2018-04-10 16:13:21 | 1ST REVIEW FBC-2017 MECHANICAL, EXISTING BUILDING, |
| ENERGY CONSERVATION CODES |
| PERMIT #18021224 |
| 4/10/2018 |
| |
| PLAN REVIEW RESULTS: DENIED. |
| |
| 1) PROVIDE AC COOLING AND HEATING CALCULATIONS FOR THE |
| NEW AND RELOCATED AC SYSTEMS- SECTION C403.2.1 FBC-17 |
| ENERGY CONSERVATION. PLEASE NOTE THAT BECAUSE THIS IS A |
| CHANGE OF OCCUPANCY WITH NEW HEAT PRODUCING BREWERY |
| EQUIPMENT, IT IS NECESSARY TO PROVIDE NEW HEAT LOAD |
| CALCS TO VERIFY SYSTEM SIZING. |
| |
| 2) M-1: PROVIDE AN UP-TO-DATE SURVEY THAT INDICATES THE |
| PROPERTY LINE OR RIGHT OF WAY ON THE WEST SIDE OF THE |
| BUILDING THE M-1 PLAN SHOWS THE AC CONDENSERS, THE |
| CHILLER, AND THE O/A INTAKES ON THAT SIDE OF THE |
| BUILDING. PLEASE NOTE THAT O/A INTAKES SHALL BE LOCATED |
| NOT LESS THAN 10' FROM LOT LINES PER SECTION 401.4. |
| |
| 3) M-1 & M-2: INDICATE THE TYPE AND SIZE OF THE GLYCOL |
| PIPING, THE TYPE AND THICKNESS OF THE PIPE INSULATIONS, |
| AND THE SPACING OF THE PIPE SUPPORT STANDS. |
| |
| 4) M-2: PROVIDE AN EQUIPMENT SCHEDULE FOR THE CHILLER |
| AND SUBMIT MANUFACTURER'S SPECIFICATIONS. |
| |
| 5) M-2: PROVIDE THE OUTSIDE AIR CFMS FOR AHU-2 & 3 IN |
| THE EQUIPMENT SCHEDULE. |
| |
| 6) M-1 & M-2: PROVIDE THE WIND DESIGN CRITERIA USED TO |
| DETERMINE THE PRESSURES AND ANCHORING AND FASTENING |
| METHODS FOR ALL OF THE EXTERIOR MECHANICAL EQUIPMENT |
| AND COMPONENTS- SECTION 301.15 |
| |
| 7) M-1: PROVIDE COMBUSTION AIR CALCULATIONS FOR THE |
| BREWHOUSE TANK- SECTION 304 FBC-17 FUEL GAS. |
| |
| 8) SUBMIT MANUFACTURER'S SPECIFICATIONS AND |
| INSTALLATION INSTRUCTIONS FOR THE BREWERY TANKS WITH |
| APPROVAL STAMPS BY THE DESIGNER OF RECORD. REFER TO |
| SECTION1003.1 FBC-17 MECHANICAL: IF THE TANKS ARE |
| DETERMINED TO BE CLASSIFIED AS PRESSURE VESSELS, THEY |
| SHALL BE CONSTRUCTED AND CERTIFIED IN ACCORDANCE WITH |
| ASME BOILER AND PRESSURE VESSEL CODE. |
| |
| 9) IDENTIFY AND LABEL ALL THE BREWERY TANKS AND |
| EQUIPMENT SHOWN ON THE PLAN PROVIDE A PROCESS PIPING |
| PLAN AND ISOMETRIC DRAWING. |
| |
| 10) THE PROPOSED OCCUPANCY SHALL BE IN COMPLIANCE WITH |
| SECTION C505.1 FBC-17 ENERGY CONSERVATIONS. PLEASE |
| PROVIDE A COMPLIANCE REPORT AS REQUIRED BY SECTION |
| C101.5. |
| |
| 11) PROVIDE A FLORIDA PRODUCT APPROVAL OR MIAMI-DADE |
| NOA FOR THE O/A LOUVERS- RULE 9N-3 FAC. |
| |
| CHRISTOPHER L. COLE |
| MECHANICAL PLANS EXAMINER |
| 401 CLEMATIS STREET |
| WEST PALM BEACH FL 33401 |
| 561-805-6719 |
| [email protected] |
| |