2018-06-29 14:52:10 | 06/29/2018 1ST PLUMBING/GAS REVIEW **DENIED** WITH |
| COMMENTS. |
| |
| NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS |
| TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE |
| GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS. |
| |
| 1. SUBMIT MANUFACTURES SPECIFICATIONS FOR THE GENERATOR |
| AND MANUFACTURER'S SPECIFICATIONS FOR THE GENERATOR |
| SHALL BE ONSITE FOR FINAL GAS INSPECTION. THE GENERATOR |
| SHALL BE LISTED AND APPROVED. NFPA 58 SEC. 5.20.1. THE |
| GENERATOR SHALL MEET THE REQUIREMENTS OF UL 2200. 2017 |
| FBC FUEL GAS SEC.305.1. |
| 2. IS THE EXISTING STEAM GENERATOR THE ONLY APPLIANCE |
| ON THIS SYSTEM? WPB AMENDMENTS TO FBC SEC.107.2.1. |
| INFORMATION ON CONSTRUCTION DOCUMENTS. |
| 3. A SET OF PLANS HAS BEEN SUBMITTED THAT IS DRAWN IN |
| PENCIL. PLANS DONE IN PENCIL ARE UNACCEPTABLE AS THE |
| DRAWING CAN BE MODIFIED/CHANGED. I HAVE VOIDED IT AND |
| MADE A COPY AND PUT IT WITH THE OTHER SET. WPB |
| AMENDMENTS TO THE FBC SEC. 107.2.1.4 QUALITY OF |
| BUILDING PLANS. |
| 4. SUBMIT MANUFACTURER?S SPECIFICATIONS FOR THE |
| PRESSURE REGULATORS. REGULATORS INSTALLED ON THE |
| EXTERIOR OF THE BUILDING SHALL BE APPROVED FOR OUTDOOR |
| INSTALLATION. IF INSIDE THE GENERATOR PLEASE CLARIFY. |
| 2017 FBC FUEL GAS SEC.410.1. |
| 5. SUBMIT TWO COPIES OF THE SIZING TABLE AFTER PE THAT |
| IS USED IN THE DESIGN FOR THE GAS SYSTEM OR PLACE A |
| NOTE ON BOTH SETS OF PLANS LISTING THE SIZING TABLES |
| FROM GAS CODES OR ANOTHER STANDARD THAT WERE USED IN |
| THE DESIGN OF THIS SYSTEM, 2017 FBC FUEL GAS SEC. |
| 402.3. |
| 6. SHOW SHUTOFF VALVE SHALL BE INSTALLED IMMEDIATELY |
| AHEAD OF EACH MP REGULATOR AND GENERATOR, PLEASE SHOW |
| ON LAYOUT DESIGN, 2017 FBC FUEL GAS SEC. 409.4. |
| 7. IS THE NEW GENERATOR GOING TO THE EXISTING LOCATION |
| AND WILL IT COMPLY WITH NFPA 37, SECTION 4.1.4, ENGINES |
| LOCATED OUTDOORS OR MANUFACTURES SPECIFICATION, PLEASE |
| SHOW ON DRAWINGS IF APPLICABLE? |
| 8. THE IS AN APPLICATION FOR A 75 KW AND THE PLANS LIST |
| AN 80 KW, I ALSO SAW A TOWER GENERATOR UNDER THIS |
| ADDRESS, PLEASE CLARIFY. WPB AMENDMENTS TO THE FBC SEC. |
| 107.2.1 INFORMATION ON CONSTRUCTION DOCUMENTS. |
| |
| LUIS A. CRESPO |
| PLUMBING INSPECTOR / |
| PLUMBING PLAN REVIEW |
| AVAILABLE FROM 1:00 PM TO 4:00 PM |
| [email protected] |
| 561-805-6720 |
| |