2018-06-02 04:34:16 | 1) ) THE PLANS INDICATE AN EXISTING GAS METER. THE BTU |
| LOAD OF THE EXISTING GAS SYSTEM MUST BE ADDED INTO THE |
| TOTAL BTU LOAD ON THE SYSTEM TO ENSURE THE EXISTING |
| SYSTEM IS PROPERLY SIZED. IF UNDERSIZED, THE EXISTING |
| SYSTEM MUST BE REDONE TO ENSURE A SAFE OPERATING |
| SYSTEM. SUBMIT A GAS PIPING RISER DIAGRAM THAT SHOWS |
| THE TYPE OF EXISTING APPLIANCE, THE BTU LOAD OF EACH |
| APPLIANCE, THE PIPE SIZE AND TYPE OF PIPE TO EACH |
| APPLIANCE, AND THE DISTANCE OF THE LONGEST LENGTH OF |
| PIPING FROM THE POINT OF DELIVERY TO THE MOST REMOTE |
| OUTLET AND THE LOAD OF THE SECTION. NOTE: IF THE |
| EXISTING SYSTEM IS LESS THAN A 2 PSI SYSTEM AND THE |
| SYSTEM PRESSURE IS INCREASED TO 2 PSI, A LINE PRESSURE |
| REGULATOR IS REQUIRED AT ALL THE EXISTING APPLIANCES. |
| FGC SECS. 401.4, 401.8, 402.1, 402.2, 402.3 OR FBCR |
| SECS.G2412.4, G2412.8, G2413.1, G2413.2, G2413.3. |
| 2) THE GAS PLAN SHOWS A LESS THAN 2 PSI SYSTEM SO WHY |
| IS THERE A REGULATOR AT THE GENERATOR? CLARIFY. |
| 3) SHOW THE TYPE OF PIPE AND PIPE SIZE AT THE OUTLET OF |
| THE GAS METER. |
| 4) SUBMIT THE MANUF. SPECIFICATIONS FOR THE GAS FLEX |
| CONNECTOR FOR THE GENERATOR.THE FLEX CONNECTOR SHALL BE |
| APPROVED TO FLOW THE MAXIMUM BTU LOAD FOR THE |
| GENERATOR. 2017 FBCR SEC. G2422.1 (8). |
| 5) THE TRACER WIRE OR TAPE SHALL NOT BE IN DIRECT |
| CONTACT WITH |
| THE POLYAMIDE OR POLYETHYLENE PIPE PER NFPA-15 |
| SEC.6.9.4.6. |
| 6) SEDIMENT TRAP IS REQUIRED PER 2017 FBC - FUEL GAS |
| SEC. 408.4. |
| |
| TIM LARGE |
| CHIEF PLUMBING INSPECTOR |
| PLUMBING PLAN REVIEW |
| 561-805-6692 |
| |
| |