Date |
Text |
2018-06-30 11:01:33 | 06/30/2018 1ST GAS REVIEW**DENIED** |
| |
| MASTER #17080170 SHOWS BOTH THE TANKLESS AND RANGE AS |
| ELEC.NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT |
| THIS TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE |
| GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS. |
| |
| 1) SHOW THE TYPE OF PIPE MATERIAL BEING INSTALLED, ALL |
| PIPE SIZES, AND THE CORRESPONDING EHD NUMBER OF THE |
| CORRUGATED STAINLESS STEEL TUBING |
| (IF APPLICABLE) FOR EACH PIPE SIZE. WPB AMENDMENTS TO |
| FBC SEC.107.2.1 |
| |
| 2) TYPE OF GAS (LP OR NATURAL).WPB AMEND. TO FBC SEC. |
| 107.2.1 |
| |
| 3) SUBMIT MANUFACTURER?S SPECIFICATION SHEETS / |
| INSTALLATION MANUAL FOR ALL GAS EQUIPMENT TO VERIFY |
| COMPLIANCE WITH STANDARDS NFPA 54, NFPA 58, AND |
| FBC-2017 FUEL GAS CODE SEC. 402.2, AND 301.3 OR 2017 |
| FBC-RES. SEC. G2404.3. GAS APPLIANCES SHALL BE LISTED |
| AND LABELED. THE INSTALLATION MANUALS FOR ALL GAS |
| APPLIANCES / EQUIPMENT SHALL BE ONSITE AT THE TIME OF |
| INSPECTION. FGC SEC.305.1, FBC-RES. SEC.G2408.1. |
| |
| 4) THE MASTER PLAN SHOW THE TANKLESS AT 2'. GAS MIN |
| DISTANCE AWAY FOR SOURCE OF IGNITION. SUBMIT TWO COPIES |
| OF A HOUSE PLAN SHOWING THE LOCATION OF THE TANKLESS |
| WATER HEATER AND THE LOCATION AND DISTANCE OF ANY |
| OPERABLE DOORS OR WINDOWS IN RELATION TO THE WATER |
| HEATER. THE LOCATION OF THE WATER HEATER SHALL COMPLY |
| WITH THE MANUFACTURER'S INSTALLATION INSTRUCTIONS. THE |
| HOUSE PLAN CAN BE HAND DRAWN. WPB AMEND. TO FBC SEC. |
| 107.2.1 |
| |
| 5) SUBMIT COMBUSTION AIR CALCULATIONS FOR THE ADDED GAS |
| APPLIANCES. WHERE COMBUSTION AIR IS PROVIDED BY THE |
| BUILDING?S MECHANICAL VENTILATION SYSTEM, THE SYSTEM |
| SHALL PROVIDE THE SPECIFIED COMBUSTION AIR RATE IN |
| ADDITION TO THE REQUIRED VENTILATION AIR. 2017 FBC-FUEL |
| GAS SEC.304.9.3 OR FBCR G2407.9.3. |
| |
| 6) SUBMIT TWO COPIES OF THE APPLICABLE SIZING TABLES |
| USED TO SIZE THE GAS SYSTEM OR PLACE A NOTE ON THE |
| PLANS/DRAWINGS SPECIFYING WHICH SIZING TABLE(S) FROM |
| THE GAS CODE OR OTHER STANDARD THAT WERE USED IN THE |
| DESIGN OF THIS GAS SYSTEM. REFER TO THE 2017 FBC-FUEL |
| GAS SECS. 401.4, 401.8, 402.3, AND TABLES 402.4 (1) |
| THRU 402.4 (37) OR 2017 FBC-RES. SEC. G2413.3, G2412.8, |
| G2413.1, G2413.2, & G2413.3 |
| |
| 7) VALUE. THE TOTAL VALUE MUST INCLUDE THE COST OF THE |
| TANKLESS AND RANGE GOING FROM ELC TO GAS. A REVISION ON |
| MASTER #17080170 WILL BE REQUIRED FOR ELC. |
| |
| TIM HUNT |
| PLUMBING INSPECTOR / PLUMBING PLAN REVIEWER |
| CITY OF WEST PALM BEACH DEVELOPMENT SERVICES DEPARTMENT |
| BUILDING DIVISION |
| 561-805-6695 |
| [email protected] |
| |
| |