECT MOUNTING OF STRIKE TERMINATION DEVICES TO |
| THE SOLAR |
| PANEL FRAMING |
| (3) LOCATING STRIKE TERMINATION DEVICES (INCLUDING AIR |
| TERMINALS, |
| MASTS, AND OVERHEAD GROUND WIRES) ADJACENT TO THE |
| SOLAR PANELS IN SUCH A MANNER AS TO PLACE THE SOLAR |
| PANELS |
| IN A ZONE OF PROTECTION AS DEFINED IN SECTION 4.8 |
| 12.3 STRIKE TERMINATION DEVICES. |
| 12.3.1 STRIKE TERMINATION DEVICES SHALL EXTEND A |
| MINIMUM OF |
| 10 IN. (254 MM) VERTICALLY ABOVE THE APEX OF THE SOLAR |
| PANEL. |
| 12.3.2 STRIKE TERMINATION DEVICES SHALL BE LOCATED AT |
| THE ENDS |
| OF THE UPPERMOST EDGE OR NEAREST SUPPORT OF PITCHED |
| SOLAR |
| PANELS OR PANEL ARRAYS NOT TO EXCEED 2 FT (0.6 M) FROM |
| THE END |
| OF THE PANEL OR ARRAY UNLESS THE UPPERMOST EDGE OR |
| NEAREST |
| SUPPORT IS WITHIN A ZONE OF PROTECTION. |
| 12.3.3 STRIKE TERMINATION DEVICES SHALL BE LOCATED |
| ALONG THE |
| UPPERMOST EDGE OF SOLAR PANELS OR PANEL ARRAYS AT |
| INTERVALS NOT |
| EXCEEDING 20 FT (6 M) UNLESS THE PANEL ARRAYS ARE |
| WITHIN A ZONE |
| OF PROTECTION. |
| |
| |
| PLEASE PROVIDE THE REQUIRED PROTECTION. |
| |
| |
| 2) THE POWER DICONNECT SHALL BE CLEARED MARKED WITH |
| AREA DIRECTIONAL SIGNAGE IF NEEDED. |
| |
| |
| PETER LEDUC |
| FIRE MARSHAL |
| 561-804-4709 |
| [email protected] |
| |