2018-09-28 18:59:5709/28/2018 1ST POOL PLUMBING REVIEW**DENIED** WITH
 COMMENTS
  
 NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS
 TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE
 GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS.
  
 1. SHOW HOW EXISTING SANITARY WILL CONNECT TO THE NEW
 SYSTEM ON THE SECOND FLOOR IN MASTER AND BATH 2 FOR THE
 PLUMBING RISER DIAGRAM, WPB AMENDMENTS TO THE FBC SEC.
 107.3.5.3 (11) RESIDENTIAL PLUMBING.
  
 2. THERE IS NO VALUE LISTED ON THE PLUMBING
 SUB-APPLICATION AND THE OVERALL VALUE IS LOW. WPB
 AMENDMENTS TO THE FBC 109.3 BUILDING PERMITS
 VALUATIONS. IF IN THE OPINION OF THE BUILDING OFFICIAL,
 THE CLAIMED VALUATION OF BUILDING, ALTERATION,
 STRUCTURE, ELECTRICAL, GAS, MECHANICAL OR PLUMBING
 SYSTEMS APPEARS TO BE UNDERESTIMATED ON THE
 APPLICATION, THE PERMIT SHALL BE DENIED UNLESS THE
 APPLICANT CAN SHOW DETAILED, QUANTITY ESTIMATES, AND/OR
 BONA FIDE SIGNED CONTRACTS (EXCLUDING LAND VALUE) TO
 MEET THE APPROVAL OF THE BUILDING OFFICIAL. FOR
 PERMITTING PURPOSES, VALUATION OF BUILDINGS AND SYSTEMS
 SHALL BE TOTAL REPLACEMENT VALUE TO INCLUDE STRUCTURAL,
 ELECTRIC, PLUMBING, MECHANICAL, INTERIOR FINISH,
 RELATIVE SITE WORK, ARCHITECTURAL AND DESIGN FEES,
 MARKETING COSTS, OVERHEAD AND PROFIT; EXCLUDING ONLY
 LAND VALUE. VALUATION REFERENCES MAY INCLUDE THE LATEST
 PUBLISHED DATA OF NATIONAL CONSTRUCTION COST ANALYSIS
 SERVICES (MARSHALL-SWIFT, MEANS, ETC.), AS PUBLISHED BY
 INTERNATIONAL CODE CONGRESS. FINAL BUILDING PERMIT
 VALUATION SHALL BE SET BY THE BUILDING OFFICIAL.
  
 3. TUB STANDALONE REQUIRED A CONTROL VALVE BY A WATER
 TEMPERATURE LIMITING DEVICE THAT CONFORMS TO ASSE 1070
 OR CSA B125.3, EXCEPT WHERE SUCH PROTECTION IS
 OTHERWISE PROVIDED BY A COMBINATION TUB/SHOWER VALVE IN
 ACCORDANCE WITH SECTION P2708.4. FBC R 2713.3 BATHTUB
 AND WHIRLPOOL BATHTUB VALVES. SHOWER PAN MUST HAVE A
 SLOPED MORTAR BED THAT IS PRE-PITCHED BENEATH PRIOR TO
 LINER INSTALLATION OF 1/4" IN PER FOOT TOWARD THE
 DRAIN, MUST HAVE DAM CORNER, BACKING AROUND THE
 PERIMETER AND BEFORE FINAL MORTAR APPLICATION PLACE
 SOME PEA GRAVEL OVER WEEP HOLES SO THE MORTAR DOES NOT
 COVER THEM PER MANUFACTURES SPECIFICATIONS.
  
 4. IF THE SHOWER PAN IS NOT RECEDED IT WILL REQUIRE
 LINING FBC R 2709.2 SHOW DETAIL OF SHOWER LINING
 REQUIRED. THE LINING MATERIAL SHALL EXTEND NOT LESS
 THAN 2 INCHES BEYOND OR AROUND THE ROUGH JAMBS AND NOT
 LESS THAN 2 INCHES ABOVE FINISHED THRESHOLDS.
 SHEET-APPLIED LOAD-BEARING, BONDED WATERPROOF MEMBRANES
 SHALL BE APPLIED IN ACCORDANCE WITH THE MANUFACTURER?S
 INSTRUCTIONS.
  
 WHEN RESUBMITTING PLANS PLEASE INDICATE THE REVISION &
 REMOVE ANY VOIDED SHEETS & REPLACE ANY PAGES AS
 NECESSARY. A TRANSMITTAL LETTER LISTING THE ORIGINAL
 REVIEW COMMENT NUMBER, WITH A DESCRIPTION OF THE
 REVISION, MADE, IDENTIFYING THE SHEET OR SPECIFICATION
 PAGE WHERE THE CHANGES CAN BE FOUND WILL HELP TO
 EXPEDITE YOUR PERMIT. THANK YOU FOR YOUR ANTICIPATED
 COOPERATION.
  
 LUIS A. CRESPO
 PLUMBING INSPECTOR /
 PLUMBING PLAN REVIEW
 AVAILABLE FROM 1:00 PM TO 4:00 PM
 [email protected]
 561-805-6720
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved