Date |
Text |
2018-12-18 15:19:53 | 2ND REVIEW FBC-2017 MECHANICAL |
| PERMIT #18081039 |
| 12/18/18 |
| |
| CODES IN EFFECT: |
| |
| FBC B- FLORIDA BUILDING CODE SIXTH EDITION 2017 |
| FBC M- FLORIDA MECHANICAL CODE SIXTH EDITION 2017 |
| FBC EC- FLORIDA ENERGY CONSERVATION CODE SIXTH EDITION |
| 2017 |
| FBC R- FLORIDA RESIDENTIAL CODE SIXTH EDITION 2017 |
| FBC FG- FLORIDA FUEL GAS CODE SIXTH EDITION 2017 |
| FS- FLORIDA STATUTES |
| FAC- FLORIDA ADMINISTRATIVE CODE |
| WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH |
| EDITION 2017 |
| GUIDELINES FOR DESIGN AND CONSTRUCTION OF HEALTH CARE |
| FACILITIES |
| ASHRAE 170-2008. |
| |
| PLAN REVIEW RESULTS: DENIED. |
| |
| AN INCOMPLETE RESPONSE NARRATIVE TO MECHANICAL COMMENTS |
| THAT ENDED AT COMMENT #17 WAS UPLOADED WITH THE |
| CORRECTED PLANS. MISSING FROM THE NARRATIVE ARE |
| RESPONSES TO COMMENTS #18- 32. |
| |
| 1) THE COMCHECK COMPLIANCE REPORT IS MISSING DATA FOR |
| THE CHILLERS AND THE FAN COIL UNITS. PLEASE NOTE THAT |
| THE 8.78 EER FOR CH-1 SHOWN IN THE EQUIPMENT SCHEDULE |
| DOES NOT MEET COMPLIANCE WITH TABLE C403.2.3(7) FBC EC. |
| |
| 2) SHEET M-701: PLEASE LIST THE COOLING AND HEATING |
| CAPACITIES OF THE AHU 1 & 2, AND DOAS 1 & 2 IN THE |
| EQUIPMENT SCHEDULES- SECTION C403.2.1 FBC EC. |
| |
| 3) PLEASE VERIFY THAT COMMISSIONING OF THE MECHANICAL, |
| AND ELECTRICAL POWER AND LIGHTING SYSTEMS WILL BE |
| ACCOMPLISHED BY EITHER PROVIDING A NOTE OR AN OUTLINE |
| ON THE PLAN. |
| |
| 4) M-703: THE ASHRAE 170 VENTILATION RATE SCHEDULE IS |
| INCOMPLETE. PLEASE REFER TO TABLE 7-1 ASHRAE 170-2008 |
| AND PROVIDE COMPLETE DESIGN PARAMETERS THAT INCLUDE |
| PRESSURE RELATIONSHIPS TO ADJACENT AREAS, MINIMUM TOTAL |
| ACH, EXHAUST AND RECIRCULATION AIR, RELATIVE HUMIDITY, |
| AND TEMPERATURE. ALSO MISSING FROM THE SCHEDULE ARE THE |
| DESIGN PARAMETERS FOR THE SOILED AND CLEAN HOLDING AND |
| UTILITY ROOMS, AND THE HAZARDOUS STORAGE ROOM. INDICATE |
| HOW THE PRESSURE RELATIONSHIPS WILL BE MONITORED. WILL |
| SENSORS BE INSTALLED? |
| |
| 5) M-201: THE REQUESTED MANUFACTURER'S SPECIFICATIONS |
| FOR THE GENERATOR AND ASSOCIATED EQUIPMENT INCLUDING |
| THE VENT PIPING WERE NOT SUBMITTED. THE EXHAUST FLUE |
| TERMINATION REQUIRED CLEARANCE MEASUREMENTS NOT |
| PROVIDED ON THE PLAN. A) PROVIDE AN EXHAUST FLUE |
| DIAGRAM THAT INCLUDES THE TOTAL RUN LENGTH, AND |
| INDICATE HOW THE PIPE WILL BE SUPPORTED. B) VERIFY THE |
| EXHAUST SYSTEM INCLUDING SILENCER COMPLY WITH THE |
| GENERATOR ENGINE'S MAX BACKPRESSURE- PLEASE PROVIDE A |
| CALCULATION. C) CLARIFY HOW THE RADIATOR EXHAUST AT THE |
| TOP OF THE GENERATOR WILL BE VENTED TO THE OUTDOORS. |
| THE GENERATOR ROOM IS ONLY OPEN ON ONE SIDE AND MAY BE |
| SUBJECT TO POSITIVE PRESSURE WHICH WOULD TRAP THE |
| EXHAUST IN THE ROOM. |
| |
| 6) M-201 & M-703: PROVIDE THE DESIGN PARAMETERS AND |
| EXHAUST CALCULATIONS FOR THE MRI ROOMS ON THE PLANS AND |
| IN THE VENTILATION SCHEDULE. B) PROVIDE A DETAIL |
| SHOWING THE LOCATION OF THE CRYOGENIC EXHAUST PIPE |
| TERMINATIONS WITH ALL REQUIRED CLEARANCE DISTANCES |
| NOTED- SEE SECTION 501.3.1 FBC M. |
| |
| 7) M-201: PLEASE REVISE THE PLANS TO SHOW THE REQUIRED |
| MECHANICAL VENTILATION SYSTEM FOR THE MED GAS ROOM IN |
| ACCORDANCE WITH SECTION 510.1 AND 510.2 FBC M AND 414.3 |
| FBC B. THE EXHAUST SYSTEM SHALL BE SIZED TO OPERATE |
| CONTINUOUSLY AT A RATE OF 1.0 CFM PER SQ. FT.- SECTION |
| 60.3.2.5.3 FFPC-2017, AND THE DUCT SYSTEM SHALL EXTEND |
| DIRECTLY TO THE EXTERIOR OF THE BUILDING. PLEASE NOTE |
| THAT HAZARDOUS EXHAUST DUCTS THAT PENETRATE FIRE-RATED |
| WALL ASSEMBLIES SHALL BE ENCLOSED IN FIRE-RESISTANT |
| RATED CONSTRUCTION FROM THE POINT OF PENETRATION TO THE |
| OUTLET TERMINAL- SECTION 510.7.3 FBC M. |
| |
| 8) REPEAT COMMENT #10 FROM THE 1ST REVIEW: M-201, 202 & |
| 203: DUCT SMOKE DETECTORS ARE REQUIRED IN THE SUPPLY |
| AIR SYSTEMS OF EACH FCU IN COMPLIANCE WITH SECTION |
| 606.2.2 FBC M. PLEASE PROVIDE A SYMBOL AT EACH FCU TO |
| VERIFY COMPLIANCE. |
| |
| 9) REPEAT COMMENT #11 FROM THE 1ST REVIEW: M-204: |
| PROVIDE A DUCT SMOKE DETECTOR IN THE SUPPLY SYSTEMS OF |
| AHU- 1 & 2, AND DOAS- 1 & 2 PER SECTION 606.2.1 FBC M. |
| A) PLEASE REFER TO SECTIONS 606.4 AND 606.4.1 FBC M AND |
| PROVIDE FAN SHUTDOWN SEQUENCES. |
| |
| 10) REFER TO SECTIONS 406.5.2 AND 406.6.2 FBC B: THE |
| EAST SECTION OF THE PARKING GARAGE THAT IS BOUNDED BY |
| INTERIOR WALLS AND A CEILING IS CLASSIFIED AS ENCLOSED |
| AND REQUIRES MECHANICAL VENTILATION IN COMPLIANCE WITH |
| SECTIONS 404 AND 502.13 FBC M. PLEASE REVISE THE PLANS |
| ACCORDINGLY. |
| |
| 11) M-203: SECOND REQUEST FOR RETURN DUCT SIZES FOR |
| FCU-5 & 10. |
| |
| 12) THE DUCTLESS FAN COIL UNITS ARE NOT PERMITTED FOR |
| INSTALLATION IN THE INTERIOR EXIT STAIRWAYS IN |
| COMPLIANCE WITH SECTION 1023.5 & 1023.6 FBC B. |
| |
| PRINTED BELOW ARE COMMENTS 22-31 FROM THE 1ST REVIEW |
| THAT HAVE NOT BEEN ADDRESSED IN THE RESPONSE NARRATIVE |
| AND THE PLANS. |
| |
| 22) M-205: PROVIDE WIND LOAD ENGINEERING FOR |
| INSTALLATION OF ALL ROOFTOP MECHANICAL EQUIPMENT |
| INCLUDING THE CHILLERS, DOAS?S UNITS, AHU- 1 & 2, EF-1 |
| &2, H-1 & 2, VENT FLUES, AND THE CHILLED WATER PIPE |
| SUPPORTS- SECTION 301.15 FBC M. |
| |
| 23) M-701: PROVIDE EFFICIENCY RATINGS FOR THE DOAS-1 & |
| 2 UNITS IN THE SCHEDULE- TABLE C403.2.3(1) FBC EC. |
| |
| 24) M-701: THE EFFICIENCY RATING OF CH-1 AT 8.78 EER IS |
| DEFICIENT ACCORDING TO TABLE C403.2.3(7) FBC EC. |
| |
| 25) M-701: NO EFFICIENCY RATINGS HAVE BEEN PROVIDED FOR |
| THE MRI CH-2- TABLE C403.2.3(7) FBC EC. |
| |
| 26) M-701: ALTHOUGH VENTILATION CALCULATIONS HAVE NOT |
| BEEN PROVIDED, IT APPEARS BY THE EXHAUST RATE OF EF-1 |
| THAT AN ERV WILL BE REQUIRED FOR THE SYSTEM- SEE |
| SECTION C403.2.7 FBC EC. |
| |
| 27) CLARIFY IF THE ELEVATOR HOISTWAYS WILL BE VENTED |
| AND PROVIDE DETAILS. |
| |
| 28) PROVIDE UL TESTED AND APPROVED FIRESTOPPING |
| ASSEMBLIES FOR THE CHILLED WATER PIPING, CONDENSATE |
| PIPING, AND DUCTWORK. |
| |
| 29) INDICATE THE R-VALUE AND THICKNESS OF THE CHILLED |
| WATER PIPING INSULATION IN THE BUILDING AND ABOVE THE |
| ROOF- TABLE C403.2.10 FBC EC. |
| |
| 30) REQUIRED SUBMITTALS TO APPROVED BY THE EOR: |
| |
| A) FIRE SMOKE DAMPERS |
| B) FIRE DAMPERS |
| C) MOTORIZED DAMPERS |
| D) DUCT SMOKE DETECTORS |
| E) GENERATOR |
| F) PRE- MANUFACTURED ACCESS PANELS FOR AC UNITS AND |
| DAMPERS |
| G) WATER HEATERS AND VENT PIPING |
| H) O/A AND EXHAUST LOUVERS INCLUDING FL. PRODUCT |
| APPROVALS AND/OR MIAMI-DADE NOA'S |
| I) OR DUCTS & DIFFUSERS, & MRI DUCTS AND EXHAUST FANS |
| J) PIPE AND DUCT INSULATIONS |
| |
| 31) REFER TO SECTION 451.1.1- 451.1.5 AND CLARIFY IF |
| THE PROPOSED PLANS FOR THE AMBULATORY SURGICAL CENTER |
| HAS BEEN REVIEWED AND APPROVED BY ACHA. |
| |
| PLEASE NOTE THAT ADDITIONAL COMMENTS MAY OCCUR WHEN |
| CORRECTED PLANS AND SPECIFICATIONS ARE RESUBMITTED. |
| WHEN RESUBMITTING PLEASE PROVIDE A RESPONSE LETTER |
| ADDRESSING EACH ITEM ALONG WITH THE CITY RE-SUBMITTAL |
| FORM. ADDITIONALLY, PLEASE INSERT CORRECTED PLAN SHEETS |
| INTO THE SETS, REMOVE THE PREVIOUSLY REVIEWED SHEETS |
| AND MARK VOID ON THEM, AND KEEP THEM WITH THE |
| SUBMITTALS |
| |
| CHRISTOPHER L. COLE |
| MECHANICAL PLANS EXAMINER |
| 401 CLEMATIS STREET |
| WEST PALM BEACH FL 33401 |
| 561-805-6719 |
| [email protected] |
| |
| |
| |
| |
| |
| |
| |