2018-02-28 17:47:04 | 02/28/2018 1ST PLUMBING REVIEW**DENIED** |
| |
| |
| A STOP WORK ORDER WAS ISSUED ON 01/17/2018 DURING THE |
| DEMO OF THE BATH TUB. BOTH OWNER AND PLUMBERS ON-SITE |
| HAD BEEN ADVISED TO CEASE ALL WORK UNTIL PERMIT WAS |
| ISSUED AND APPROVED INSPECTIONS HELD. THIS WAS IGNORED |
| AND THE JOB WAS FOUND TO BE COMPLETED DURING A STATUS |
| CHECK OF THE STOP WORK ORDER THAT WAS PERFORMED ON |
| 02/22/2018 COMFIRMED BY THE OWNER.1 OF THE FOLLOWING 2 |
| OPTIONS BELOW MUST HAPPEN IN ORDER FOR THIS PERMIT TO |
| BE ISSUED BY 03/12/2018 OR THE VIOLATION WILL BE |
| FORWARDED TO THE SPECIAL MAGISTRATE FOR A HEARING. |
| |
| 1) THE REMOVAL OF ALL MATERIALS DOWN TO THE BARE WALLS |
| SAME AS WHICH THE INSPECTOR ISSUED THE STOP WORK ORDER. |
| |
| 2) A SIGN LETTER FROM YOU ( GEORGE BEYS) ACKNOWLEDGING |
| THE WORK HAS BEEN PERFORMED WITH OUT PERMITS AND |
| BENEFIT OF CITY OF WEST PALM BEACH INSPECTION AS |
| REQUIRED BY THE FLORIDA BUILDING CODE AND TAKING FULL |
| RESPONSIBILITY OF THE ENTIRE INSTALL OF ALL COMPONENTS |
| OF THIS REMODEL. A SIGED LETTER FROM THE OWNER (MR. |
| ROSE) ACKNOWLEDGE HE IS AWARE OF THE CURRENT EVENTS AND |
| ACCEPTS THIS COURSE OF ACTION. A MIN OF 2 HOLES CUT |
| INTO THE DRYWALL IN LOCATIONS OF THE INSPECTORS CHOICE |
| TO ALLOW SOME INSPECTION TO BE PERFORMED. 2- COPIES WET |
| SIGNED FROM EACH |
| |
| MUST COMPLY WITH 1 OF THE 2 BY 03/12/2018 OR THE |
| VIOLATION WILL BE FORWARDED TO THE SPECIAL MAGISTRATE |
| FOR A HEARING |
| |
| |