2018-02-13 18:44:00 | RESIDENTIAL (R3) ALTERATION, BUILDING REVIEW COMMENTS. |
| CODE: FBC 6TH EDITION (2017). |
| |
| 1- INSTALLATION SCHEDULE SUBMITTED: |
| A) CALCULATED DESIGN PRESSURES ARE INCORRECT. ALSO, THE |
| DESIGN CRITERIA TAKEN INTO CONSIDERATION DOESN'T MATCH |
| ACTUAL BUILDING. THERE IS INFORMATION IN THE DESIGN |
| CRITERIA THAT DOESN'T SEEM TO APPLY FOR THIS PROJECT. |
| PROVIDE COMPLETE SIGNED AND SEALED WIND LOAD |
| CALCULATIONS THAT CORRESPOND TO THE ACTUAL BUILDING OR |
| USE THE TABLE R301.2(2) OF THE FBC-RESIDENTIAL, 6TH |
| EDITION (2017) TO OBTAIN THE CORRESPONDING DESIGN |
| PRESSURES. NOTE: IF USING THE FBC TABLE TAKE INTO |
| CONSIDERATION THAT DESIGN PRESSURES NEED TO BE ADJUSTED |
| TO BUILDING EXPOSURE "C" AND THE ACTUAL BUILDING MEAN |
| ROOF HEIGHT. SEE TABLE R301.2(3) FBC-RESIDENTIAL. |
| |
| B) REVISE ANCHOR SPACING BASED ON THE REVISED DESIGN |
| PRESSURES. COORDINATE WITH ITEM #1(A) ABOVE. SEC. |
| R301.1 FBC-RESIDENTIAL. |
| |
| C) INSTALLATION SCHEDULE IS MISSING THE GLASS |
| SEPARATION DISTANCE. SEC. R301.1 FBC-RESIDENTIAL. |
| |
| D) SECTION OR TYPE "A" SPECIFIED ON THE TOP CONNECTION |
| IS FOR POURED CONCRETE SUBSTRATE ONLY NOT FOR WOOD |
| FRAME AS SHOWN ON SCHEDULE SUBMITTED. SEE DETAIL "A" ON |
| SHEET 6 OF 20 AND REVISE AS REQUIRED. SEC. 107.2.1 CITY |
| AMENDMENTS. |
| |
| E) SECTION OR TYPE "U" SPECIFIED ON THE TOP CONNECTION |
| IS FOR WOOD SUBSTRATE ONLY NOT FOR CONCRETE AS SHOWN ON |
| SCHEDULE SUBMITTED. SEE DETAIL "U" ON SHEET 17 OF 20 |
| AND REVISE AS REQUIRED. SEC. 107.2.1 CITY AMENDMENTS. |
| |
| F) CLARIFY WHAT'S CONNECTION TYPE 3/8"WM AND CONNECTION |
| TYPE ADJ SILL?. SEC. 107.2.1 CITY AMENDMENTS. |
| |
| G) TOP CONNECTION USING SECTION OR TYPE "U" DETAIL |
| NEEDS TO SPECIFY LAG SCREWS NOT TAPCONS. SEE DETAIL "U" |
| AND REVISE AS REQUIRED. SEC. R301.1 FBC-RESIDENTIAL. |
| |
| H) PROVIDE COMPLETE SPECIFICATIONS FOR TYPE OF ANCHOR |
| TO BE USED. SPECIFY ANCHOR DIAMETER AND LENGTH TO |
| VERIFY COMPLIANCE WITH THE PRODUCT APPROVAL |
| REQUIREMENTS FOR MINIMUM EMBEDMENT. SEC. R301.1 |
| FBC-RESIDENTIAL. |
| |
| I) CLARIFY WHAT ARE THE "ALLOWABLE PRESSURES" SPECIFIED |
| NEXT TO THE DESIGN PRESSURES STAND FOR AND, CLARIFY |
| WHERE ARE THESE PRESSURES TAKEN FROM?. COORDINATE WITH |
| ITEM #1(A) ABOVE. SEC. 107.2.1 CITY AMENDMENTS. |
| |
| IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT |
| JULIO GOMEZ |
| COMMERCIAL COMBINATION PLANS EXAMINER |
| DEVELOPMENT SERVICES DEPARTMENT |
| BUILDING DIVISION |
| (561)805-6712 |
| [email protected] |