Date |
Text |
2018-11-26 14:42:36 | 2ND REVIEW FBC-2017 MECHANICAL |
| PERMIT #18050277 |
| 11/26/18 |
| |
| CODES IN EFFECT: |
| |
| FBC B- FLORIDA BUILDING CODE SIXTH EDITION 2017 |
| FBC M- FLORIDA MECHANICAL CODE SIXTH EDITION 2017 |
| FBC EC- FLORIDA ENERGY CONSERVATION CODE SIXTH EDITION |
| 2017 |
| FBC FG- FLORIDA FUEL GAS CODE SIXTH EDITION 2017 |
| FS- FLORIDA STATUTES |
| FAC- FLORIDA ADMINISTRATIVE CODE |
| WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH |
| EDITION 2017 |
| |
| PLAN REVIEW RESULTS: DENIED. |
| |
| 1) A-1.0.05, A-2.0.02, A-5.0.01, A-6.0.00, & M-1.3.01: |
| THE EXTERIOR DOORS AND INTERIOR DOORS ENCLOSING THE |
| POOL EQUIPMENT STORAGE AND ELECTRICAL ROOMS SHALL BE |
| FIRE-RATED PER SECTION 707.6 FBC B. ( CORRECTED |
| ARCHITECTURAL PLANS NOW SHOW THE EXTERIOR WALLS TO BE |
| 3HR FIRE-RATED). FIRE DAMPERS SHALL BE PROVIDED FOR THE |
| MAKEUP AIR LOUVERS ON THE EAST WALLS, AND FOR THE AC-1 |
| OUTDOOR AIR INTAKE LOUVER, THE FOOD PREP EXHAUST |
| OUTLET, AND THE EXHAUST HOOD MAKEUP AIR INLET- SECTION |
| 607.5.2 FBC M. |
| |
| 2) SHEET M-1.3.01: THE STAINLESS STEEL EXHAUST DUCKWORK |
| IN THE POOL EQUIPMENT STORAGE ROOM IS NOT IN COMPLIANCE |
| WITH SECTION 510.9 FBC M WHICH REQUIRES THE DUCT TO BE |
| G90 GALVANIZED OR NON-METALLIC MATERIALS THAT EXHIBIT A |
| FLAME SPREAD/SMOKE-DEVELOPED INDEX OF 25/50. |
| |
| 3) M-1.3.01: SUBMIT MANUFACTURER'S SPECIFICATIONS FOR |
| EF-1 WITH AN APPROVAL STAMP BY THE ENGINEER OF RECORD. |
| THE SPECS SHALL INDICATE THE FAN HAS BEEN TESTED FOR |
| USE IN CONVEYING CORROSIVE OR HAZARDOUS EXHAUST FUMES- |
| SECTION 304.1 FBC M. A) CLARIFY THE LOCATION OF THE |
| FAN- ABOVE OR BELOW THE CEILING. IF LOCATED ABOVE THE |
| CEILING PROVIDE AN ACCESS PANEL FOR SERVICE AND |
| REPLACEMENT- SECTION 306.1 FBC M. |
| |
| 4) A-2.0.02 & M-1.3.01: AS INDICATED BY NOTE #6 ON |
| M-1.3.01 PLEASE SHOW THE EXACT LOCATION OF THE EF-1 |
| EXHAUST OUTLET TO VERIFY COMPLIANCE WITH SECTION |
| 501.3.1(2) FBC M. (PLEASE NOTE THIS OUTLET SHALL NOT BE |
| PROTECTED WITH A FIRE DAMPER- SECTION 510.6.7 FBC M). |
| |
| 5) M-1.3.01: COMMENT #3(E) FROM THE 1ST TREVIEW STILL |
| EXISTS- PLEASE SUBMIT SPECS FOR THE CHEMICAL TANKS IN |
| THE POOL EQUIPMENT STORAGE ROOM. |
| |
| 6) COMMENT #2 FROM THE 1ST REVIEW REQUESTING EVIDENCE |
| OF ENERGY EFFICIENCY COMPLIANCE WAS NOT ADDRESSED- THE |
| PROPOSED BUILDING SHALL BE IN COMPLIANCE WITH THE FBC |
| EC. REFER TO SECTIONS C101.2 -SCOPE AND C401.2 |
| APPLICATION (COMPLIANCE PATHS). PROVIDE A COMPLIANCE |
| SUBMITTAL C101.5.1- COMPLIANCE MATERIALS. |
| |
| 7) COMMENT #6 FROM THE 1ST REVIEW STILL EXISTS. IF THE |
| REQUESTED WIND LOAD ENGINEERING IS TO BE A DEFERRED |
| SUBMITTAL PLEASE INDICATE THAT ON THE CORRECTED PLANS, |
| OR IN THE RESPONSE NARRATIVE. |
| |
| 8) COMMENT #8 FROM THE 1ST REVIEW HAS NOT BEEN |
| COMPLETELY ADDRESSED. WHEN USING A MECHANICAL |
| VENTILATION SYSTEM TO PROVIDE COMBUSTION AIR, THE |
| SYSTEM SHALL PROVIDE THE SPECIFIED COMBUSTION RATE IN |
| ADDITION TO THE REQUIRED VENTILATION AIR- SECTION |
| 304.9.3 FBC FG. BASED ON THE AIR BALANCE CALCULATION ON |
| M-1.3.01, IT APPEARS THAT ALL VENTILATION AIR FROM AC-1 |
| WILL BE UTILIZED AS MAKEUP AIR FOR THE EXHAUST SYSTEMS. |
| |
| 9) M-1.3.01: THE LOCATION OF THE MAKEUP AIR OPENING FOR |
| THE EXHAUST HOOD SHALL BE A MINIMUM 3' AWAY FROM THE |
| FOOD PREP EXHAUST OUTLET- SECTION 501.3.1 (3) FBC M. |
| |
| |
| WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT |
| CORRECTED PLAN SHEETS INTO THE SETS, REMOVE THE |
| PREVIOUSLY REVIEWED SHEETS AND MARK VOID ON THEM, AND |
| KEEP THEM WITH THE SUBMITTALS |
| |
| CHRISTOPHER L. COLE |
| MECHANICAL PLANS EXAMINER |
| 401 CLEMATIS STREET |
| WEST PALM BEACH FL 33401 |
| 561-805-6719 |
| [email protected] |
| |